Commencing of the Statute of Repose for Construction Defects
November 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida has a ten-year statute of repose which applies predominantly to construction defect claims. This can be found in Florida Statute s. 95.11(3)(c). After ten years, any rights relative to a construction defect claim are time-barred. However, the statute of repose date has been watered down and can be made to be more of a factual question due to the lack of objectivity as to the date that starts the ten-year repose clock. The watering down of the statute of repose date benefits parties asserting construction defect claims provided they strategically appreciate the question of fact that can be created when up against the statute of repose. Stated differently, when up against the clock to assert a construction defect claim, strategically develop those facts, evidence, and arguments to maximize creating a question of fact as to when the statute of repose clock commenced. Conversely, as a defendant sued for construction defects, you want to maximize the facts, evidence, and arguments to fully establish the date the statute of repose clock had to commence for purposes of a statute of repose defense.
The recent opinion in Spring Isle Community Association, Inc. v. Herme Enterprises, Inc., 46 Fla. L. Weekly D2306b (Fla. 5th DCA 2021) demonstrates the factual question associated with the clock that starts the statute of repose date. This factual question is created by Florida Statute s. 95.11(3)(c) that provides:
[T]he action [founded on the design, planning, or construction of an improvement to real property] must be commenced within 10 years after the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion or termination of the contract between the professional engineer, registered architect, or licensed contractor and his or her employer, whichever date is latest.
Spring Isle Community Association, supra. (Note, see also current s. 95.11(3)(c) version in effect per hyperlink above.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
BHA’s Next MCLE Seminar in San Diego on July 25th
July 02, 2014 —
Beverley BevenFlorez-CDJ STAFFThere are just three weeks remaining to sign up for Bert L. Howe & Associate’s next California MCLE seminar, UNDERSTANDING CONSTRUCTION DEFECT LITIGATION.
This activity will be presented on Friday, July 25th at noon, in BHA’s San Diego offices, located at:
402 W. Broadway
Suite 400
San Diego, CA 92101
There is no cost for attendance at this seminar and lunch will be provided.
This course has been approved for Minimum Continuing Legal Education credit by the State Bar of California Committee on MCLE in the amount of 1.0 credit hours, of which 0.0 credit hours will apply to legal ethics/professional responsibility credit. The seminar will be presented by Charlie Miller, general contractor and project manager.
Water intrusion through doors, windows and roofing systems, as well as soil and foundation-related movement, and the resultant damage associated therewith, are the triggering effects for the vast majority of homeowner complaints today and serve as the basis for most residential construction defect litigation. The graphic and animation-supported workshop/lecture activity will focus on the residential construction process from site preparation through occupancy, an examination of associated damages most often encountered when investigating construction defect claims, and the inter-relationships between the developer, general contractor, sub trades and design professionals. Typical plaintiff homeowner/HOA expert allegations will be examined in connection with those building components most frequently associated with construction defect and claims litigation.
The workshop will examine:
• Typical construction materials, and terminology associated with residential construction
• The installation process and sequencing of major construction elements, including interrelationship with other building assemblies
• The parties (subcontractors) typically associated with major construction assemblies and components
• An analysis of exposure/allocation to responsible parties.
Attendance at THE UNDERSTANDING CONSTRUCTION DEFECT LITIGATION seminar will provide the attendee with:
• A greater understanding of the terms and conditions encountered when dealing with common construction defect issues
• A greater understanding of contractual scopes of work encountered when reviewing construction contract documents
• The ability to identify, both quickly and accurately, potentially responsible parties
• An understanding of damages most often associated with construction defects, as well as a greater ability to identify conditions triggering coverage
To register for the event, please email Charlie Miller at cmiller@berthowe.com. If you have any questions, please feel free to contact Charlie at (800) 482-1822 (office) or (714) 353-1959 (cell).
Read the court decisionRead the full story...Reprinted courtesy of
HOA Coalition Statement on Construction-Defects Transparency Legislation
May 12, 2016 —
David M. McClain – Colorado Construction LitigationFOR IMMEDIATE RELEASE
Contact: Bill Ray / 303-885-1881
DENVER—The Homeownership Opportunity Alliance—a broad coalition of business groups, builders, elected officials and affordable housing advocates—provided the following statements on reports that there will be no construction-defects transparency legislation this session:
“We are disappointed that negotiations broke down today and that event was immediately turned into an effort to use the media to score political points. The Homeownership Opportunity Alliance has worked on this issue for three years, and we are committed to finding a resolution that will address Colorado’s housing needs, especially through the development of attainable condominiums,” said Tom Clark, Chief Executive Officer of the Metro Denver Economic Development Corporation. “We understand the importance of this issue for our state, for working families, for first-time homebuyers and for anyone along the housing spectrum who is struggling to find a home. That's why we will remain committed to working on this issue.”
The Homeownership Opportunity Alliance’s diverse coalition includes more than 50 organizations from across Colorado. The coalition also includes individual mayors and 14 different communities that have passed local ordinances to address attainable condominium development.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McClain, Higgins, Hopkins, McLain & Roswell, LLCMr. McClain may be contacted at
mclain@hhmrlaw.com
Is Safety Compliance Putting Your Project in Jeopardy? Examining the Essentials of DOE’s Worker Safety and Health Program
July 02, 2024 —
Lucas T. Daniels & Benjamin J. Hochberg - ConsensusDocsMost contractors are familiar with the myriad of labor and safety regulations intended to safeguard the health and safety of workers. Many contractors will be equally familiar with the maze of forms and reports, the maintenance of safety personnel, safety walks and talks, and the many other measures intended to prevent and prepare for accidents. Less known among contractors and construction industry leaders is the regulatory framework establishing safety requirements and the ramifications of ignoring safety-related rules. Knowing and understanding the jurisdiction and authority of the agencies monitoring safety compliance on your project is critical to avoiding administrative ordeals and audits that could add days or weeks to your schedule and frustrate your staff.
The Department of Energy’s Worker Safety and Health Program
Under the Occupational Safety and Health Act of 1970, as amended (OSH), the Department of Labor’s Occupational Safety and Health Administration (OSHA) issues and enforces occupational health and safety regulations. OSHA, or a state with approval from OSHA, regulates the occupational health and safety of private sector employees unless another federal agency has and exercises its statutory authority to regulate. Several federal agencies have developed their own safety programs and conduct their own enforcement of those regulations independent of OSHA. For example, projects receiving funding from the Department of Energy (DOE) are subject to additional oversight of their safety programs by this agency. DOE directly manages its own Worker Safety and Health Program (WSHP), codified at 10 C.F.R. § 851, et seq., and will enforce compliance with its WSHP at all DOE sites. A “DOE site” is defined as a DOE-owned or -leased area or location or other area or location that DOE controls, where a contractor performs activities and operations in furtherance of a DOE mission. This broad definition encompasses a wide range of facilities and operations, including those not directly managed by the DOE but still under its control. The contractor at such a site must be aware of the specific requirements and procedures of the DOE under the WSHP and the ramifications of violating these regulations.
Reprinted courtesy of
Lucas T. Daniels, Peckar & Abramson, P.C and
Benjamin J. Hochberg, Peckar & Abramson, P.C
Mr. Daniels may be contacted at ldaniels@pecklaw.com
Mr. Hochberg may be contacted at bhochberg@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
City of Birmingham Countersues Contractor for Incomplete Work
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in December of 2013, WVTM News reported that Chris Woods, a contractor, filed a lawsuit against the City of Birmingham, Alabama, demanding $1.5 million for the West Police Precinct and two other projects he had been contracted on. However, “Birmingham claimed Woods was fired for not completing projects on time and other contract breaches.”
On March 7th, WVTM News reported that the City of Birmingham has filed a counterclaim against Woods, alleging that he “owes $1.2 million for incomplete work.” The city listed his “inability to meet specific construction deadlines and finish either project on time as factors for his termination.” Woods, however, blamed the city for delays, citing multiple design changes requested by Birmingham.
The city’s counterclaim also alleged that “Star Insurance Company, ‘identified major, numerous defects in the work that Woods had performed prior to the termination of the West Precinct Project.’”
Read the full story, December 2013 Article...
Read the full story, March 2014 Article... Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Appellate Court Breaks New Ground on Policy Exhaustion
April 26, 2021 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsThe Connecticut Appellate Court recently issued a wide-ranging opinion, Continental Casualty Co. v. Rohr, Inc.,[1] which significantly extended the current restrictive view on when a general liability policy can be considered exhausted so as to trigger overlying excess coverage. The case marks a further step away from Judge Augustus Hand’s almost-century-old ruling in Zeig v. Massachusetts Bonding & Ins. Co.,[2] which held that an underlying policy could be “exhausted” by a below-limits settlement as long as the insured was willing to “fill the gap” between the settlement amount and the limits of the policy.[3]
In recent years, courts in California and elsewhere have increasingly walked back Zeig’s broad ruling – holding in Qualcomm v. Certain Underwriters,[4] for example, that an insured’s below-limits settlement with primary carriers does not exhaust the limits of primary coverage, or allow the insured to access overlying excess coverage.[5]
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Failure to Allege Property Damage Within Policy Period Defeats Insured's Claim
October 03, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's inability to determine when water damage occurred meant it could not pursue claims of property damage against the insurers. Creek v. State Farm Fire & Cas. Co., 2022 U.S. Dist. LEXIS 116939 (W.D. Wash. July 1, 2022).
Gold Creek Condominium complex experienced water damage. The complex was completed in 1982. The owners sued State Farm and Travelers under all-risk policies when tenders for the damage were denied.
In 2017, Creek hired an expert to investigate deterioration due to water intrusion. The expert noted that "water intrusion had been evident in the exterior walls, soffits, terraces, handrails and elevated entry walkways for some time." Thereafter, Creek tendered claims for property damage to State Farm and to Travelers.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Data Is Critical for the Future of Construction
April 19, 2022 —
Raghi Iyengar - Construction ExecutiveAccording to a
recent study, real-time visibility and access to critical data and insights are vital for rapid construction decision-making. Notably, inaccurate and missing data cost the industry almost $2 trillion in 2020. Even more surprising, construction companies often don’t know if they’ve made or lost money until the job is complete or if they’re on schedule until they start falling behind. These findings portray an important reality for the industry: Construction needs to establish and optimize data strategies to ensure it has the visibility control, and transparency needed to improve efficiency and productivity on projects.
Luckily, while historically slow to change, the construction industry has begun to adopt technologies that help firms improve efficiency and productivity on projects. With this technology, contractors can establish and optimize data strategies to ensure they have visibility, control and transparency.
Embracing data is a game changer as the industry continues to expand. In fact, the report from Autodesk and FMI cited above found that the construction companies using data technologies and strategies saw
fewer project delays, less rework and fewer change orders.
Reprinted courtesy of
Raghi Iyengar, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.