Illinois Appellate Court Finds Insurer Estopped From Denying Coverage Where Declaratory Judgment Suit Filed Too Late
August 07, 2018 —
TLSS Insurance Law BlogIn an unpublished opinion from the Illinois Appellate Court, Country Mutual Insurance Co. v. Badger Mutual Insurance Co., 2018 IL App (1st) 171774-U, the court held that because an insurer breached its duty to defend and failed to file a declaratory judgment action before the underlying lawsuit was resolved, it was estopped from denying coverage for the default judgment entered against its insured in the underlying lawsuit.
The underlying lawsuit concerned a claim that plaintiff’s property allegedly sustained damage when the insured performed work on the plaintiff’s residence. The complaint in the underlying lawsuit did not specifically identify when the property damage occurred. However, the complaint did state that the insurer’s investigator alerted it in 2010 that the property damage was due to the insured’s faulty work during the policy period. The insurer did not defend the insured during the action and a default judgment was entered against the insured.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Straus & Shrewsberry LLP
New WA Law Caps Retainage on Private Projects at 5%
May 29, 2023 —
Brett M. Hill & Ryanne S. Mathisen - Ahlers Cressman & Sleight PLLCThis month, Governor Jay Inslee signed into law a new statute that caps retainage on private construction projects to five percent (5%), provides a mechanism for subcontractors to get paid their retainage prior to project completion, and allows for contractors and subcontractors to post a retainage bond and get paid their retainage early. For those interested in reading the full text of this new law, the statute can be found
here.
The new statute goes into effect on July 23, 2023. Under the statute, when a contractor or subcontractor considers their work under a contract subject to retainage complete, they may notify the party they contracted to perform the work for. Within 15 days of receiving the notice of completion of work, the party receiving the notice must respond with either (1) notice of acceptance of work or (2) notice of uncompleted items to the contractor or subcontractor.
If the party receiving notice does not provide notice of uncompleted items within 15 days or fails to respond to the notice of completion entirely, the unpaid retainage will begin to accrue interest at a rate of one percent (1%) per month, 30 days after the initial 15-day period. However, this interest will not accrue against a contractor who has not been paid the retainage by an upper-tier contractor or owner until payment has been received, so long as that contractor has submitted its subcontractor’s notice of completion to the upper-tier contractor or owner within 30 days of receipt.
Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLC and
Ryanne S. Mathisen, Ahlers Cressman & Sleight PLLC
Mr. Hill may be contacted at brett.hill@acslawyers.com
Ms. Mathisen may be contacted at ryanne.mathisen@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
The Colorado Construction Defect Reform Act Explained
December 11, 2013 —
CDJ STAFFColorado passed its Construction Action Defect Reform Act twelve years ago, but as Anne K. McMichael of Zupkus & Angell, PC, points out, “while portions of this act are reasonably straightforward, several of the sections are subject to ongoing debate as to how these concepts should be applied to achieve fair and unbiased results.” The process for a construction defect claim under the CDARA starts with filing a notice of defects, after which the construction professional is permitted to inspect the alleged defect. The construction professional can then offer to repair or settle.
The law offers protections for construction professionals who follow through with the process. But, as Ms. McMichael notes, these are denied to construction professionals who do not make offers, fail to meet settlement agreements, or offers a settlement that is insufficient for repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Homebuilder Predictions for Tallahassee
October 10, 2013 —
CDJ STAFFThe cost of putting up a new home in Tallahassee has risen, but Joe Manausa thinks that builders might be putting up homes that will cost more than home buyers are able to pay. He notes that permits and sales are up, but numbers are still well below those in 2006.
Mr. Manusa thinks that Tallahassee could face “a need (demand) for homes priced below $300,000, but a glut of supply for those priced above $300,000.” He says that home builders “need to target construction opportunities below that price point.”
He notes that average price of new construction is $272,000, but resales are going for $161,000, which puts quite a premium on a new home.
Read the court decisionRead the full story...Reprinted courtesy of
NJ Court Reaffirms Rule Against Coverage for Faulty Workmanship Claims and Finds Fraud Claims Inherently Intentional
September 20, 2021 —
Anthony L. Miscioscia & Frank J. Perch, III - White and Williams LLPAwarding summary judgment to an insurer under both liability and directors & officers (D&O) coverage parts, a New Jersey trial court reaffirmed the principle that claims of defective workmanship without resulting “property damage” are not covered under a general liability policy, and further dismissed claims for fraud and breach of fiduciary duty, finding that such claims were inherently intentional and do not state a covered “occurrence.”
In Velez v. AR Management Company, et al., 2021 N.J. Super. Unpub. LEXIS 1675 (Law Div. Bergen Co. Aug. 10, 2021), owners of a condominium unit rebuilt after a fire sued the condominium association, several association board members, the association’s property management company and the general contractor for the reconstruction work. The owners’ suit alleged faulty workmanship and incomplete repairs. In addition, the owners asserted fraud and breach of fiduciary duty claims against the management company, alleging conflicts of interest and self-dealing between the management company and the general contractor, which had common ownership.
In a third-party complaint, the management company sought coverage from the condo association’s liability and D&O insurer. The court dismissed the D&O coverage claim, noting that the management company was not a director or officer or otherwise entitled to insured status for the D&O coverage part.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Frank J. Perch, III, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Mr. Perch may be contacted at perchf@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Commonwealth Court Holds That Award of Attorney's Fees and Penalties is Mandatory Under the Procurement Code Upon a Finding of Bad Faith
October 29, 2014 —
William J. Taylor and Michael Jervis – White and Willams LLPIn a decision regarding a payment claim by a highway contractor against the City of Allentown, the Commonwealth Court of Pennsylvania has held that an award of attorney's fees and penalties is mandatory under the terms of the Pennsylvania Procurement Code, 62 Pa.C.S. § 3901 et seq., upon a finding of bad faith by the non-paying government agency, even though the statute only states that a court “may” award such fees and penalties.
In A. Scott Enterprises, Inc. v. City of Allentown, Cmwlth. Ct. No. 2163 C.D. 2013, the plaintiff, A. Scott Enterprises, Inc. (Scott), won a contract with the City of Allentown (City) to construct a one mile roadway. Several weeks after commencing work, Scott learned that soil at the construction site was potentially contaminated with arsenic, and was instructed by the City to suspend its work. Because of the soil contamination, additional work would be required to complete the project and Scott submitted proposals for the additional work plus its suspension costs. However, the City never approved the additional work and the project was never completed. The City never paid Scott for costs incurred due to the suspension of the work and Scott filed suit to recover its losses. The jury found that the City had breached the contract with Scott and had acted in bad faith in violation of the Procurement Code, and awarded damages to Scott for its unreimbursed suspension costs. However, the trial court denied Scott’s request for an award of attorney's fees and penalty interest. Both Scott and the City appealed the final judgment to the Commonwealth Court, which reversed the trial court’s refusal to award attorney's fees and penalties.
Reprinted courtesy of
William J. Taylor, White and Williams LLP and
Michael Jervis, White and Williams LLP
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com; Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Industry Survey Says Optimism Hits All-Time High
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Nashville Business Journal reported that “construction optimism has been growing exponentially since it hit an all-time low in 2009.” Furthermore, “Wells Fargo's 2014 Construction Industry Forecast saw the Optimism Quotient rise to an all-time high of 124 after a survey that was performed in January.”
Reasons for the rise, according to Wells Fargo National Sales Manager John Crum, include “more capital available from banks, more public jobs and state and local governments being able to shore up their money supplies,” as quoted by the Nashville Business Journal.
Read the court decisionRead the full story...Reprinted courtesy of
Trade Contract Revisions to Address COVID-19
August 23, 2021 —
David R. Cook Jr. - Autry, Hall & Cook, LLPMany trade contracts contain a clause that may protect trade contractors from catastrophic events like pandemics. These clauses are known as force-majeure clauses (covering acts of God). They basically say if these unavoidable events happen, the contractor is relieved of its obligations to the extent of the impact.
However, many common industry forms have not been updated to specifically address COVID-19. (They may be waiting to see how the courts treat their existing language first.) So to ensure impacts from COVID-19 are covered, a trade contractor should consider expressly adding it to the force-majeure clause. See the example below.
Notably, typical force-majeure clauses do not say the trade contractor gets more money. So an escalation clause could be added to the force-majeure clause.
Read the court decisionRead the full story...Reprinted courtesy of