When Can a General Contractor’s Knowledge be Imputed to a Developer?
August 06, 2014 —
Zach McLeroy – Colorado Construction LitigationThe Colorado Court of Appeals recently handed down an opinion clarifying when the knowledge of a general contractor can be imputed to a developer. In the case of Jehly v. Brown, 327 P.3d (Colo. App. 2013), the Court of Appeals held that a developer cannot be held liable for fraudulent concealment when the developer has no actual knowledge of the fact or facts allegedly being concealed even if the general contractor had knowledge.
In this case, Brown, the developer, owned real property in Teller County and hired a general contractor to build a single-family house. Sometime before or during the construction, the general contractor became aware that part of the home site was located in a designated floodplain. Although the general contractor was aware that part of the home site was located in a floodplain, he continued to build the home without informing Brown of the floodplain designation.
Once the home was complete, Brown sold the property to the Jehlys. Brown completed a Seller’s Property Disclosure Form regarding the condition of the house and property, but failed to identify that the home site was located in a governmentally designated floodplain.
Read the court decisionRead the full story...Reprinted courtesy of
Zack McLeroy, Higgins, Hopkins, McLain & Roswell, LLCMr. McLeroy may be contacted at
McLeroy@hhmrlaw.com
Economic Damages Cannot be Based On Speculation
October 16, 2018 —
David Adelstein - Florida Construction Legal UpdatesEconomic damages, unlike non-economic damages (such as those in personal injury disputes), need to rest on a reasonable basis. Economic damages are those routinely seen in a construction dispute. These damages cannot be based on conjecture or guesswork and need to be supported by competent substantial evidence. Otherwise, the economic damages will be deemed too speculative because they are not reasonably quantifiable. I recently discussed a case involving the professional boxer Canelo Alvarez that was sued by a former promoter for unjust enrichment. Although the promoter recovered a jury verdict for unjust enrichment damages against Canelo Alvarez, the verdict was reversed because the methodology utilized by the promoter to demonstrate damages was speculative. This is definitely not what a plaintiff wants to happen after prevailing at the trial level!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
How Are You Dealing with Material Delays / Supply Chain Impacts?
June 07, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn a prior article I discussed a material escalation provision in your construction contract to account for the volatility of the material price market. While including such a provision may not have been much of a forethought before, it is now!
What about concerns with the actual supply chain that impacts the availability of and the lead time of materials? How are you addressing this concern in your construction contract?
The pandemic has raised awareness to this issue as certain material availability has been impacted by the pandemic. As a result, parties in construction have tried to forecast those materials where delivery issues may occur including those materials with longer than expected lead times. But equally important is how this issue is being addressed in your construction contract including how you want to negotiate this risk in future construction contracts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Housing Starts in U.S. Surge to Seven-Year High as Weather Warms
May 20, 2015 —
Sho Chandra – BloombergNew residential construction in the U.S. surged in April to the highest level in more than seven years, indicating the industry has moved beyond a weather-related soft patch to regain strength.
Housing starts jumped 20.2 percent to a 1.14 million annualized rate, the most since November 2007, from a 944,000 pace in March, a Commerce Department report showed Tuesday in Washington. The median forecast of 83 economists surveyed by Bloomberg was 1.02 million. More permits, a proxy for future construction, were issued than at any time since June 2008.
An improving labor market and mortgage costs close to multiyear lows are reviving residential construction, a sign that the weakness in early 2015 was probably due to harsh winter weather. Builders including PulteGroup Inc. have said the spring selling season is off to a good start, and sentiment data for May showed developers are optimistic about the next six months.
Read the court decisionRead the full story...Reprinted courtesy of
Shobhana Chandra, Bloomberg
Savannah Homeowners Win Sizable Judgment in Mold Case against HVAC Contractor
August 10, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPTwo Savannah homeowners filed a complaint against a local air conditioning contractor and its insurer, asserting claims of professional negligence and fraud. The couple alleged that in March 2009, the contractor replaced the duct system of their home’s air conditioning unit. The following June, the couple discovered mold growth on the vent covers. They hired an independent contractor who upon inspection concluded that the duct system, which contained holes, gaps, loose connections and insufficient mastic, had been defectively installed in violation of the applicable city ordinances, resulting in excessive moisture and mold contamination throughout the residence. The homeowners alleged that they grew ill with respiratory problems as a result and were subsequently forced to vacate the residence and abandon their personal belongings. Their complaint sought to recover repair costs, moving costs, expenses associated with rental property, costs of living, costs related to the replacement of personal property, medical expenses, punitive damages, attorney’s fees, and costs of litigation.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
New-Home Sales in U.S. Unexpectedly Fall to Four-Month Low
January 07, 2015 —
Victoria Stilwell – BloombergPurchases of new U.S. homes unexpectedly declined in November to a four-month low, underscoring a lack of momentum this year in residential real estate.
Sales dropped 1.6 percent to a 438,000 annualized pace last month following a 445,000 rate in October that was weaker than previously estimated, Commerce Department figures showed today in Washington. The median estimate of 73 economists surveyed by Bloomberg called for a 460,000 pace in November.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, BloombergMs. Stilwell may be contacted at
vstilwell1@bloomberg.net
Insurance Coverage Litigation Section to Present at Hawaii State Bar Convention
October 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Hawaii State Bar convention will be on October 24, 2014, at the Hawaiian Hilton. The Insurance Coverage Litigation Section will make a presentation from 8:30 a.m. to 11:45 a.m.
Three presentations will be made. First, Richard C. Mosher (Anderson Kill), Kathy Dang (Marsh), and Beau Monday (Hawaiian Telcom) will discuss cyber-liability claims and insurance options.
Next, David R. Harada-Stone (Tom Petrus & Miller) and I (Damon Key Leong Kupchak Hastert) will address "occurrences," i.e., deciding on and the impact of determining the number of occurrences in particular factual settings.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
AB 1701 Has Passed – Developers and General Contractors Are Now Required to Double Pay for Labor Due to Their Subcontractors’ Failure to Pay
October 19, 2017 —
Clayton T. Tanaka – Newmeyer & Dillion LLPOn September 13, 2017, the California State Legislators passed a bill that would make developers and general contractors responsible for subcontractors who fail to pay their employees even though they already paid the subcontractors for the work. Assembly Bill 1701 (AB 1701), sponsored by unions who represent carpenters and other building trades, would require general contractors to “assume, and [be] liable for . . . unpaid wage, fringe or other benefit payment or contribution, including interest owed,” which subcontractors owe their employees. Despite vehement opposition from the California Building Industry Association and the Associated General Contractors of California, this bill has been submitted to the Governor and is expected to be signed into law.
NEW REQUIREMENTS
Once signed, this bill would impose the following requirements under Labor Code section 218.7:
- Applies to All Private Works Contracts That Are Entered Starting January 1, 2018.
For private works contracts entered on or after January 1, 2018, a “direct contractor” (i.e., prime contractor or contractor who has direct contractual relationship with an owner) must assume and be liable for any debt which its subcontractor or a lower tier subcontractor incurs “for [a] wage claimant’s performance of labor included in the subject of the contract between the direct contractor and the owner.” (Lab. Code, § 218.7, subds. (a)(1) and (e).)
- The Labor Commissioner and Joint Labor-Management Cooperation Committees May Bring Action to Recover Unpaid Wages on Behalf of Wage Claimants.
The California Labor Commissioner and joint Labor-Management Cooperation Committees established under the federal Labor Management Cooperation Act of 1978 (29 U.S.C. § 175a) (typically comprised of labor unions and management) may bring a civil action against the direct contractor for unpaid wages owed to a wage claimant. (Lab. Code, § 218.7, subds. (b)(1) and (3).) The Labor Commissioner may also bring its claims through administrative hearings (Labor Code section 98) or by citations (Labor Code section 1197.1). (Lab. Code, § 218.7, subd. (b)(1).)
- Third Parties That Are Owed Fringe or Other Benefit Payments or Contribution on Behalf of Wage Claimants (Labor Unions) May Bring Action.
Third parties who are owed fringe or other benefit payments or contributions on a wage claimant’s behalf (e.g., labor unions) may bring a civil action against the direct contractor for such unpaid benefit payments or contributions. (Lab. Code, § 218.7, subd. (b)(2).)
- It Does Not Confer Wage Claimants With Any Right to Sue Direct Contractors.
AB 1701 gives the Labor Commissioner, Labor-Management Cooperation Committees and the unions standing to bring an action against the direct contractor, but it does not confer any private right of action by the wage claimants against the direct contractor.
- Labor-Management Cooperation Committees and Labor Unions Shall Recover as Prevailing Plaintiffs Their Attorneys’ Fees and Costs, Including Expert Fees.
For actions brought by Labor-Management Cooperation Committees or labor unions, “[t]he court shall award a prevailing plaintiff in such an action its reasonable attorney’s fees and costs, including expert witness fees.” (Lab. Code, § 218.7, subds. (b)(2)-(3).)
- Direct Contractor’s Property May Be Attached to Pay for Judgment.
AB 1701 authorizes the attachment of direct contractor’s property to pay for any judgment that is entered pursuant to this section. (Lab. Code, § 218.7, subd. (c).)
- One-Year Statute of Limitation to Bring Action under This Section.
Actions brought pursuant to this section must be filed within one year of the earliest of: (1) recordation of a notice of completion of the direct contract; (2) recordation of a notice of cessation of the work covered by direct contract; or (3) actual completion of work covered by direct contract. (Lab. Code, § 218.7, subd. (d).)
- Rights to Receive Payroll Records and Project Award Information from Subcontractors and to Withdraw All Payments Owed for Their Failure to Comply.
Upon the direct contractor’s request, subcontractors and lower tier subcontractors must provide payroll records and project award information. (Lab. Code, § 218.7, subds. (f)(1)-(2).) Direct contractor may withhold as “disputed” all sums owed if a subcontractor does not timely provide the requested records and information without specifying what is untimely and such failure to comply does not excuse direct contractor from any liability under this section. (Lab. Code, § 218.7, subds. (f)( 3) and (i).)
- Rights to Receive Payroll Records and Project Award Information from Subcontractors and to Withdraw All Payments Owed for Their Failure to Comply.
Upon the direct contractor’s request, subcontractors and lower tier subcontractors must provide payroll records and project award information. (Lab. Code, § 218.7, subds. (f)(1)-(2).) Direct contractor may withhold as “disputed” all sums owed if a subcontractor does not timely provide the requested records and information without specifying what is untimely and such failure to comply does not excuse direct contractor from any liability under this section. (Lab. Code, § 218.7, subds. (f)( 3) and (i).)
- Further Legislative Efforts on Subdivision (h) Are Expected in 2018.
Subdivision (h), which states that “[t]he obligations and remedies provided in this section shall be in addition to any obligations and remedies otherwise provided by law . . .” (emphasis added) is potentially misleading since the author and sponsor of the bill have indicated that the bill is not intended to punish direct contractors with liquidated damages or penalties. As such, further legislative efforts on subdivision (h) are expected in 2018.
ADDITIONAL CONSIDERATIONS
While workers should be paid for the work they perform, AB 1701 would place undue burden on general contractors to monitor their subcontractors’ payroll, confirm that all wages and benefits are paid timely and withhold disputed payments from non-compliant subcontractors. General contractors would also need to caution against the chain reaction that could result from such withholding, including work stoppage, increased change order requests, and an overall increase in construction costs. Finally, general contractors would need to brace themselves for at least a year after project completion against any union or a Labor-Management Cooperation Committee actions armed with a prevailing party’s right to recover attorneys’ fees and expert fees, for previously unidentified subcontractor or sub-subcontractor workers.
STRATEGIES DEVELOPERS AND GENERAL CONTRACTORS SHOULD LOOK FOR
In anticipation of AB 1701 being signed into law and its potentially harsh effects, developers and general contractors are advised to consult their attorneys for a review and revision of their existing contracts, to develop plans for accessing and monitoring subcontractor payroll records, and to consider strategies for mitigating claims that may be brought against them, as follows:
- Execute all pending agreements
before January 1, 2018 to avoid the effects of AB 1701;
- Include an audit provision
requiring subcontractors and sub-subcontractors to provide payroll records (at minimum, information set forth in Labor Code section 226) and project award information, regularly and/or upon request, with specific deadlines for such production, as subdivision (f) does not specify what is untimely;
- Include defense and indemnity provisions
that would require subcontractors to defend and indemnify the general contractor for claims that are brought pursuant to this section arising from labor performed by employees for subcontractors and sub-subcontractors, and require subcontractors to include a similar provision in their own contracts with sub-subcontractors that would require lower tier subcontractors to also defend and indemnify the general contractor for claims arising from their respective employees’ work;
- Require subcontractors to provide a payment bond and/or a letter of credit
to satisfy claims that are made against the general contractor under this section;
- Require personal guarantees
from owners, partners or key subcontractor personnel;
- Include withholding and back-charge provisions
that would allow general contractors to withhold or charge back the subcontractors for disputed amounts, for claims brought against them, and for failure to comply with the audit, bond, and guarantee requirements.
- Consider implementing a system to confirm evidence of payments,
such as signed acknowledgment of payment by each subcontractor and sub-subcontractor employees and by third parties entitled to recover fringe and other benefit payments or contribution, possibly working with electronic billing software providers to implement such system.
Clay Tanaka is a partner in the Newport Beach office of Newmeyer & Dillion, focusing on construction, real estate, business and insurance disputes in both California and Nevada. As a licensed civil engineer, Clay has significant experience in design and construction of all types of construction projects, which he has effectively utilized in his litigation, trial and arbitration practice to obtain great results for his clients. For questions related to AB1701, please contact Clay Tanaka (clay.tanaka@ndlf.com) or Newport Beach Partner Mark Himmelstein (mark.himmelstein@ndlf.com).
Read the court decisionRead the full story...Reprinted courtesy of
Clayton T. Tanaka, Newmeyer & Dillion LLPMr. Tanaka may be contacted at
clay.tanaka@ndlf.com