The Show Must Go On: Shuttered Venues Operators Grant Provides Lifeline for Live Music and Theater Venues
March 29, 2021 —
David Rao - Snell & Wilmer Real Estate Litigation BlogAlthough it’s been a tough twelve months for many live music venues, movie theaters, and performing arts organizations, help may finally be around the corner. On December 27, 2020, the Economic Aid to Hard-Hit Small Businesses, Nonprofits, and Venues Act was signed into law, creating a $15 billion fund for grants to shuttered venues to be administered by the Small Business Administration’s (“SBA”) Office of Disaster Assistance. The law states that Shuttered Venues Operator Grants (“SVOGs”) will be made available to the following entities and individuals:
- Live venue operators or promoters;
- Theatrical producers;
- Live performing arts organization operators;
- Relevant museum operators, zoos, and aquariums which meet specific criteria;
- Movie theater operators;
- Talent representatives; and
- Each business entity owned by an eligible entity that also meets the eligibility requirements.
Read the court decisionRead the full story...Reprinted courtesy of
David Rao, Snell & WilmerMr. Rao may be contacted at
drao@swlaw.com
Contractor Haunted by “Demonized” Flooring
December 14, 2020 —
Garret Murai - California Construction Law BlogThe most un-Halloween of Halloweens has come and gone. If you ask me though, between COVID, protests, fires, hurricanes, the passing of a Supreme Court Justice, and one of the most hotly contested elections in U.S. history, we’ve had enough scares this year to make up for it and then some.
In the next case, Sieg v. Registrar of Contractors, Case No. A156089 (September 28, 2020), 1st District Court of Appeal, one contractor, haunted by “demonized” flooring, and who couldn’t catch a break even with the talisman of a release of liability signed by the homeowner, can add one more to his list of reasons why 2020 needs to be relegated to the history books.
The Sieg Case
In January 2012, homeowners Dennis and Ana Torchia purchased wood flooring for their home in Windsor, California. Specifically, they selected Brazilian Ebony, an exotic species of unusually hard wood, for its appearance and durability.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Newport Beach Attorneys John Toohey and Nick Rodriguez Receive Full Defense Verdict
July 31, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara is pleased to report that Partner John Toohey and Senior Associate Nicholas Rodriguez received a complete defense verdict after a 5-week jury trial in Orange County Superior Court.
The case involved a multimillion-dollar home in Orange County. Plaintiff had originally suffered a water loss throughout areas of the home. Our client, an Orange County restoration and construction company, was hired to provide on-going estimates and perform demolition. Plaintiff claimed that, in the course of the demolition process, asbestos containing material was disturbed and spread resulting in contamination throughout home. Plaintiff claimed contractor negligence and breach of contract against our client. Plaintiff sought millions against our client in general and special damages for whole home restoration and other related general damages. The jury found in complete favor of our client on all allegations and awarded zero dollars to the opposing party.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Mediating is Eye Opening
September 17, 2015 —
Christopher G. Hill – Construction Law MusingsAs anyone that reads this construction law blog on any sort of regular basis knows, I am a big advocate for mediation in most cases (construction or otherwise). I took this truly to heard about four years ago when I decided to go through the training and mentorship to become a certified mediator here in Virginia. This training led to many opportunities to act as a mediator in the General District Courts here in Virginia and has recently given me the great privilege of helping parties that were not court referred resolve their disputes.
I’ve discussed this first category of mediations at other times here at Musings, but it is the second category that has opened my eyes lately. The non-court referred mediations are those where the parties actively seek out the assistance of a mediator because they, like me, know that more often than not the control and ability to come to some form of negotiated solution (not to mention short circuiting the litigation process in a way that saves money) is a better way to go than to go through the expensive (though as a construction attorney I acknowledge sometimes necessary) process of litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Joint Venture Dispute Over Profits
January 27, 2020 —
David R. Cook - AHC Construction and Procurement BlogA recent Georgia Court of Appeals case demonstrates the risk of joint ventures failing to carefully define accounting rules in their joint venture agreement. Two trade contractors teamed up to accomplish certain tasks on a job at a wastewater lift station at Fort Gordon. A joint venture agreement provided for an equal split of the profits and losses. Unfortunately, the parties did not define “profit,” and particularly did not define what cost would be deducted in calculating profit. They disputed in particular whether certain large payments to individuals and 15% overhead charges should be deducted in calculating profits.
One party presented the expert testimony of an accountant while the other did not. The party presenting expert testimony asked the court to dismiss the other party’s claim because it was not supported by expert testimony of an accountant. The trial court granted the motion and dismissed the claim.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Defining Constructive Acceleration
March 22, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to the definition of “constructive acceleration,” the case of Fraser Const. Co. v. U.S., 384 F.3d 1354 (Fed.Cir. 2004) is a cited case and contains an instructive definition, quoted below, for proving a constructive acceleration claim.
In a nutshell, a constructive acceleration claim is when the contractor incurs added costs for trying to complete the contract on time when it should be provided extensions of time to perform based on excusable delay (i.e., delay not caused by the contractor). These added costs could be bringing in additional supervision to manage the work, adding manpower to perform the work, working overtime, working weekends, adding more shift work, stacking trades, etc. However, just because a contractor claims they have been constructively accelerated does not make it so. The contractor has to actually ask for an extension of time based on an excusable delay and the owner either denied the extension or unreasonably sat on the request for an extension of time; thus, the contractor incurred significant costs to accelerate in order to finish the project on time because it was deprived of a requested time extension for excusable delay.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
COVID-19 Could Impact Contractor Performance Bonds
March 30, 2020 —
Ben Williams & MG Surety - Construction ExecutiveAs COVID-19 continues to expand around the United States and the world, it may only be a matter of time before U.S. construction projects are affected by the virus. Performance bonds guarantee that a project will be completed by a contractor according to the contract. However, what if a contractor cannot complete a project on time due to widespread disease? What, if any, impact could the virus have on a contractor’s surety bond program?
Risk Factors
Several risks associated with the virus could trigger a performance bond claim.
1. Materials. The Chinese account for a large supply of construction materials, including steel, copper, cabinetry, etc. An inability to obtain these materials could significantly delay or stop a project all together. Even if a contractor is able to obtain them from other sources, it may be at a significantly higher cost than they put into the bid.
2. Labor. There is already a shortage of qualified labor in the construction industry. Additionally, construction already lends itself to the spreading of viruses; workers are often in close proximity, handling common materials, and they may not have an easily accessible place to wash their hands. Furthermore, even though many now have paid sick leave, there is often pressure not to use it. These things could magnify the labor shortage and make it difficult to complete projects on time.
3. Safety. Finally, the world is having a serious shortage of respirators. Because of widespread panic, many people have been purchasing N95 respirators—so much that the Surgeon General has asked people to stop buying them. It has created a shortage for people who really need them, like contractors. If contractors can’t get these safety masks, certain trades will either be unable to work, or risk continuing the project without masks, which would endanger workers and open them up to OSHA penalties.
Reprinted courtesy of
Ben Williams and MG Surety, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Williams may be contacted at
benw@mgsuretybonds.com
Free Texas MCLE Seminar at BHA Houston June 13th
May 29, 2014 —
Beverley BevenFlorez-CDJ STAFFThere are just two weeks remaining to sign up for Bert L. Howe & Associate’s next Texas MCLE seminar, THE RESIDENTIAL CONSTRUCTION PROCESS & CONSTRUCTION DEFECT LITIGATION.
This activity will be presented on Friday, June 13th at noon, at BHA’s Houston offices, located at:
800 Town & Country Blvd.
Suite 300
Houston, TX 77024
There is no cost for attendance at this seminar and lunch will be provided.
This course has been approved for Minimum Continuing Legal Education credit by the State Bar of Texas Committee on MCLE in the amount of 1.0 credit hours, of which 0.0 credit hours will apply to legal ethics/professional responsibility credit. The seminar will be presented by Don MacGregor, general contractor and project manager.
Water intrusion through doors, windows and roofing systems, as well as soil and foundation-related movement, and the resultant damage associated therewith, are the triggering effects for the vast majority of homeowner complaints today and serve as the basis for most residential construction defect litigation. The graphic and animation-supported workshop/lecture activity will focus on the residential construction process from site preparation through occupancy, an examination of associated damages most often encountered when investigating construction defect claims, and the inter-relationships between the developer, general contractor, sub trades and design professionals. Typical plaintiff homeowner/HOA expert allegations will be examined in connection with those building components most frequently associated with construction defect and claims litigation.
The workshop will examine:
*Typical construction materials, and terminology associated with residential construction
*The installation process and sequencing of major construction elements, including interrelationship with other building assemblies
*The parties (subcontractors) typically associated with major construction assemblies and components
*An analysis of exposure/allocation to responsible parties.
Attendance at THE RESIDENTIAL CONSTRUCTION PROCESS & CONSTRUCTION DEFECT LITIGATION seminar will provide the attendee with:
*A greater understanding of the terms and conditions encountered when dealing with common construction defect issues
*A greater understanding of contractual scopes of work encountered when reviewing construction contract documents
*The ability to identify, both quickly and accurately, potentially responsible parties
*An understanding of damages most often associated with construction defects, as well as a greater ability to identify conditions triggering coverage
Course #: 901290467 / Sponsor #: 14152. To register for the event, please email Don MacGregor at dmac@berthowe.com. If you have any questions, please feel free to contact Don at (800) 482-1822 (office) or (714) 713-4956 (cell).
Read the court decisionRead the full story...Reprinted courtesy of