Unqualified Threat to Picket a Neutral is Unfair Labor Practice
January 08, 2019 —
Wally Zimolong - Supplemental ConditionsOn December 27, 2018, the National Labor Relations Board enforced a decades old policy that a union’s unqualified threat to picket a neutral employer at a “common situs” a/k/a a construction site is a violation of the National Labor Relations Act.
Background
The case involved area standards picketing by the IBEW of a project owned by the Las Vegas Convention and Visitors Authority (LVCVA). The IBEW sent a letter to various affiliated unions who were working on the project advising them of its intent to engage in area standards picketing at the project directed to the merit shop electrical subcontractor performing work there. The IBEW also sent a copy of the letter to the LVCVA.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
City Development with Interactive 3D Models
October 23, 2018 —
Aarni Heiskanen - AEC BusinessThe Finnish city of Hyvinkää has developed a unique internet service for collaborative 3D city planning. It gives real estate owners, investors, developers, designers, authorities, and citizens easy-to-use tools to publish their 3D plans and ideas for the built city environment.
Participants can comment on the 3D plans directly in the city model. The 3D app is integrated with Facebook, which enables further conversation.
Building the 3D City Model
Päivi Tiihonen is the manager of the information services unit of the city’s technical and environmental sector. The city started building a browser-based 3D city model when Tiihonen assumed her position in 2014.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Updates to the CEQA Guidelines Have Been Finalized
February 06, 2019 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThe California Natural Resources Agency (CNRA) recently posted final adopted text for amendments to the CEQA Guidelines. The result of over five years of development efforts by the Governor’s Office of Planning & Research and CNRA, the amendments are the most comprehensive update to the CEQA Guidelines since 1998. In “Natural Resources Agency Finalizes Updates to the CEQA Guidelines,” Pillsbury environmental attorneys Norman F. Carlin, Kevin Ashe and Eric Moorman explore the wide range of issues covered in the amendments, including the new Vehicle-Miles-Traveled (VMT) methodology for analyzing transportation impacts; use of regulatory standards as significance thresholds; environmental baselines; and numerous procedural and technical improvements.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Court Rejects Efforts to Limit Scope of Judgment Creditor’s Direct Action Under Insurance Code Section 11580
May 01, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Ins. Co. of St. of PA v. Amer. Safety Indemnity Co. (No. B283684, filed 3/1/19) (“ICSOP”), a California appeals court rejected one insurer’s efforts to limit the scope of another insurer’s direct action as a judgment creditor under Insurance Code section 11580(b)(2).
In ICSOP, homeowners filed a claim in arbitration against their general contractor alleging damages from subsidence. While the arbitration was pending, the general contractor filed suit against the grading subcontractor seeking indemnity and contribution. The complaint attached the homeowners’ complaint in arbitration pleading damages of $2.3 million, and alleged that the subcontractors had a duty to indemnify for those damages. The arbitrator awarded the homeowners $1.1 million.
The general contractor was insured by plaintiff ICSOP, which paid the arbitration award. A default judgment was entered against the grading subcontractor for $1.5 million, that included both the arbitration award plus $356,340 for the general contractor’s attorney’s fees. American Safety insured the grading subcontractor but refused to indemnify ICSOP. ICSOP then sued American Safety on the default judgment, pursuant to Insurance Code section 11580(b). The trial court granted summary judgment for ICSOP and the appeals court affirmed.
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP Read the court decisionRead the full story...Reprinted courtesy of
Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
California Supreme Court Finds Negligent Supervision Claim Alleges An Occurrence
July 21, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAnswering a question posed by the Ninth Circuit, the California Supreme Court found that a suit against a employer for negligent hiring, retention and supervision of a employee who intentionally injures a third party alleges an occurrence under a CGL policy. Liberty Surplus Co. Corp. v. Ledesma & Meyer Construction Co., 2018 Cal. LEXIS 4063 (Cal. June 4, 2018)
Ledesma & Meyer Construction Company (L&M) contracted with the school district to manage a construction project at a middle school. L&M hired Darold Hecht as an assistant superintendent on the project. In 2010, Jane Doe, a 13-year-old student at the school, sued alleging that Hecht had sexually abused her. Doe’s claims included a cause of action against L&M for negligent hiring, retaining, and supervising Hecht.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Update: Amazon Can (Still) Be Liable in Louisiana
December 31, 2024 —
Michael Ciamaichelo - The Subrogation StrategistOn November 25, 2024, in Pickard v. Amazon.com, Inc., No. 5:20-cv-01448, 2024 U.S. Dist. LEXIS 215377, the United States District Court for the Western District of Louisiana (District Court) ruled that Amazon.com, Inc. (Amazon) could be liable for manufacturer-seller liability under the Louisiana Products Liability Act (LPLA) for a defective product sold by a third-party seller through the “Fulfillment by Amazon” program (FBA). The court also dismissed two tort claims against Amazon as follows: (i) Amazon does not qualify as a “seller” for purposes of non-manufacturer seller liability (because passing title is required for that claim); and (ii) there is insufficient evidence to prove the decedent, Archie Pickard (Pickard), relied on Amazon’s safety practices when purchasing the defective product, precluding a claim for negligent undertaking.
Background
Pickard died from injuries sustained in a house fire allegedly caused by a defective battery charger he purchased on Amazon. Jisell, a Chinese company and a third-party seller, manufactured and sold the charger. Amazon never took title to the charger but stored it in its warehouse and delivered it to Pickard through the FBA. Pickard’s children filed a wrongful death lawsuit against Amazon alleging three claims: (i) manufacturer-seller liability under the LPLA; and tort-based claims of (ii) non-manufacturer seller liability and (iii) negligent undertaking. After Amazon moved for summary judgment on all claims, the District Court certified questions to the Supreme Court of Louisiana (Supreme Court) seeking guidance as there was minimal guidance regarding the application of products claims to online marketplaces.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
Encinitas Office Obtains Complete Defense Verdict Including Attorney Fees and Costs After Ten Day Construction Arbitration
May 23, 2022 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Vik Nagpal and Associate Attorney Tim McNulty of the Encinitas office recently obtained a substantial victory on behalf of BWB&O’s client after a 10-day binding construction arbitration before a three-arbitrator panel of the American Arbitration Association.
BWB&O’s client was sued by the Owner of a commercial office building related to a multimillion-dollar tenant improvement project in San Diego. The Owner asserted construction defect damages, delay damages, architectural negligence, fraudulent billing practices and consequential damages of $3.6 million dollars. BWB&O’s client claimed breach of contract damages against the owner for failure to pay invoices.
The Owner who had substantial financial resources and a personal spite against the general contractor, unreasonably pursued the case with an extensive team of lawyers and experts. At an earlier full-day mediation, the owner rejected a reasonable settlement offer which included a settlement payment to the Owner and the client’s agreement to dismiss their affirmative claim for damages.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP