Guessing as to your Construction Damages is Not the Best Approach
November 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesArbitrarily guessing as to your construction damages is NOT the best approach. Sure, experts can be costly. No doubt about it. Having an expert versus guessing as to your construction damages caused by another party’s breach of contract is a no brainer. Engage an expert or, at a minimum, be in a position to competently testify as to your damages caused by another party’s breach of contract. Otherwise, the guessing is not going to get you very far as a concrete subcontractor found out in Patrick Concrete Constructors, Inc. v. Layne Christensen Co., 2018 WL 6528485 (W.D. New York 2018) where the subcontractor could not competently support its delay-related damages or change orders and, equally important, could not support that the damages were proximately caused by the general contractor’s breach of the subcontract.
In this case, the concrete subcontractor entered into a subcontract to perform concrete work for a public project. The project was delayed and the general contractor was required to pay liquidated damages to the owner. Not surprisingly, the subcontractor disputed liability for delays and sued the general contractor for all of its delay-related damages “in the form of labor and materials escalation, loss of productivity, procurement and impact costs, field and home office overhead, idle equipment, inability to take on other work, lost profits, and interest.” Patrick Concrete Constructors, 2018 WL at *1.
The general contractor moved for summary judgment as to the plaintiff’s delay-related damages – the subcontractor’s damages were nothing but guesses and the subcontractor could not prove the general contractor was the cause of the subcontractor’s damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Even with LEED, Clear Specifications and Proper Documentation are Necessary
December 31, 2014 —
Christopher G. Hill – Construction Law MusingsA recent lawsuit filed in California over the proper documentation necessary for LEED certification (discussed in detail at the Green Building Law Update) emphasizes the fact that, no matter how detailed the LEED certification process seems to be, a mere reference to that process or a certain level of LEED certification is far from sufficient to assure a smooth project.
While I don’t practice in California and don’t have any idea how the lawsuit will turn out, the fact that there is litigation over even the basics of LEED like documentation shows the clear necessity to make sure that your specifications and contract documents are specific and clear from the beginning. Owners, General Contractors and Subcontractors need to remember this fact at all times and particularly in situations where, like in the instance of LEED, the “specification” seems to be set out by others.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Structural Defects in Thousands of Bridges in America
November 06, 2013 —
CDJ STAFFWriting under the pseudonym “Babbage,” a technology blogger at The Economist takes note of some of the depressing facts about America’s infrastructure. Babbage notes that most of the United States’ transportation infrastructure was “built in a furious burst of road construction during the 1950s and 1960s.” Citing a report from the American Society of Civil Engineers, President Obama recently warned that “we’ve got about $2 trillion of deferred maintenance.”
Some of this deferred maintenance can cost lives. The 2007 collapse of the I-35W bridge in Minneapolis killed 13 people and injured 145 others. The cost of fixing structural defects in the nation’s bridges was estimated at $32 billion in 2004. In that year, about 66,500 bridges were deemed structurally defective. Another 84,000 were termed “structurally obsolete,” meaning they could be used, but with restrictions on vehicle weight and speed.
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Business Interruption Claims Four Years Later: What Have We Learned?
September 23, 2024 —
Patrick McKnight - The Dispute ResolverFour and half years ago the COVID-19 pandemic spread around the globe, bringing with it interesting, but challenging, legal problems for construction attorneys. Construction projects ground to a halt. Ever-changing guidance from authorities ranging from the U.S. Department of Labor to local health authorities resulted in a web of evolving obligations for general contractors and subs alike. One of the most closely watched legal questions was the wave of business interruption claims filed by plaintiffs, many of whom owned businesses impacted by government shutdowns. During the opening months of the pandemic, I
noted that hundreds of business interruption claims had been filed by insureds across the country. At that time, the only thing certain was that although the outcome remained unknown, virus exclusions were likely to become more likely in the future. Needless to say, much has happened since early 2020.
What does the data say about the outcome of business interruption claims?
In sum, plaintiffs have had an uphill battle. A helpful resource for analyzing the outcome of business interruption suits is the
Covid Coverage Litigation Tracker (“Tracker”), an insurance law analytics tool offered by Penn Carey Law of the University of Pennsylvania. According to its website, “[t]he Covid Coverage Litigation Tracker is a multi-sourced database and dashboard through which to view the unfolding insurance litigation arising out of the pandemic in federal and state courts. Widely cited in briefs, judicial opinions, and the press, the tracker also serves as a proof of concept for new methods to identify, track, and understand emerging case congregations in real time.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Philadelphia Voters to Consider Best Value Bid Procurment
May 10, 2017 —
Wally Zimolong - Supplemental ConditionsMy friend and colleague,
Chris McCabe, recently
published an opinion piece on Philly.com concerning the May 16 ballot question that asks Philadelphia voters to approve a change in the way Philadelphia awards public contracts.
Currently, Philadelphia, like all municipalities in Pennsylvania, uses an objective lowest responsible bidder standard in the award of public contracts. Under this approach, public contracts must be awarded to a bidder that responds to all of the criteria of the request for bids and offers the lowest price. Under this traditional approach the award of public contracts is completely transparent.
The May 16 ballot initiative seeks to change this. If approved, Philadelphia could award public contracts using a host of subjective factors. What those factors would be are unknown because the policies are not yet written.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Unbilled Costs Remain in Tutor Perini's Finances
October 23, 2018 —
Scott Van Voorhis – Engineering News-RecordTutor Perini is struggling to shake off long-running concerns over the hundreds of millions in unbilled costs that have been on the contractor’s balance sheet for years. The Sylmar, Calif.-based construction giant reported more than $1 billion in unbilled costs or receivables at the end of the second quarter, up by more than $100 million from the start of the year, according to the company’s federal filings. That was $100 million higher than at the end of 2016, when the amount was $832 million.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENRENR may be contacted at
ENR.com@bnpmedia.com
Traub Lieberman Partner Bradley T. Guldalian Wins Summary Judgment
November 19, 2021 —
Bradley T. Guldalian - Traub LiebermanOn September 14, 2021, Traub Lieberman Partner Bradley T. Guldalian secured summary judgment on behalf of a City which operated a park containing a natural bathing spring in Sarasota County, Florida. The underlying loss occurred when the Plaintiff went to the park, entered the spring without incident, swam for more than an hour, then exited the spring and was returning to the area where she had stored her belongings when she slipped and fell on mud and grass, sustaining an open angulated fracture of her right tibia and fibula. The Plaintiff was rushed to the hospital where she underwent open reduction, internal fixation surgery on her right leg which consisted of implantation of a metal rod into the medullary cavity of her tibia that was secured by two proximal and two distal interlocking screws. She was in the hospital for four days. Upon discharge, the Plaintiff was placed in a walking boot and confined to a wheelchair for several months. The Plaintiff incurred nearly $100,000 in medical expenses. The Plaintiff filed a premises liability action against the City claiming it failed to maintain its premises in a reasonably safe condition. The Plaintiff also alleged that the City failed to warn her that the area where she had stored her belongings had become saturated and slippery proximately causing her fall and resulting injuries.
After the close of discovery, Mr. Guldalian filed a Motion for Summary Judgment on behalf of the City arguing the wet grass and mud upon which the Plaintiff fell and injured herself was a byproduct of patrons going in and out of the water and walking to and from the area where they stored their belongings, was open and obvious, and did not constitute a dangerous condition as a matter of law. Citing to case law from the Florida Supreme Court which held that it is common knowledge that walks adjacent to, leading to, or surrounding a bathing area generally have water constantly thrown upon them and are in a slippery condition, as well as deposition testimony from the Plaintiff confirming she had been swimming at the spring for the past eighteen plus years and was “very familiar” with the park, the spring, and the area where she normally stored her belongings, Mr. Guldalian argued that some injury-causing conditions, like wet grass and mud surrounding a swimming area, are simply so open and so obvious that they cannot be held, as a matter of law, to give rise to liability as dangerous conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley T. Guldalian, Traub LiebermanMr. Guldalian may be contacted at
bguldalian@tlsslaw.com
Landlords Beware: Subordination Agreements
May 03, 2017 —
Kevin J. Parker - Snell & Wilmer Real Estate Litigation BlogIn the recent Arizona Court of Appeals case Earle Investments, LLC v. Southern Desert Medical Center Partners, 762 Ariz. Adv. Rep. 12 (2017), the Court of Appeals addressed the question of the scope of a subordination agreement signed by the property owner (Lessor/Landlord) at the request of the Lessee/Tenant and Lessee/Tenant’s Lender. In general, by subordination, Party No. 1 with a higher/better lien priority agrees to allow Party No. 2 (usually a lender providing construction funds for the overall betterment of the property) to get a lien position in front of Party No. 1. Party No. 1 presumably believes the switch of lien position in return for someone else paying for the property improvements will benefit Party No. 1 in the long run by resulting in an increase in the value of Party No. 1’s position.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker, Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com