Waiver of Subrogation Enforced, Denying Insurers Recovery Against Additional Insured in $500 Million Off-Shore Oil Rig Loss
September 30, 2019 —
Sergio F. Oehninger & Daniel Hentschel - Hunton Insurance Recovery BlogThe United States District Court for the Southern District of Texas recently rejected a claim by a group of insurance companies (“Underwriters”) against American Global Maritime Inc. for more than $500 million that the Underwriters paid the named insured under an Off-Shore Construction Risk insurance policy for losses resulting from the an alleged off-shore oil rig failure.
The action arose out of alleged construction defects related to Chevron’s “Big Foot” oil-drilling platform in the Gulf of Mexico. Chevron hired American Global to be the marine warranty surveyor responsible for reviewing and certifying the project’s specifications and materials. American Global issued the certificate of approval required for the project to proceed; however, during the attempted installation of the platform in 2015, it was alleged that parts from the structure fell to the sea floor. The Underwriters paid more than $500 million in connection with the incident under an Off-Shore Construction insurance policy they had issued to Chevron.
After paying the claim, the Underwriters filed a negligence action against American Global and other contractors involved in the project.
Reprinted courtesy of
Sergio F. Oehninger, Hunton Andrews & Kurth and
Daniel Hentschel , Hunton Andrews & Kurth
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Prevailing Payment Bond Surety Entitled to Statutory Attorneys’ Fees Even if Defended by Principal
January 09, 2023 —
Garret Murai - California Construction Law BlogFor contractors involved in California public works projects the scenario is not uncommon: The general contractor awarded the public works project is required to obtain a payment bond for the benefit of subcontractors and suppliers and the payment bond surety issuing the payment bond requires the general contractor to defend and indemnify the surety from and against any claims against the payment bond.
In Cell-Crete Corporation v. Federal Insurance Company, 82 Cal.App.5th 1090 (2022), the 4th District Court of Appeal examined whether a payment bond surety, who prevails in a claim against the payment bond, is entitled to statutory attorneys’ fees when the party actually incurring the attorneys’ fees was the general contractor, pursuant to its defense and indemnity obligations, as opposed to the surety itself.
The Cell-Crete Case
General contractor Granite Construction Company was awarded a public works contract issued by the City of Thermal known as the Airport Boulevard at Grapefruit Boulevard and Union Pacific Railroad Grade Separation Project. We’ll just call it the “Project.” Subcontractor Cell-Crete Corporation entered into a subcontract with Granite for lightweight concrete and related work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Cameron Pledges to Double Starter Homes to Boost Supply
March 05, 2015 —
Svenja O’Donnell – Bloomberg(Bloomberg) -- Prime Minister David Cameron pledged to double the number of homes built for first-time buyers by the end of the next parliamentary term in a bid to tackle Britain’s housing shortage.
In a speech in Colchester, Essex, on Monday setting out the final part of his Tory party’s six-point campaign platform for the May 7 election, Cameron said 200,000 properties will be built by 2020 under his starter-homes plan. Prices of the homes, only available to first-time buyers under the age of 40, will be capped at 450,000 pounds ($692,000) in London and 250,000 pounds outside the capital. Reduced planning constraints will make it easier for developers to cut building costs, allowing the homes to be sold at a 20 percent discount.
Read the court decisionRead the full story...Reprinted courtesy of
Svenja O’Donnell, BloombergMs. O’Donnell may be contacted at
sodonnell@bloomberg.net
State Audit Questions College Construction Spending in LA
August 17, 2011 —
CDJ STAFFA state audit of the Los Angeles Community College District found many problems with their construction spending. Their report, as described in the Los Angeles Times, found construction money spent for other purposes, such as promotional photography and public relation tours, $28.3 million spent on projects that were later cancelled, and oversight committees that provided no oversight.
Earlier this year, the LA Times ran a series of articles detailing problems with the Los Angles Community College District’s construction program. The LA Times reported that the State Controller’s audit reached many of the same conclusions.
The Community College District disputed the findings.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
AIA Releases State-Specific Waiver and Release Forms
September 05, 2022 —
Garret Murai - California Construction Law BlogThe American Institute of Architects (AIA) has released a new series of state-specific waiver and release forms including forms for California. The new
California-specific forms are:
- G901CA-2022 – California Conditional Waiver and Release on Progress Payment
- G902CA-2022 – California Unconditional Waiver and Release on Progress Payment
- G903CA-2022 – California Conditional Waiver and Release on Final Payment
- G904CA-2022 – California Unconditional Waiver and Release on Final Payment
California is one of twelve states – including Arizona, Florida, Georgia, Massachusetts, Michigan, Mississippi, Missouri, Nevada, Texas, Utah and Wyoming – which regulate waiver and release forms on construction projects. California’s waiver and release statute, which is codified at Civil Code section 8120 et seq., sets forth specific language which should be used in waivers and releases. While the exact language set forth under California’s waiver and release statutes does not need to be used, the statute provides that the language must be “in substantially” the same form, and most people follow the statutory language exactly.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
HP Unveils Cheaper, 3-D Printing System to Spur Sales
November 05, 2014 —
Jack Clark - BloombergHewlett-Packard Co. (HPQ) unveiled a new 3-D-capable computer and speedier 3-D printer technology as it prepares to spin off its personal-computer and printer businesses into a stand-alone company.
The company today introduced Sprout, an $1,899 computer that lets people scan and manipulate 2-D and 3-D objects. It will be available early next month online and in some U.S. stores. Hewlett-Packard also said new 3-D printer technology will make the process cheaper and faster than competitors.
The Palo Alto, California-based company is betting that 3-D technology will help revitalize sales and spur growth in the printer industry. More than 2.3 million 3-D printers will ship in 2018, up from about 108000 this year, according to researcher Gartner Inc. Earlier this month, Hewlett-Packard said it would split into two companies by late 2015, with one focused on corporate hardware services and the other -- dubbed HP Inc. -- on PCs and printers.
Read the court decisionRead the full story...Reprinted courtesy of
Jack Clark, BloombergMr. Clark may be contacted at
jclark185@bloomberg.net
AAA Revises Construction Industry Arbitration Rules and Mediation Procedures
July 22, 2024 —
Patrick McKnight - The Dispute ResolverThe American Arbitration Association (AAA) recently revised its Construction Industry Arbitration Rules and Mediation Procedures (“the Rules”). Several notable changes went into effect March 1, 2024, involving the scope of confidentiality, regular and fast track procedures, and updates to certain monetary thresholds.
I. Revisions to Regular Track Procedures
Rule 45: Confidentiality
For the first time, confidentiality is now the default standard. Under Rule 45(a), arbitrators must keep all matters confidential unless otherwise required by law, court order or the agreement of the parties. Rule 45(b) allows a mediator to issue confidentiality orders and “take measures for protecting trade secrets and confidential information.”
Rule 7: Consolidation and Joinder
Under the new provisions, consolidation and joinder requests must be filed before confirmation of the Merits Arbitrator’s appointment. This language eliminates a previous option that allowed confirmation up to 90 days after filing of such requests. A failure to timely respond to a joinder request will result in a waiver of objections. Now, a party must establish both good cause and prejudice for a successful joinder request after confirmation of the arbitrator.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Dreyer v. Am. Natl. Prop. & Cas. Co. Or: Do Not Enter into Nunn-Agreements for Injuries that Occurred After Expiration of the Subject Insurance Policy
January 20, 2020 —
Jean Meyer - Colorado Construction LitigationWhile Nunn-Agreements[1] may be appealing for both plaintiffs and defendants where an insurer unreasonably fails to defend a lawsuit, a recent opinion from The Honorable Marcia Krieger in the United States District Court of Colorado[2] (“Opinion”) demonstrates the importance of first confirming that there exists a viable insurance claim before proceeding with such a Nunn- Agreement.
The facts giving rise to the Opinion were as follows. In March 2015, a Homeowner couple (the “Homeowners”) suffered damages to their home resulting from a brushfire. Fortunately, the Homeowners were insured, they submitted their claim to their homeowners’ insurance carrier which was in effect at the time of the brushfire (the “Insurance Carrier”), and the Insurance Carrier paid the claim. Ostensibly as part of the Homeowners’ remediation efforts to their home they removed a large bush which left a hole in the ground. After paying the claim, in August 2015 the Insurance Carrier cancelled or elected not to renew the Homeowners’ policy. In October 2015, a repairman working on the Home (the “Repairman”) was injured after his ladder fell over allegedly because of the hole in the ground caused by the bush that had been removed.
As a result of injuries caused by the fall from the ladder, the Repairman brought suit against the Homeowners. In response to the Repairman’s claim, the Homeowners again tendered to their Insurance Carrier. This time, however, the Insurance Carrier denied coverage on the basis that the Repairman’s injuries occurred after the expiration of the relevant policy. Without insurance coverage, the Homeowner’s entered into a Nunn-Agreement with the Repairman, conceding liability, and assigning any claims they might have had against the Insurance Carrier in lieu of execution of any judgment against the Homeowners.
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at