Litigation Roundup: “You Can’t Make Me Pay!”
August 19, 2024 —
Daniel Lund III - LexologyThe foregoing is an accurate statement, generally speaking, for Louisiana public entities. Statutory and constitutional provisions in Louisiana protect public entities from being forced to pay monies – including satisfying court judgments – when the monies have not been specifically allocated for the purpose. Correspondingly, there is ordinarily no means to seize public assets to satisfy judgments.
On the other hand, writs of mandamus in Louisiana – actions designed to compel a public official to undertake a ministerial duty over which the public official has no discretion – can be aimed at forcing a public official (on behalf of the public entity) to pay money.
In an inverse condemnation case, plaintiffs prevailed on the theory that a Louisiana public entity had “damaged and interfered with their use and enjoyment of their private homes and church” during a New Orleans drainage project. The plaintiffs pursued a writ of mandamus to compel payment their approximately $1.5 million judgment for damages and fees as a “ministerial duty” of the public entity. To be sure, in connection with the judgment, the public entity had not at any time specifically allocated funds for the payment.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Insurance Law Client Alert: California Appeals Court Refuses to Apply Professional Services Exclusion to Products-Completed Operations Loss
March 19, 2014 —
Valerie A. Moore and Chris Kendrick - Haight Brown & Bonesteel LLPIn North Counties Engineering v. State Farm (No. A133713, filed 3/13/14), State Farm insured an engineering company under CGL insurance that had a professional services exclusion and included products-completed operations (PCO) coverage. The owner of the engineering company, NCE, contracted with a winery to construct a dam and associated works. Also on the project was the owner's son, who had his own construction company, NCD. There were multiple contracts, both oral and written, variously naming one company or the other. The evidence later showed that the father performed hands-on work for the project.
After completion, the winery was sued over sediment and erosion caused by the dam. State Farm denied coverage on the ground that the professional services exclusion applied, as well as a mistaken belief that the policy had no PCO coverage. State Farm then changed its position and agreed to defend, but only going forward. The insured sued State Farm over past defense fees, alleging breach of contract and bad faith. The case went to trial and after testimony detailing State Farm's claim handling, the trial judge granted a nonsuit, finding that the professional services exclusion barred all coverage:
"[I]f you look at the pleadings, the legal pleadings and the contracts, the NCE role is, as the engineering company, the support company, and that company was overseeing the [sic] NCD to make sure that whatever they did was done right.... NCE is the expert on the job, the professional providing professional services, design and construction, and also overseeing the work of NCD, the son’s business, which is doing more of the physical activity.... That takes professional expertise and I think all of what Mr. Akerstrom did was professional.... It was this professional work, and not 'something incidental to their professional involvement' that gave rise to the underlying actions. In this situation, it’s not a malpractice or E and O policy. It’s a business policy, which has good benefits, but is subject to the professional services exclusion."
Reprinted courtesy of
Valerie A. Moore and
Chris Kendrick of Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com; Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Will Colorado Pass a Construction Defect Reform Bill in 2016?
December 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to blogger Jill Jamieson-Nichols of the Colorado Real Estate Journal, another construction defects bill may be debated in Colorado next year. Representative Dan Pabon told Jamieson-Nichols that “the answer lies in ‘thinking about the insurance piece’ so condominium developers can afford insurance against litigation that might arise.” She also stated that the city of Denver is considering ways to increase funding to increase affordable housing in the area.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer’s Discovery Requests Ruled to be Overbroad in Construction Defect Suit
October 28, 2011 —
CDJ STAFFThe US District Court has ruled in the case of D.R. Horton Los Angeles Holding Co. Inc. v. American Safety Indemnity, Co. D.R. Horton was involved in a real estate development project. Its subcontractor, Ebensteiner Co., was insured by ASIC and named D.R. Horton as an additional insured and third-party beneficiary. D.R. Horton, in response to legal complaints and cross-complaints, filed for coverage from ASIC under the Ebensteiner policy. This was refused by ASIC. ASIC claimed that “there is no potential coverage for Ebensteiner as a Named Insurer and/or D.R. Horton as an Additional Insured.” They stated that “the requirements for coverage are not satisfied.”
The case same to trial with the deadline for discovery set at March 1, 2011. ASIC stated they were seeking the developer’s “job file” for the Canyon Gate project. D.R. Horton claimed that ASIC’s discovery request was overbroad and that it would be “unduly burdensome for it to produce all documents responsive to the overbroad requests.”
D.R. Horton did agree to produce several categories of documents, which included:
“(1) final building inspection sign-offs for the homes that are the subject of the underlying litigation;(2) an updated homeowner matrix for the underlying actions; (3) the concrete subcontractor files; (4) the daily field logs for D.R. Horton’s on-site employee during Ebensteiner’s work; (5) documents relating to concrete work, including documents for concrete suppliers; (6) documents relating to compacting testing; (7) documents relating to grading; and (8) D.R. Horton’s request for proposal for grading”
The court found that the requests from ASIC were overbroad, noting that the language of the ASIC Request for Production of Documents (RFP) 3-5 would include “subcontractor files for plumbing, electric, flooring, etc. - none of these being at issue in the case.” The court denied the ASIC’s motion to compel further documents.
The court also found fault with ASIC’s RFPs 6 and 7. Here, D.R. Horton claimed the language was written so broadly it would require the production of sales information and, again, subcontractors not relevant to the case.
Further, the court found that RFPs 8, 10, 11, and 13 were also overbroad. RFP 8 covered all subcontractors. D.R. Horton replied that they had earlier complied with the documents covered in RFPs 10 and 11. The court concurred. RFP 13 was denied as it went beyond the scope of admissible evidence, even including attorney-client communication.
The court denied all of ASIC’s attempts to compel further discovery.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
California Court of Appeal Provides Clarity On What Triggers Supplemental Analysis Under California Environmental Quality Act
July 20, 2020 —
Kelly Alhadeff-Black & Alexander N. Knaub - Lewis BrisboisIn a recent ruling, California’s Sixth District Court of Appeal clarified the need for supplemental environmental analysis under the California Environmental Quality Act (CEQA). Willow Glen Trestle Conservancy v. City of San Jose (6th Dist., May 18, 2020). Specifically, the court held that seeking additional discretionary approvals, such as regulatory permits, does not constitute a “new discretionary approval for the project” under the California Public Resources Code Section 21166 and the California Code of Regulations, title 14, section 15162 (the CEQA Guidelines).
In 2014, the City of San Jose approved a project that included the demolition and replacement of a wooden railroad bridge known as the Willow Glen Trestle (the Project). CEQA review for the Project was conducted via mitigated negative declaration (MND). The Project was quickly challenged by a local group called Friends of the Willow Glen Trestle, alleging that the City should have prepared an Environmental Impact Report based on the allegation that the Willow Glen Trestle constituted an historic resource for CEQA purposes. Ultimately, the City prevailed in that litigation (See Friends of the Willow Glen Trestle v. City of San Jose, et al. (6th Dist., 2016), which remanded the case to the trial court for further review consistent with the Court of Appeal’s verdict) with the court eventually finding that the City correctly analyzed and answered the question of historic resource classification and significance in reference to the Willow Glen Trestle.
Reprinted courtesy of
Kelly Alhadeff-Black, Lewis Brisbois and
Alexander N. Knaub, Lewis Brisbois
Ms. Alhadeff-Black may be contacted at Kelly.Black@lewisbrisbois.com
Mr. Knaub may be contacted at Alexander.Knaub@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Alaska Supreme Court Dismisses Claims of Uncooperative Pro Se Litigant in Defect Case
August 11, 2011 —
CDJ STAFFThe Alaska Supreme Court found that in the case of Khalsa v. Chose, Ms. Khalsa? failure to cooperate with the courts has obligated them to dismiss her claims against Mr. Chose. Ms. Khalsa bought a home kit from Mandala Custom Homes of Nelson, British Columbia, Canada. Mr. Chose, one of the owners of Mandala was paid by Ms. Khalsa to supervise assembly in Fairbanks. After construction, the roof developed leaks. Ms. Khalsa stated that when climbing a ladder to inspect a skylight leak, she fell and injured herself.
During the subsequent suit, Khalsa proved uncooperative. She skipped a pretrial conference. She attended a hearing that set discovery deadlines but then did not comply with discovery, including her failure to provide medical records documenting her injuries. She eventually said that she would only be able to travel from Arizona to Alaska if the defendants paid for her and her caretaker?s expenses.
When finally deposed, Khalsa terminated the deposition after five minutes, alleging the deposition was “intentionally designed to cause [her] to endure further emotional distress, due to the psychological trauma . . . that was caused or contributed to by the defendants.”
Eventually, the lower court sanctioned her twice. In July, 2008, the court concluded that her failure to provide medical records required dismissal of her injury lawsuit. In October of that year, the court dismissed all remaining claims due to her “pattern of excuses and long delays in providing information for discovery culminating in her refusal to participate in her deposition by the defendants.” Further, Khalsa has argued that the trial court displayed “prejudice and bias toward the pro se plaintiff.”
The Alaska Supreme Court rejected all of Ms. Khalsa?s claims, dismissing her case. They did, however, note that she has thirty days to file an appeal.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
GA Federal Court Holds That Jury, Not Judge, Generally Must Decide Whether Notice Was Given “As Soon as Practicable” Under First-Party Property Damage Policies
November 01, 2021 —
Edward M. Koch & Lynndon K. Groff - White and WilliamsInsurance policies covering first-party property damage often require insureds to notify insurers of a loss “as soon as practicable.” Where an insured may or may not have given notice “as soon as practicable,” the issue arises as to who should determine whether the insured complied with this requirement: the judge or the jury?
On October 6, 2021, the United States District Court for the Middle District of Georgia addressed this issue in Vintage Hospitality Group LLC v. National Trust Insurance Company, Case No. 3:20-cv-90-CDL, 2021 U.S. Dist. LEXIS 192651 (M.D. Ga. Oct. 6, 2021). In Vintage Hospitality, a July 2018 hailstorm damaged the roof of a hotel owned by the policyholder. The policyholder did not discover leaks from the hotel roof until two months later, in September 2018. The policyholder, not realizing that the hailstorm had caused the leaks, unsuccessfully attempted to repair the leaks. Eventually, in February 2020—19 months after the hailstorm and 17 months after the policyholder discovered the leaks—the policyholder hired a construction company to evaluate the roof. It was not until then that the policyholder learned that the hotel had sustained hail damage from the July 2018 storm. The policyholder notified its July 2018 first-party property damage insurer a few days later.
Reprinted courtesy of
Edward M. Koch, White and Williams and
Lynndon K. Groff, White and Williams
Mr. Koch may be contacted at koche@whiteandwilliams.com
Mr. Groff may be contacted at groffl@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Charting Your Contractual Rights With Respect To The Coronavirus
April 06, 2020 —
David Adelstein - Florida Construction Legal UpdatesAs more and more information is being learned, and more and more industries are being impacted, it is likely that the construction industry will follow suit. And, while impacts with the global supply chain may not yet be realized, impacts could begin with labor supply and, frankly, employers’ safety protocols dealing with the coronavirus. One suggestion that should be implemented is a detailed chart, similar to the below, where you are charting rights and obligations under your contracts dealing with force majeure, notice, and project suspensions. This is step one to make sure you are making prudent decisions, preserving rights, and making sure contractual obligations are being met. Be proactive, not reactive.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at