4 Lessons Contractors Can Learn From The COVID-19 Crisis
May 25, 2020 —
Patrick Hogan - Handle.comAt the start of 2020, the industry outlook in construction was positive. Many contractors were optimistic about what the year had in store for construction businesses in terms of profit, expansion of operations, and even payment issues. That was until the COVID-19 pandemic put a wrench in everyone’s business plans.
There’s no question about how huge the impact of the novel coronavirus crisis is on business operations. With the federal and state governments implementing strict measures to slow down the spread of COVID-19, construction businesses are experiencing significant delays and disruptions in their operations. Because of the lockdowns and stay-at-home orders, many construction projects are forced to postpone operations or, worse, cancel them altogether.
Nevertheless, there are lessons in the COVID-19 pandemic that contractors can learn. Here are some of them.
1. Contractors need to be proactive in meeting preliminary notice requirements
Cash is tight in times of crisis. As the economy comes to a standstill, construction businesses will need to deal with decreasing profits. They may even have to dip into their own cash reserves to cover fixed expenses and their employees’ salaries.
In times like this, it is crucial that contractors perform due diligence in protecting their right to get paid. The first step in doing so is to prepare
preliminary notices. These notices are an important step in the mechanics lien process and without them, chances contractors will not be able to recover the unpaid compensation for the materials they furnished and services they rendered.
2. Force majeure provisions are crucial parts of a contract
The novel coronavirus pandemic has highlighted the importance of force majeure provisions in construction contracts. Before the COVID-19 crisis hit business operations, force majeure provisions were typically considered as simple boilerplate clauses. This means they were just there as a standard part of contracts.
However, the same force majeure clauses, as well as impossibility of performance provisions, have become crucial in the current crisis. As many construction businesses experience difficulties with their operations, they may not be able to fulfill their contractual responsibilities. The said clauses can give contractors a much-needed reprieve.
As the current crisis continues, contractors should review contracts as these provisions can give them more time to finish the job. And in the hopefully near future when the crisis ends, business owners should review the contract creation process and ensure that these clauses included in contracts will be able to address the impact of situations similar to COVID-19.
3. Having solid internal communication is crucial
There’s a lot of uncertainty with the COVID-19 situation. With work operations temporarily stopping, the circumstances can be quite stressful for employees. There will be doubts and fears within your workforce on whether work will be back to normal as soon as possible or not.
Keeping your workforce well-informed and trusting of your organization is crucial, especially in this time of uncertainty. That is why it is paramount that you have a solid internal communication infrastructure to disseminate information about the current work situation and the next steps that the business will take. In addition, only through proper employee communication can the implementation of social distancing and hygiene measures be effective.
4. Contractors can benefit from flexible work arrangements
As the coronavirus crisis has made it necessary for everyone to stay at home, construction businesses should look for ways to continue operations. Expanded work arrangements such as work-from-home setups may just be the solution.
Of course, most of the physical work that is needed to be done on-site will be impossible to do at home, but office-based functions such as sales, client relations, design, and administrative roles can still continue. This can even have additional benefits to productivity and health. And when the crisis is over, business owners should consider incorporating these work arrangements into their operations permanently.
The COVID-19 crisis is not showing any sign of stopping soon, and even when it ends, it will take quite a long time before we can be back to business as usual. As the crisis continues, however, business owners should take the situation as a learning experience.
Once the COVID-19 crisis is over, it will take a long time for things to go back to normal. In fact, things may not end up going back to the way they were before and businesses will need to adapt to the new normal. However the situation evolves, business owners should take this opportunity to learn new things and maintain resilience in trying times.
About the Author:
Patrick Hogan is the CEO of Handle.com, where they build software that helps contractors, subcontractors, and material suppliers with late payments. Handle.com also provides funding for construction businesses in the form of invoice factoring, material supply trade credit, and mechanics lien purchasing.
Read the court decisionRead the full story...Reprinted courtesy of
Fire Tests Inspire More Robust Timber Product Standard
March 22, 2018 —
Nadine M. Post– ENRBased on recent fire test results, mass timber groups have adjusted product certification standards to require the use of cross-laminated timber with structural adhesives tested to demonstrate better fire performance.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, Engineering News-RecordMs. Post may be contacted at
postn@enr.com
Partner John Toohey and Senior Associate Sammy Daboussi Obtain a Complete Defense Verdict for Their Contractor Client!
December 11, 2023 —
Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to share that Newport Beach attorneys John Toohey and Sammy Daboussi obtained a complete defense verdict after years-long litigation in favor of their concrete contractor client.
This lawsuit arises from a claim made by Plaintiff for construction defects in a high-end single-family home. Our client was hired to perform concrete work on the foundations of the home. It was alleged that the home’s foundation was incorrectly built. It was further alleged that the construction defects/errors led to delays and substantial expenses. We argued that our client relied on the certifications provided to them by design professionals and the City. We further argued that our client, like any reasonable concrete/foundation subcontractor, has no responsibility or obligation, contractual or otherwise, to review and recheck the work completed by a licensed professional.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
The 2019 ISO Forms: Additions, Revisions, and Pitfalls
February 24, 2020 —
Richard W. Brown, Michael V. Pepe & Janie Reilly Eddy - Saxe Doernberger & Vita, P.C.The Insurance Services Office, Inc. (ISO) issued several new and revised endorsements for use with Commercial General Liability (CGL) coverage forms, which became effective December 1, 2019, in most jurisdictions. The new ISO endorsements include several notable changes that Policyholders should be aware of, including revisions to existing Additional Insured (AI), Primary and Noncontributory, and Waiver of Subrogation endorsements, as well as a number of new AI and other endorsement forms. A summary of the more significant elements of new ISO endorsements is provided below.
NEW ISO FORMS
- New AI Endorsements - Automatic Status for Completed Operations
For Contractors, Owners and other construction industry stakeholders, there are two new AI endorsements of note, CG 20 39 12 19 – Additional Insured – Owners, Lessee or Contractors – Automatic Status when Required in Written Construction Agreement with You (Completed Operations) and CG 20 40 12 19 – Additional Insured – Owners Lessees or Contractors – Automatic Status for Other Parties when Required in Written Construction Agreement (Completed Operations). AI coverage for Completed Operations is generally provided under form CG 20 37, which requires each additional insured to be listed in the endorsement schedule. The new ISO endorsements automatically extend AI status for Completed Operations without having to specifically identify each additional insured, thereby mirroring current AI endorsements that confer automatic AI status for Ongoing Operations (e.g. CG 20 33 and CG 20 38). Thus, the CG 20 39 and CG 20 40, correspond with CG 20 33 (ongoing operations), and CG 20 38 (ongoing operations), respectively, to extend AI coverage for Completed Operations.
Reprinted courtesy of Saxe Doernberger & Vita, P.C. attorneys
Richard Brown,
Michael V. Pepe and
Janie Reilly Eddy
Mr. Brown may be contacted at rwb@sdvlaw.com
Mr. Pepe may be contacted at mvp@sdvlaw.com
Ms. Eddy may be contacted at jre@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Protect Your Right To Payment By Following Nedd
August 03, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogIn order to preserve your right to payment, you must satisfy the contractual requirements supporting a change order for the increased costs or time due to the delay. The key to the successful presentation of change order claims is educating your team on the following:
1. NOTICE
- Review the change order and notice provisions of your contracts. Make your contract searchable and insert the term “Noti” and look for the items listed below.
- Who: Check the designated representative for notice.
- It may not be the project manager.
- Confirm who can authorize the change order.
- Is owner approval required?
- Ensure that the party approving the change order has authority to do so.
- What: Check for specific information required by the contract.
- Provide ALL information available.
- If certain information is not yet available, state that the information will be provided when available.
- Reserve all rights to amend and submit additional information.
- Request both an increase to the Contract Sum and Contract Time.
- Make the request even if you do not believe the delay or time necessary will cause a significant impact.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com
Connecting IoT Data to BIM
September 04, 2018 —
Aarni Heiskanen - AEC BusinessInternet of Things sensors and IoT-capable devices provide a huge amount of data from buildings. To make this data useful and usable for research, Aalto University is developing and testing a service that links IoT with building information models, BIMs.
“The idea to start an experiment on linking IoT with BIM at the Otaniemi campus originated from discussions we had within professor Martti Mäntylä’s Aalto campus IoT group. We realized that several small research projects were simultaneously testing IoT here. So we decided to create a framework for sharing information between the projects,” says Seppo Törmä, CEO of VisuaLynk.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Client Alert: Service Via Tag Jurisdiction Insufficient to Subject Corporation to General Personal Jurisdiction
August 27, 2014 —
R. Bryan Martin and Kristian B. Moriarty - Haight Brown & Bonesteel LLPIn Martinez v. Aero Caribbean (No. 3:11-cv-03194-WHA, filed 8/21/2014), the United States Court of Appeals for the Ninth Circuit held service of process on a corporation's officer, within the forum state, does not establish general personal jurisdiction over the corporation unless the corporation's contacts with the forum render it essentially at home in the state.
Decedent, Lorenzo Corazon Mendoza, was traveling by airplane when the plane crashed, killing everyone aboard. Defendant Avions De Transport Régional (ATR) manufactured the airplane that crashed. Plaintiffs Lorenzo Martinez, Eliezer Martinez, Eliu Mendoza and Gloria Montes (Plaintiffs) filed suit against ATR as heirs of decedent.
ATR is a business entity organized under French law with its principal place of business in France. It is not licensed to do business in California, and it has no office or other physical presence there. It has purchased parts from California suppliers, sent representatives to California to promote its business, and advertised in trade publications available in California. It has also sold airplanes to a California corporation. Empire Airlines flies from Santa Barbara to Ontario using ATR planes on a regular basis; however, Empire Airlines purchased the ATR planes secondhand from third parties, and never directly from ATR. At the time of the crash, ATR North America (a wholly owned subsidiary of ATR) had its headquarters in Virginia, and has since relocated to Florida.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Kristian B. Moriarty, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com; Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “That’s Not How I Read It”
June 05, 2023 —
Daniel Lund III - LexologyA general contractor seeking to litigate with its subcontractor concerning a construction project in Indiana found itself fighting in court against assertions by the sub that arbitration of the dispute was required.
The GC was already in litigation in federal court with the project owner. The GC filed a third-party demand against the sub, which was met with a motion to stay and to compel arbitration.
At the crux of the sub’s argument was this clause in its subcontract: “Subcontractor agrees that the dispute resolution provisions of the Prime Contract between [GC] and Owner, if any, are incorporated by reference as part of this Subcontract so as to be binding as to disputes between Subcontractor and [GC] that involve, in whole or in part, questions of fact and/or law that are common to any dispute between [GC] and Owner or others similarly bound to such dispute resolution procedures... ."
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com