Business Risk Exclusions (j) 5 and (j) 6 Found Ambiguous
April 22, 2019 —
Tred R. Eyerly - Insurance Law HawaiiReversing the district court's grant of summary judgment in favor of the insurer, the Tenth Circuit found that exclusions (j) 5 and (j) 6 were ambiguous as applied to the facts of the case. MTI, Inc. v. Emplrs. Ins. Co., 2019 U.S. App. LEXIS 2543 (10th Cir. Jan. 25, 2019).
Western Farmers Electrical Cooperative (WFEC) owned cooling towers which were serviced by MTI, Inc. Wausau provided a CGL policy to MTI.
In 2011, MTI found that anchor bolts in Cooling Tower 1 were corroded. WFEC hired MTI to make repairs by installing new anchor castings with anchor bolts and anchor adhesive.
On May 23, 2011, MTI employees removed all of the corroded anchor bolts in Tower 1. Because the adhesive applicator had not yet arrived, MTI did not immediately install new anchor bolts. On the night of May 24, strong winds struck the tower, causing it to lean and several structural components broke. Due to the extent of the structural damage, removal and replacement of the tower was determined to be the only viable option.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Claim for Punitive Damages Based on Insurers' Alleged Bad Faith Business Practices Fails
September 05, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss the bad faith claim based upon allegations of a general business practice of acting recklessly toward an insured's rights under the policy. Sandpiper Isle Condo. Ass'n v. Empire Indem. Ins. Co., 2022 U.S. Dist. LEXIS 114279 (M.D. Fla. June 28, 2022).
Sandpiper suffered property damage from Hurricane Irma. Empire accepted the claim but there was disagreement on the value of the damage. An appraisal issued an award in favor of Sandpiper but Empire failed to pay the benefits for two years.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
When an Intentional Act Results in Injury or Damage, it is not an Accident within the Meaning of an Insurance Policy Even When the Insured did not Intend to Cause the Injury or Damage
June 06, 2022 —
Gary L. LaHendro - Haight Brown & Bonesteel LLPIn
Maryam Ghukasian v. Aegis Security Insurance Company (No. B311310, filed April 14, 2022, and certified for publication on May 5, 2022), the Court of Appeal of the State of California, Second Appellate District held that Maryam Ghukasian’s insurer, Aegis Security Insurance Company (“Aegis”), had no duty to defend her in an underlying lawsuit alleging she cleared land and cut trees on her neighbors’ property without their consent. The appellate court explained Ms. Ghukasian’s acts of intentionally cutting the trees and clearing the land were not accidental for purposes of insurance coverage, even if she acted on the good faith but mistaken belief the trees were on her property.
Ms. Ghukasian owns a home in Glendale, California. She purchased a homeowner’s insurance policy from Aegis for the policy period of June 13, 2018 to June 13, 2019 (the “Aegis Policy”). In August 2018, Ms. Ghukasian hired a contractor to clear and cut trees she believed were on her property. However, the trees were on the property of her neighbors, Vrej and George Aintablian.
Read the court decisionRead the full story...Reprinted courtesy of
Gary L. LaHendro, Haight Brown & Bonesteel LLPMr. LaHendro may be contacted at
glahendro@hbblaw.com
Sierra Pacific v. Bradbury Goes Unchallenged: Colorado’s Six-Year Statute of Repose Begins When a Subcontractor’s Scope of Work Ends
November 03, 2016 —
Luke Mecklenburg – Snell & Wilmer Real Estate Litigation BlogIt’s official: the October 20, 2016 deadline to petition for certiorari to the Colorado Court of Appeals on its decision in Sierra Pacific Industries, Inc. v. Bradbury has passed, so it appears that decision will stand.
In Sierra Pacific, the Court of Appeals held as a matter of first impression that the statute of repose for a general contractor to sue a subcontractor begins to run when a subcontractor’s scope of work is substantially complete, regardless of the status of the overall project. Sierra Pac. Indus., Inc. v. Bradbury, 2016 COA 132, ¶ 28, ___ P.3d ___. The Court of Appeals interpreted the statute of repose in C.R.S. section 13-80-104, which requires that “all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of any improvement to real property” must be brought within six years of substantial completion of that improvement. C.R.S. § 13-80-104(1)(a). Recognizing that “an improvement may be [to] a discrete component of an entire project” under Shaw Construction, LLC v. United Builder Services, Inc., 296 P.3d 145 (Colo. App. 2012), the Court of Appeals determined that “a subcontractor has substantially completed its role in the improvement at issue when it finishes working on the improvement.” Sierra Pac., 2016 COA at ¶¶ 20, 28. In doing so, it rejected Sierra Pacific’s argument that the statute could be tolled under the repair doctrine “while others worked to repair [the subcontractor’s] ‘improper installation work and flawed repair work.’” Id. at ¶ 29. Because six years had undisputedly passed since the subcontractor completed its scope of work when Sierra Pacific filed suit against it, the Court of Appeals affirmed the trial court’s order granting the subcontractor’s motion for summary judgment under Section 13-80-104(1)(a).
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & Wilmer Real Estate Litigation BlogMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Court Strikes Down Reasonable Construction Defect Settlement
December 20, 2012 —
CDJ STAFFThe Court of Appeals of Washington has struck down a construction defect settlement between a building owner and the companies she hired to repair the siding, among other repairs to bring the building up to code. Yuan Zhang hired Hawk Construction LLC to do repair work. Hawk, in turn, hired Ready Construction LLC for some aspects of the project. Hawk and Ready were both insured by Capital Specialty Insurance Corporation.
There were several problems with Ready’s work. After removing old siding, they did not protect the building, nor did they remove all of the damaged layers. Ready covered, but did not fix, a mildew problem under the old siding. When new siding was reattached, the nails used were too short to adequately attach it.
After paying for an inspection of the work, Zhang had Hawk and Ready begin the repairs again, but the work was abandoned without being completed. Zhang sued Hawk for breach of contract. Hawk then sued Ready, claiming that “Ready was liable to Hawk to the extent that Hawk was liable to Zhang.” Capitol retained defense for both contractors.
Zhang settled with Hawk, in an agreement that gave her “the right to collect and/or pursue all costs and attorney fees paid by Hawk or its insurance company defending against the Zhang’s claims and pursuing claims against Ready.” Subsequently, she also settled with Ready. Both companies ceased operations.
Zhang had the settlements reviewed by a court, which concluded that the settlements were reasonable. Capital was allowed to appeal, claiming that the settlement included costs that were Zhang’s responsibility. The appeals court did not examine the question of the reasonableness of the settlement, concluding that Capitol’s interests were relevant only to “questions of bad faith, collusion, and fraud.”
In the case of Zhang, the court concluded that the relationship between Zhang and her former contractors was collusive. The court noted that “bad faith or collusion may exist when the evidence indicates a joint effort to create, in a non-adversarial atmosphere, a resolution beneficial to both parties, yet highly prejudicial to the insurer as intervener.” The court noted that both companies had minimal assets which were, in any case, exempted from the agreement. Further, the court found that the agreements failed to determine “what amount of the repairs related to preexisting water damage.” Zhang’s calculation of costs also included her expenses for architectural and engineering services, which the court points out, “where always Zhang’s costs to bear.”
The court concluded that “the overall structure of the settlements is highly probative of collusion, fraud, or bad faith.” Zhang’s agreements with Hawk and Ready allowed her to collect compensation from Hawk and then collect Ready’s compensation to Hawk for their portion of the settlement, allowing Zhang to collect the monies twice. Further, she was allowed to pursue Capitol for Hawk’s attorney expenses, even though Hawk had none. “The right to recover Hawk’s fees merely set up a windfall recovery for Zhang.” The court described the agreements among Zhang, Hawk, and Ready as “precisely the type of manipulation [the law] is intended to preclude.”
Read the court decisionRead the full story...Reprinted courtesy of
Four Key Steps for a Successful Construction Audit Process
May 03, 2021 —
Ronald L. Williams, Fox Rothschild LLP - ConsensusDocsThe implications of the audit provisions contained in construction agreements between owners and contractors owners extend far beyond post-completion bean counting, and can affect multiple aspects of a project, from project administration to relationships with key subcontractors. It is critically important that contractors give audits the attention they deserve by taking the following four steps. First, invest the time to negotiate the audit provisions that ultimately appear in contracts with the owner. Second, ensure that the project team and the owner’s project auditors engage in timely communication during construction. Third, make certain that post-completion audit administration is prompt and complete. And finally, carefully draft adequate “flow-down” provisions with subcontractors and vendors so that they understand and comply with their contractual obligations, as well as the expectations of the contractor and owner. All four aspects are critical, and if not addressed effectively can undermine the profitability of the contract, and contractors’ business relationships with both upstream and downstream parties.
Negotiations
At the outset of contract negotiations, a contractor must completely understand the owner’s audit process expectations. An owner’s understanding of the audit process and its potential pitfalls depends on their own experience, as well as the knowledge of their personnel, including internal audit members and external auditors. Negotiations, which like the audit itself need not be adversarial, can be educational for both the owner and any representatives involved.
Read the court decisionRead the full story...Reprinted courtesy of
Ronald L. Williams, Fox Rothschild LLPMr. Williams may be contacted at
rwilliams@foxrothschild.com
Going Digital in 2019: The Latest Technology for a Bright Future in Construction
February 18, 2019 —
Jim Romeo - Construction ExecutiveThe spectrum of technology available to today’s contractors is wide and deep. This techno-ecosystem will change just about every operational tick and tock needed to build world-class projects—from where and how people work to what equipment they use and how they record payments.
“Generally speaking, the use of technology in construction is surging, particularly in the past three to five years,” says Chris Amato, principal and national advisory leader for the Chicago-based management consultancy Grant Thornton. “It’s becoming the cost of doing business; every player, at some point or another, is going to need to embrace it to some degree. The key questions are where to start, where to invest and how to minimize risk.”
Reprinted courtesy of
Jim Romeo, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
The Pandemic of Litigation Sure to Follow the Coronavirus
March 30, 2020 —
Aaron Lovaas - Newmeyer DillionAs the Coronavirus crisis persists, America’s richly diverse private business sector finds itself increasingly subject to unprecedented governmental orders and restrictions that were unheard of only a few weeks ago. While the various “shutdown,” “shelter in place,” and “non-essential business” orders all aim to protect the public health, there is no doubt that the wave of litigation to follow is already swelling.
Business interruption, civil authority, and cyber insurance coverages have already been widely discussed as issues certain to be litigated over the coming months and beyond. Additionally, breach of contract litigation is likely to spike as parties attempt to recoup their losses from canceled events, unfulfilled purchase commitments and other unmet obligations.
Moreover, regional and national businesses are now in the difficult position of managing their respective affairs to comply with a patchwork of executive orders that are inconsistent from state to state. And, as the pandemic wears on, many are questioning the authority under which some of these executive orders and emergency regulations are being issued in the first place. Indeed, constitutional challenges are almost certain to follow as the business community reframes the characterization of their losses into notions of unconstitutional takings of private property and governmental impairment of private contract rights.
Read the court decisionRead the full story...Reprinted courtesy of