A Teaming Agreement is Still a Contract (or, Be Careful with Agreements to Agree)
November 18, 2019 —
Christopher G. Hill - Construction Law MusingsI have discussed teaming agreements in this past here at Construction Law Musings. These agreements are most typically where one of two entities meets a contracting requirement but may not have the capacity to fulfill a contract on its own so brings in another entity to assist. However, these agreements are contracts and are treated as such here in Virginia with all of the law of contracts behind them.
One illustrative case occurred here in Virginia and was decided by the Virginia Supreme Court. That case is CGI Fed. Inc. v. FCi Fed. Inc. While this is not strictly a “construction” case, it helps lay out some of the pitfalls of teaming agreements in general.
In this case, the parties entered into a fairly typical small business (FCI) Big Business (CGI) teaming arrangement for the processing of visas for the State Department. The parties negotiated the workshare percentage (read payment percentage) should FCI get the work and the teaming agreement set out a framework for the negotiation of a subcontract between FCI, the proposed general contractor, and CGI, the proposed subcontractor. After a while working together, FCI submitted a proposal to the State Department and as part of the negotiations of this proposal, the work percentage for CGI was lowered in exchange for some management positions for CGI relative to the work by amendment to the original teaming agreement. However, one day later FCI submitted a proposal to the State Department that not only didn’t include the management positions, but further lowered CGI’s workshare.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Finding Highway Compromise ‘Tough,’ DOT Secretary Says
May 05, 2014 —
Alan Levin – BloombergDivisions in Congress over boosting funding for bridge repairs and highway construction are making it difficult to pass a long-term measure in time to prevent a disruption in existing road projects, U.S. Transportation Secretary Anthony Foxx said.
“I would say that we have a tough, a tough challenge ahead of us that hasn’t been solved for a long time,” Foxx said in an interview on Bloomberg Television’s “Political Capital with Al Hunt,” airing this weekend.
The Highway Trust Fund, financed by gasoline and diesel taxes, may soon not be able to meet its financial obligations, according to Foxx’s agency. The Obama administration on April 29 sent legislation to Congress proposing $302 billion for road and mass transit projects over four years, with part of the money coming from new taxes on company earnings overseas.
Read the court decisionRead the full story...Reprinted courtesy of
Alan Levin, BloombergMr. Levin may be contacted at
alevin24@bloomberg.net
Erector Tops Out 850-Foot-Tall Rainier Square Tower in Only 10 Months
September 23, 2019 —
Nadine M. Post - Engineering News-RecordAs predicted, the Erection Co. topped out Seattle’s 850-ft-tall Rainier Square Tower, with its radical composite steel frame dubbed “speed core,” in only 10 months. Steel erection began last October in the lowest basement.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions
March 16, 2017 —
Jean Meyer - Colorado Construction LitigationOn February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.
However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, _ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Not So Unambiguous: California Court of Appeal Finds Coverage for Additional Insured
October 11, 2017 —
Malcom Ranger-Murdock - Saxe Doernberger & Vita, P.C.California’s Fourth District Court of Appeal recently determined that manuscript additional insured endorsements (AIEs), which purportedly provided coverage for ongoing operations only, were ambiguous. The court also found the insurer that issued the policies, American Safety Indemnity Co. (American Safety), acted in bad faith due to its systematic efforts to deny coverage to general contractors as additional insureds.
In Pulte Home Corp. v. American Safety Indemnity Co.,1 Pulte Home Corporation (Pulte Home), a general contractor, sued American Safety for failure to defend Pulte Home as an additional insured in connection with two underlying construction defect lawsuits. American Safety contended that it did not have a duty to defend Pulte Home because the loss occurred after the construction project was complete and the applicable AIEs did not provide coverage for completed operations, and/or because the policy’s faulty workmanship exclusions applied. The trial court awarded $1.4 million in compensatory and punitive damages to Pulte Home, and American Safety appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Malcom Ranger-Murdock, Saxe Doernberger & Vita, P.C.Mr. Ranger-Murdock may be contacted at
mrm@sdvlaw.com
Quick Note: COVID-19 Claim – Proving Causation
August 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesIn certain jurisdictions, the number of people testing positive for COVID-19 is on the rise. As this occurs, there is the possibility that a construction project will have to deal with one or more workers testing positive. That is the current reality. If the dialogue has not occurred before, now is the time to discuss any enhanced measures—above OSHA guidelines—that could be implemented to address this reality and mitigate the risk. Part of the reality, though, is that regardless of the enhanced measures and mitigation, it is impossible to truly prevent this risk.
No one disputes COVID-19. There may be a dispute as to whether COVID-19 constitutes a force majeure event or some other event, however, before you start labeling it, you still NEED TO PROVE the impact caused by COVID-19. There needs to be a cause-and-effect relationship so you can address (i) how this impacted the critical path of your schedule and/or (ii) how this impacted labor productivity. In other words, you need to prove causation. Stating there was a delay or loss of productivity without establishing the cause-and-effect relationship (i.e, causation) provides no value because it does not support the production impact or time extension and, without either, there is no basis for additional compensation (even if you establish it should be deemed an excusable, compensable delay).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Best Practices After Receiving Notice of a Construction Claim
July 18, 2022 —
Lauren Meadows - Construction ExecutiveBeing served with a lawsuit is typically not a welcomed experience. However, a construction professional that has been proactive in an early investigation of the claim will be better equipped to defend the case. The following best practices should be used by construction professionals as soon as a potential claim becomes evident.
Notify
Immediately after the receipt of a claim or notice of an incident, efforts should be made to notify all essential parties. This includes any potential insurers that may provide coverage for the claim as well as any parties to whom notice may be required or warranted under the project contract and/or scope of work. Some construction contracts contain an insurance clause that requires one party to provide additional insured coverage under its liability policy to another party. Notice should be given to any insurer that potentially provides additional insured coverage as soon as possible. The failure to provide an insurance company with prompt notice of a potential claim could result in the denial of the claim.
Reprinted courtesy of
Lauren Meadows, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Trends in Project Delivery Methods in Construction
April 03, 2023 —
Sarah B. Biser - ConsensusDocsThe three key measures of a construction project’s success are cost, quality, and time (delays). The project delivery method that the owner of the project selects can affect each of these metrics. Project delivery methods in complex construction projects evolve as technology and processes improve. The traditional methods of design-bid-build (DBB), design-build (DB), and construction management (CM) have been the standard for many years. More recently, however, newer methods such as integrated project delivery (IPD), and public-private partnerships (PPP) have gained traction.
Design – Bid – Build (DBB)
Design-bid-build is the oldest, most commonly used method of project delivery. It involves three distinct phases: design, bid/award, and construction. An owner asks a team of professionals, such as architects, engineers, and contractors, to produce design documents that will be used to solicit bids. After the owner evaluates the bids and chooses a contractor, a construction contract is written. While this method is the most familiar and well-understood, it can lead to disputes during the construction process as changes are made to the original plans.
In DBB, the owner bears the risk for funding increased costs attributed to design changes and related delays – thanks to the Spearin Doctrine, which holds that the owner impliedly warrants the information, plans, and specifications that it provides to a general contractor. See 248 U.S. 132 (1918) Although the owner cannot claim against the contractor, it can make a claim against the design firm.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah B. Biser, Fox Rothschild LLP (ConsensusDocs)Ms. Biser may be contacted at
sbiser@foxrothschild.com