Contractors and Force Majeure: Contractual Protection from Hurricanes and Severe Weather
October 11, 2017 —
Christopher G. Hill - Construction Law MusingsThis week’s Guest Post Friday here at Musings welcomes back Clay Olsen. Clay is is an attorney at Harper Whitwell PLLC. The firm is located in Mississippi and South Carolina where they routinely represent the interests of construction.
This season is not special as hurricanes are a part of life on the east coast and gulf shores. From New York to Louisiana, just about every state has seen massive property loss from hurricanes during the past ten years.
We often see harsh outcomes for those on the coast living in finished homes. What happens to the unfinished and current projects awaiting completion? If you’re building on the coast, take a look at all of the following risk aversion mechanisms:
- Builders Risk Insurance is necessary as is Coverage for named storms. Be sure to review the “excluded perils” or speak to your agent as hurricane coverage best not be omitted.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Offices of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
California Supreme Court Holds that Requirement of Prejudice for Late Notice Defense is a Fundamental Public Policy of the State for Choice of Law Analysis
November 04, 2019 —
Lorelie S. Masters, Michael S. Levine & Michelle M. Spatz - Hunton Insurance Recovery BlogCalifornia’s highest court held yesterday in Pitzer College v. Indian Harbor Insurance Co., that the state’s insurance notice-prejudice rule is a “fundamental public policy” for the purpose of choice of law analyses. This unanimous ruling, issued in response to certified questions from the Ninth Circuit, confirms and emphasizes California’s common law rule that policyholders who provide “late notice” may proceed with their insurance claim, absent a showing by the insurer of substantial prejudice. The California Supreme Court also extended the prejudice requirement, holding that a first-party insurer must show that it was prejudiced before denying coverage under a policy’s “consent provision,” which typically provides that the policyholder must obtain the insurer’s “consent” before incurring costs and expenses.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Lorelie S. Masters,
Michael S. Levine and
Michelle M. Spatz
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Spatz may be contacted at mspatz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Boston’s Tunnel Project Plagued by Water
August 11, 2011 —
CDJ STAFFBoston’s Tip O’Neil Tunnel, part of the “Big Dig” project, is suffering from water leaks which has lead to millions of dollars of damage, according to an article in the Boston Globe. The report quotes Frank DePaola, the highway administrator, as likening the water leaks to “three garden hoses.” The project’s chief engineer notes that those “three garden hoses” add up to 17 million gallons a year.
Further, the chief engineer reports notes that the leaks could compromise both safety and structural integrity. Problems have included a 110-pound light fixture that fell in February, ventilation ducts clogged with ice during the winter, and mold in utility rooms and ventilation buildings.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Insurer’s Duty to Indemnify Not Ripe Until Underlying Lawsuit Against Insured Resolved
February 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesA liability insurer has two duties: 1) the duty to defend its insured; and 2) the duty to indemnify its insured.
With respect to the second duty – the duty to indemnify – this duty is typically “not ripe for adjudication unless and until the insured or putative insured has been held liable in the underlying action.” Hartford Fire Ins Co. v. Beazer Homes, LLC, 2019 WL 5596237, *2 (M.D.Fla. 2019) (internal quotation omitted).
For instance, Beazer Homes involved an insurance coverage dispute stemming from construction defects. An owner sued its general contractor for construction defects relating to stucco problems. The general contractor paid for the repairs. The general contractor then sued its stucco subcontractor to recover the costs it incurred. The subcontractor tendered the defense of the lawsuit to its commercial general liability insurer which is defending its insured-subcontractor under the commonly issued reservation of rights.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Antitrust Walker Process Claims Not Covered Under Personal Injury Coverage for Malicious Prosecution
May 18, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Travelers Property Casualty Co. of America v. KLA-Tencor Corp. (No. H044890; filed 1/16/20, ord. pub. 2/13/20), a California appeals court ruled that commercial general liability insurance for personal and advertising injury, defined to include malicious prosecution, does not cover a Walker Process antitrust cause of action under the Sherman Act and the Clayton Act for using a fraudulently procured patent to attempt to monopolize the market.
Travelers insured KLA under commercial liability policies with coverage for personal and advertising injury liability, which was defined as “injury, other than ‘advertising injury’, caused by. . . (2) Malicious prosecution.”
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Specification Challenge; Excusable Delay; Type I Differing Site Condition; Superior Knowledge
January 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesAn Armed Services Board of Contract Appeals dispute, Appeal of L.S. Black-Loeffel Civil Constructors JV, ASBCA No. 62402, 2023 WL 5827241 (ASBCA 2023), involved which party bore liability for delay—the federal government or the prime contractor–based on various legal theories. Without detailing the factual details, a number of interesting legal issues were raised in this dispute including (1) a defective specification challenge, (2) excusable delay, (3) Type I differing site condition, and (4) superior knowledge. These legal issues are discussed below.
1. Specification Challenge (Defective Specifications)
The contractor claimed that the government’s specifications were defective in regard to a thermal control plan. The government countered that the specifications were not design specifications but performance specifications. The specifications were performance based because they did not tell the contractor how to achieve the performance-based criteria.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Appeals Court Upholds Decision by Referee in Trial Court for Antagan v Shea Homes
May 10, 2012 —
CDJ STAFFIn the case Antangan v. Shea Homes Ltd. Partnership (Cal. App., 2012), Plaintiffs appealed “an order vacating a judgment and entering a modified judgment in their construction defect action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership,” while the Defendant, Shea Homes Limited Partnership (Shea Homes) appealed “an order of the judicial referee denying its motion to strike and tax costs.”
On the Antagon issue, the appeals court concluded that “the trial court did not err by vacating and modifying its judgment so that the cost of referee’s fees would be equally divided by the parties and consistent with a prior stipulation they filed in court.”
On the Shea Homes issue, the appeals court concluded: “1) the judicial referee did not err by ruling that plaintiffs’ offers to compromise (§ 998) were validly served on Shea Homes’ counsel, 2) the offers substantially complied with statutory requirements, 3) the offers were not required to be apportioned, and 4) the referee’s award of $5,000 as costs for a person assisting plaintiffs’ counsel was not an abuse of discretion.” The appeals court affirmed the judgment.
Here is a brief history of the trial case: “Plaintiffs Chito Antangan, Jimmy Alcova and other homeowners brought an action against defendants Shea Homes, Inc. and Shea Homes Limited Partnership for damages alleging that the properties they purchased from these ‘developer defendants’ were defective. Plaintiffs claimed numerous construction defects required them ‘to incur expenses’ for ‘restoration and repairs’ and the value of their homes had been diminished.”
In response, Shea Homes filed a motion for an order to appoint a judicial referee. The motion was granted and it was ruled that “a referee would ‘try all issues’ and ‘report a statement of decision to this court.’”
On May 10, 2010 the judicial referee (Thompson) “awarded plaintiffs damages and various costs, and ruled that ‘Shea Homes shall bear all of the Referee’s fees.’” The latter ruling would become a matter for contention later on.
In July of 2010, the plaintiffs “sought, among other things, $54,409.90 for expert fees, and $14,812.50 for the services of Melissa Fox for ‘exhibit preparation & trial presentation.’ Shea Homes filed a motion to strike and/or tax costs claiming: 1) Fox was a paralegal, 2) plaintiffs were not entitled to attorney’s fees, and 3) the fees for Fox’s services were an indirect and improper method to obtain attorney’s fees. The referee disagreed and awarded $5,000 for Fox’s services. The referee also ruled that plaintiffs had properly served valid offers to compromise (§ 998) on Shea Homes’ counsel in 2009. He said those offers to defendants in the case at that time did not have to be apportioned.”
“Antangan contends the trial court erred when it vacated and modified its original judgment, which ordered Shea Homes to pay all the referee’s fees. We disagree.”
Antagon contended that the trial court erred when it vacated and modified its original judgment regarding Shea Homes paying the referee’s fees. The appeals court disagreed: “A trial court has inherent authority to vacate or correct a judgment that is void on its face, incorrect, or entered by mistake. (§ 473; Rochin v. Pat Johnson Manufacturing Co. (1998),67 Cal.App.4th 1228; Olivera
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
2020s Most Read Construction Law Articles
January 25, 2021 —
ConsensusDocs2020 was . . . well . . . well it was memorable. Among many other things, construction was recognized as essential and ConsensusDocs published industry firsts in addressing prefabricated construction and lean for design-build, as well as 8 comprehensively revised performance and payment bonds. We also saw unprecedented readership of our construction law newsletter. As we celebrate the end of 2020 and wish you a happy new year, we continue a new a tradition of recognizing the below most read construction law articles of the year.
The ConsensusDocs Team.
5.
Level 10 Construction v. Sea World LLC: Can Force Majeure Save Sea World?
By:
Jamey B. Collidge Associate,
Troutman Pepper.
4.
The Designer’s Pre-bid Standard Of Care In A Design-Build Project
By:
Joshua A. Morehouse Associate,
Peckar & Abramson P.C. Read the court decisionRead the full story...Reprinted courtesy of