Stormy Seas Ahead: 5th Circuit to Review Whether Maritime Law Applies to Offshore Service Contract
July 26, 2017 —
Richard W. Brown & Afua S. Akoto - Saxe Doernberger & Vita, P.C.Earlier this year, the 5th Circuit applied the Davis factors to determine the validity of an indemnity clause in a Master Services Contract. In Larry Doiron Inc. et al., v. Specialty Rental Tool & Supply LLP et al., the court affirmed the notion that if a contract provides services on navigable waters aboard a vessel, a maritime contract exists, even if the contract calls for incidental or insubstantial work unrelated to the use of a vessel. With this decision, plaintiffs were granted indemnification for a crane injury and all was well on the open seas.
The 5th Circuit made waves, however, on July 7, 2017, when it agreed to rehear the case en banc. In its petition for rehearing, defendant STS argued that: (1) the original opinion conflicted with Supreme Court precedent by applying tort law principles to a contract case; (2) the court misapplied the Davis factors and the decision was contrary to Davis because the historical treatment of specialty well service work has been established as non-maritime; (3) the court needed to address whether a contract is subject to maritime or land-based law in the context of offshore mineral exploration.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Afua S. Akoto, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Ms. Akoto may be contacted at asa@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Dispute between City and Construction Company Over Unsightly Arches
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe city of Swartz Creek, Michigan alleged that Slagter Construction’s work on “Texas-style arches along a new bridge” was “terrible” and doesn’t “match up to what the company promised when it took the job to build the $20,000 walkways that include the arches,” reported M Live.
However, Slagter Construction “maintains its repairs were adequate and claims in a letter to the state that the issue shouldn't resolved by local officials who have ‘no formal training or education on these matters.’”
According to M Live, “[t]he two sides are set to meet on May 5 with MDOT officials on May 5 in Bay City for arbitration.”
Read the court decisionRead the full story...Reprinted courtesy of
Sureties do not Issue Bonds Risk-Free to the Bond-Principal
August 30, 2017 —
David Adelstein - Florida Construction Legal UpdatesIf your construction company is bonded, then you have signed a General Agreement of Indemnity with your surety / bonding company. Stated another way, if a surety issued an obligee on behalf of your construction company, as the bond-principal, a payment or performance bond, then you have signed a General Agreement of Indemnity with your surety.
The General Agreement of Indemnity is NOT to be taken lightly. Without the General Agreement of Indemnity, the surety is NOT issuing the bonds you need to work on a certain project. A bond is not insurance and sureties do not issue the bonds under a risk-free premise. Oh no! If a surety has to pay-out claims under a bond, the surety will be looking to recoup that loss from the indemnitors that executed the General Agreement of Indemnity.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
BWB&O’s Motion for Summary Judgment is Granted in a Premises Liability Matter
November 05, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Newport Beach Partner Courtney Serrato and Associate Joseph Real on Prevailing on a Motion for Summary Judgment for their Client!
Plaintiff filed a lawsuit alleging negligence and premises liability against BWB&O’s client, a general contractor of a multi-level construction project. Plaintiff was injured after a fall at the construction project and filed suit against BWB&O’s client and another subcontractor.
Plaintiff alleged BWB&O’s client was negligent and was responsible for causing Plaintiff’s fall. BWB&O filed a Motion for Summary Judgment arguing under the Privette Doctrine and its progeny, it neither owed nor breached any duty to Plaintiff and that no exception to the doctrine applied. Under the Privette Doctrine, when a person or entity hires an independent contractor to provide work or services, and one of the contractor’s employees is injured on the job, the hirer is generally not liable to the employee.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Providing Your Insurer Prompt Notice
May 20, 2024 —
David Adelstein - Florida Construction Legal UpdatesSometimes, when it comes to insurance, you may hear the argument that you breached your insurance policy by failing to provide your insurer with prompt notice as the insurance policy requires. Well, this is not such an absolute issue. With that said, you should absolutely provide your insurer with prompt notice of a claim or loss. No legitimate reason not to. But, if you don’t, it is not an absolute get out of jail free card for your insurer, but it does give them a good argument, which you don’t really want to deal with.
In Gulfpoint Construction Co., Inc. v. Westfield Ins. Co., 2024 WL 1759228 (11th Cir. 2024), an insured appealed a trial court’s ruling that found it did not provide prompt notice to its property insurer as the policy required. In this case, notice was provided two years after a loss from a hurricane. The insurer denied coverage and, in doing so, relied on the insured’s failure to provide prompt notice. Although the trial court agreed, the appellate court found this was a genuine issue of material fact.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Los Angeles Tower Halted Over Earthquake and other Concerns
December 04, 2013 —
CDJ STAFFPlans to build the Millennium Hollywood project have been halted over lawsuits alleging that the Hollywood fault line runs under the site and would render it unsafe. Additional claims are that the buildings would block views of the Hollywood sign. But Robert Silverstein alleges in his suit that the buildings would endanger lives.
The Millennium claims that the project would create about 3,000 construction jobs, and that after the building were complete, they would create 1,000 jobs.
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Supreme Court Reverses Decision against Grader in Drainage Case
June 30, 2011 —
CDJ STAFFThe Nevada Supreme Court has issued an opinion in the case of Rayburn Lawn & Landscape Designers v. Plaster Development Corporation, reversing the decision of the lower court and remanding the case for a new trial.
The case originated in a construction defect suit in which Plaster Development Corporation was sued by homeowners. Plaster filed a third-party complaint against its subcontractor, Reyburn. The testimony of Reyburn’s owner was considered to be admission of liability and so the court limited the scope of Reyburn’s closing argument and did not allow the jury to determine the extent of Reyburn’s liability. Reyburn appealed.
Plaster, in their case, cited California’s Crawford v. Weather Sheild MFG, Inc. The court held the application of these standards, but noted that the “an indemnitor’s duty to defend an indemnitee is limited to those claims directly attributed to the indemnitor’s scope of work and does not include defending against claims arising from the negligence of other subcontractors and the indemnittee’s own negligence.”
On the matter of law against Reyburn, the court concluded, “Given the conflicting evidence at trial as to whether Reyburn’s work was implicated in the defective retaining walls and sidewalls, and viewing the evidence and inferences in Reyburn’s favor, we conclude that a reasonable jury could have granted relief in favor of Reyburn.” The Nevada Supreme Court conduced that the district court should not have granted Plaster’s motion for judgement.
Further, the Nevada Supreme Court found that the district court should have apportioned the fees and costs to those claims directly attributed to Reyburn’s scope of work, “if any,” and should not have assigned all attorney costs and court fees to Reyburn.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Navy Sailors Sue Tokyo Utility Company Over Radiation Poisoning
April 09, 2014 —
Beverley BevenFlorez-CDJ STAFFIn a one billion dollar lawsuit, U.S. Navy sailors contend that they “suffered massive doses of radiation” from the Fukushima Dia-ichi nuclear power plant in Toyko, Japan while stationed on the USS Ronald Reagan, reported the Orange County Register. A tsunami (caused by a 9.0 earthquake) flooded the plant, “cutting off electrical power and disabling backup generators.” The USS Reagan was sent to provide aid, but the plant then “blew up” before they arrived.
“Sailors on the flight deck said they felt a warm gust of air, followed by a sudden snow storm: radioactive steam,” according to the Orange County Register. “Freezing in the cold Pacific air. Blanketing their ship.”
However, the Orange County Register posed the question, “Could the Reagan – one of the most advanced nuclear aircraft carriers in the U.S. fleet – really not know that it was being showered with massive doses of radiation?” TEPCO, the company being sued by the sailors, answered that it’s “wholly implausible.”
Read the court decisionRead the full story...Reprinted courtesy of