Fifth Circuit: Primary Insurer Relieved of Duty to Defend Without Release of Liability of Insured
March 02, 2020 —
Bethany L. Barrese & Ashley McWilliams - Saxe Doernberger & Vita, P.C.In Aggreko, LLC v. Chartis Specialty Ins. Co.,1 the Fifth Circuit affirmed a decision by the Texas District Court and held that a Covenant Not to Execute constituted a “settlement” sufficient to exhaust policy limits and terminate a primary insurer’s duty to defend.
This case arose out of a wrongful death suit filed by the parents of James Brenek II (“Brenek”). In 2014, Brenek was fatally electrocuted by an electrically energized generator housing cabinet while performing work on a rig in Texas for Guichard Operating Company, LLC (“Guichard”), a Louisiana-based drilling subcontractor. Guichard had leased the generator from Aggreko, LLC (“Aggreko”). A rental agreement between Guichard and Aggreko required Guichard to maintain commercial general liability insurance during the lease period and list Aggreko and the rig owner, Rutherford Oil Corporation (“Rutherford”), as additional insureds under
the policy.
Guichard’s primary insurance carrier, The Gray Insurance Company (“Gray”), agreed to defend and indemnify Aggreko and Rutherford in the wrongful death suit. The Gray policy had a limit of $1,000,000, subject to a $50,000 self-insured retention.
Reprinted courtesy of
Bethany L. Barrese, Saxe Doernberger & Vita, P.C. and
Ashley McWilliams, Saxe Doernberger & Vita, P.C.
Ms. Barrese may be contacted at blb@sdvlaw.com
Ms. McWilliams may be contacted at amw@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Not Remotely Law as Usual: Don’t Settle for Delays – Settle at Remote Mediation
May 25, 2020 —
Victor J. Zarrilli, Robert G. Devine & Michael W. Horner - White and Williams LLPThe emergence and rapid spread of COVID-19 has created extraordinary circumstances that have significantly impacted how we go about living, working and interacting with one another. The practice of law is no exception.
While most cases have been postponed and some extended indefinitely, the issues and disputes that first triggered the litigation remain. In fact, the burdens created by social distancing and other responses to the COVID-19 outbreak have served to only increase these disputes and create an urgent need in some for quick resolution.
In our previous article, we summarized some of the best practices that should be applied when taking and defending depositions in a remote, virtual setting. That technology can also offer the same benefits for alternative dispute resolutions. If planned properly, the use of technology allows remote mediations to be conducted as seamlessly as in-person mediations and, in some circumstances, affords additional benefits that can achieve the best possible resolution for all sides.
This article summarizes the opportunities technology has created by which parties can attempt to resolve their disputes through alternative dispute resolution methods, even in a time of social distancing.
Reprinted courtesy of White and Williams LLP attorneys
Victor J. Zarrilli,
Robert G. Devine and
Michael W. Horner
Mr. Zarrilli may be contacted at zarrilliv@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Horner may be contacted at hornerm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Protecting Expert Opinions: Lessons Regarding Attorney-Client Privilege and Expert Retention in Construction Litigation
August 19, 2024 —
David McLain - Higgins, Hopkins, McLain & Roswell, LLCThe Hill Hotel Owner LLC v. Hanover Insurance Company case has garnered attention due to its implications on the scope of attorney-client privilege in construction litigation. This blog post delves into the project’s background, the ensuing litigation, and the intricate work undertaken by attorneys and experts, highlighting the potential pitfalls associated with assumptions about privilege protections.
Background of the Project
Hill Hotel Owner LLC initiated a construction project in Boulder, Colorado, which included building a basement-level parking garage with an 18” thick concrete slab floor. The project utilized “void form,” a cardboard underlayment intended to create a gap between the foundation and the underlying soil. Unfortunately, the void form became wet and collapsed under the weight of the fresh concrete, causing considerable damage, and necessitating millions of dollars in remediation costs.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
In Midst of Construction Defect Lawsuit, City Center Seeks Refinancing
October 02, 2013 —
CDJ STAFFThe owners of the City Center complex in Las Vegas are going through with a refinancing of their $1.8 of debt while they still seek to demolish the Harmon Tower. The cost of building City Center was $8.5 billion, making it the most expensive development on the Las Vegas strip. Unfortunately for the owners, the Harmon Tower isn’t the only empty space in the complex.
MGM Resorts is currently in the midst of a construction defect lawsuit against the builder of the Harmon Tower. The judge in the case has given a go-ahead to tear down the building.
Read the court decisionRead the full story...Reprinted courtesy of
Arizona Supreme Court Confirms Eight-Year Limit on Construction Defect Lawsuits
July 18, 2011 —
CDJ STAFFActing on the case of Albano v. Shea Homes Ltd. Partnership, the Arizona Supreme Court has ruled that Arizona’s eight-year statute of repose applies. The case was referred to the court by the Ninth Circuit Court of Appeals which had asked for a clarification of Arizona law. The case focused on three questions:
1. Does the filing of a motion for class certification in an Arizona court toll the statute of limitations for individuals, who are included within the class, to file individual causes of action involving the same defendants and the same subject matter?2. If so, does this class-action tolling doctrine apply to statutes of repose, and more specifically, to the statute of repose for construction defects set forth in Arizona Revised Statutes ("A.R.S.") § 12-552?3. If the doctrine applies to statutes of repose, and specifically § 12-552, may a court weigh the equities of the case in determining whether, and to what extent, an action is tolled?
The litigation at hand has a lengthy history, starting with a case referred to as “Hoffman” in 2003. The Albano plaintiffs were not able to join in Hoffman, and they filed their own lawsuit in 2006. An additional lawsuit was filed by the Albano plaintiffs in 2007. The courts decided that the Albano plaintiffs’ lawsuit was untimely.
The Arizona Supreme Court concluded that the statute of repose was the appropriate standard for this case. They noted that “the eight-year statute of repose period began to run on November 6, 1997, the date of the Town of Gilbert’s final inspection. Albano II was filed on November 5, 2007.”
The court found that the plaintiffs had waited too long for start their suit. As a result, they found it unnecessary to answer the first or third questions. Justice A. John Pelander of the Arizona Supreme Court wrote the opinion, dated June 30, 2011.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Thank You for Seven Years of Election to Super Lawyers
May 01, 2023 —
Christopher G. Hill - Construction Law MusingsIt is with humility and a sense of accomplishment that I announce that I have been selected for the seventh straight year to the
Virginia Super Lawyers in the Construction Litigation category for 2023. Add this to my recent election to the
Virginia Legal Elite in Construction and I’ve had a pretty good year. As always, I am thrilled to be included on these peer-elected lists.
So without further ado, thank you to my peers and those on the panel at Virginia Super Lawyers for the great honor. I feel quite proud to be part of the
5% of Virginia attorneys that made this list for 2023.
The full lists of Virginia Super Lawyers will appear in the May edition of Richmond Magazine. Please check it out.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Ahead of the Storm: Preparing for Dorian
September 16, 2019 —
Adam P. Handfinger, Stephen H. Reisman & Gary M. Stein - Peckar & Abramson, P.C.While Hurricane Dorian churns in the Atlantic with its sights currently set on the east coast of Florida, storm preparations should be well underway. As you are busy organizing efforts to secure your job sites, we at Peckar & Abramson offer some quick reminders that may prove helpful:
- Review your contracts, particularly the force majeure provisions, and be sure to comply with applicable notice requirements
- Even if not expressly required at this time, consider providing written notice to project owners that their projects are being prepared for a potential hurricane or tropical storm and that the productivity and progress of the work will be affected, with the actual time and cost impact to be determined after the event.
- Consult your hurricane plan (which is often a contract exhibit) and confirm compliance with all specified safety, security and protection measures.
- Provide written notice to your subcontractors and suppliers of the actions they are required to take to secure and protect their portions of the work and the timetable for completion of their storm preparations.
Reprinted courtesy of Peckar & Abramson, PC attorneys
Adam P. Handfinger,
Stephen H. Reisman and
Gary M. Stein
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Mr. Reisman may be contacted at sreisman@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Waiver of Consequential Damages: The Most Important Provision in a Construction Contract
March 08, 2021 —
Jeremy P. Brummond - Construction ExecutiveConstruction agreements can be lengthy. They often include terms covering everything from logistics for working on the project site to complicated provisions regarding intellectual property. Many provisions in a construction agreement deal with risk and who is going to pay for damage claims if or when they occur.
However, not all risk-shifting provisions are equally important. While provisions that impose obligations on the contractor to maintain confidentiality, indemnify for personal injury or property damage, or correct defective work can expose a contractor to substantial damage claims and are thus important, contractors can significantly control the amount of damages the owner can claim by including a well-drafted waiver of “consequential damages” provision in the agreement.
Because the waiver of consequential damages can significantly control the amount of damages for which a contractor is assuming risk and greatly limit the owner’s ability to recoup many damages, it is arguably the most important provision in a construction contract. Therefore, it is essential for contractors and owners to carefully consider the waiver of consequential damages before entering into any construction agreement.
Reprinted courtesy of
Jeremy P. Brummond, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of