Georgia Court of Appeals Upholds Denial of Coverage Because Insurance Broker Lacked Agency to Accept Premium Payment
December 07, 2020 —
Lawrence J. Bracken II, Michael S. Levine & Rachel E. Hudgins - Hunton Insurance Recovery BlogIn American Reliable Insurance Company v. Lancaster, the Georgia Court of Appeals reversed the denial of a property insurer’s summary judgment motion concerning the insurer’s denial of a fire loss claim. The basis of the denial was that the policyholders had failed to pay the policy premium. The policyholders, Charlie and Wanda Lancaster, claimed that they had paid their policy premiums for several years to their insurance agent, Macie Yawn. In October 2014, American Reliable mailed a renewal notice to the Lancasters notifying them that premium payments had to be made directly to the insurer. After it did not receive payment from the Lancasters, American Reliable sent them a cancellation notice in December 2014, again notifying them that payments be made directly to the insurer. The Lancasters denied having received either notice from American Reliable, but the record included a receipt for certificate of mailing.
After the Lancaster’s home burned down in 2015, American Reliable denied coverage on the grounds that the policy had been cancelled for nonpayment of premium. In the subsequent coverage action, the trial court denied American Reliable’s motion for summary judgment, ruling that a factual issue existed as to the actual and apparent agency of the insurance agent, Yawn. On appeal, the Court of Appeals found that the trial court erred in deciding that there was a factual issue concerning Yawn’s agency. Specifically, the Court of Appeals ruled that the record showed American Reliable had terminated Yawn’s agency to accept policy premiums, and that the Lancaster’s received notice of that termination in the renewal and cancellation notices. In addition to determining that Yawn was not an actual agent, the Court held that Yawn did not have apparent agency, because the notices sent to the Lancasters stated that the premium payment was to be paid to American Reliable, not to the agent.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
How U.S. Design and Architecture Firms Can Profit from the Chinese Market and Avoid Pitfalls
December 23, 2024 —
Chengdong ("C.D.") Xing - The Dispute ResolverDespite recent challenges, including obvious political tensions, economic cooling in the PRC, and increased local competition, the Chinese market remains an attractive destination for U.S. design and architecture firms. For instance, PEI Architects has maintained its success in China through long-standing relationships with key clients and is currently involved in two major projects for the Bank of China: a 1.9 million-square-foot complex in Shanghai and a financial center in Haikou.[i] Similarly, NBBJ is playing a critical role in the development of Tencent’s Net City in Shenzhen, a 2-million-square-meter smart city project that aligns with China's goals of sustainable and tech-driven urbanization.[ii] These examples show that while the Chinese market presents challenges, it continues to offer significant opportunities, particularly in sectors where innovative and cutting-edge architectural solutions are in high demand. At the same time, U.S. firms should exercise care: proper advance planning and strategic alliances are crucial for profitable forays into the Chinese market.
JR Design Project: A Cautionary Tale
When operating in China, U.S. design firms often encounter regulatory challenges, particularly with respect to China’s strict qualification requirements for architectural design services. Failure to meet these requirements can result in serious legal issues, including the potential invalidation of design contracts, as demonstrated in a leading case decided by the Supreme People’s Court of PRC (the nation’s highest court).
Read the court decisionRead the full story...Reprinted courtesy of
Chengdong ("C.D.") Xing, Rajah & Tann Singapore LLPMr. Xing may be contacted at
chengdong.xing@rajahtann.com
Supreme Court Set to Alter Law on Key Project, Workforce Issues
December 02, 2019 —
Mary B. Powers & Debra K. Rubin - Engineering News-RecordWith its term now under way, the U.S. Supreme Court could change federal laws with industry impact—from where huge pipelines can be built and new regulation of pollution in groundwater to whether LGBTQ workers have anti-bias rights under the 1964 Civil Rights Act.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record and
Debra K. Rubin, Engineering News-Record
Mr. Rubin may be contacted at rubind@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Late Notice Defense Fails on Summary Judgment
December 13, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment to dismiss the claim because the insurer did not provide notice "as soon as practicable" was denied. Vintage Hospitality Group LLC v. Nat'l Trust Ins. Co., 2021 U.S. Dist. LEXIS 192651 (M.D. Ga. Oct. 6, 2021).
Vintage owned hotels, one of which was struck by a severe hailstorm on July 21, 2018. Vintage was not aware of roof damage until two months after the storm, and did not make the connection between the hailstorm and roof damage until February 2020, when it reported the damage to National. The claim was denied because it was not reported "as soon as practicable" as required by the policy.
Vintage sued and National moved for summary judgment.
Vintage did not notice the leaks until September 2018. The focus was on fixing the leaks, and connection to the hailstorm did not register. The leaks persisted over the next year and a half. A construction company was called in to evaluate the leaking roof. The construction company advised that the roof had experienced previous hail damage which was causing the leaks. At this point, Vintage connected the damage to the hailstorm. A claim was promptly submitted to National, which denied the claim.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Anatomy of a Construction Dispute- A Wrap Up
November 15, 2022 —
Christopher G. Hill - Construction Law MusingsOver the past four weeks, I’ve “mused” on the “stages” of a construction dispute. What started as a kernel of thought in my mind turned into what has seemed to be a popular set of four posts that I hope were both informative and interesting. Because of the great feedback I’ve gotten, I thought that I’d consolidate the posts into one so that my readers (thank you, by the way) will have them all in one place. Here they are:
The Anatomy of a Construction Dispute- The Claim– This post discussed the steps for setting out a claim under your construction contract and the steps to lay the groundwork should you need to move forward with a more formal means of collection.
The Anatomy of a Construction Dispute Stage 2- Increase the Heat– This post discussed various methods to increase the heat on the party with whom you have a claim prior to litigation or arbitration.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
California Superior Court Overrules Insurer's Demurrer on COVID-19 Claim
February 15, 2021 —
Tred R. Eyerly - Insurance Law HawaiiA Superior Court in California overruled the insurer's demurrer to the policy holder's complaint seeking business interruption coverage after government shutdown orders were issued because of the coronavirus pandemic. Goodwill Industries of Orange County, California v. Philadelphia Indemnity Ins. Co., Cal. Superior Ct., Civil No. 30-2020-01169032-CU-IC-CXC (Minute Order Jan. 28,, 2021). The minute order is here [Goodwill Decision].
The insurer demurred on the ground that the insured had not alleged sufficient facts to show "direct physical loss" under the business income, extra expenses and civil authority provisions in the policy because coronavirus and COVID-19 did not physically alter the structure.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Indemnity Clauses That Conflict with Oregon Indemnity Statute Can Remain Partially Valid and Enforceable
November 30, 2016 —
Masaki James Yamada – Ahlers & Cressman PLLCWhen the indemnity provision of a contract conflicts with ORS 30.140, it is voided to the extent that it conflicts with the statute, but no more. Such provisions can remain partially valid and enforceable.[i] In Montara Owner Assn., the owner brought claims against the contractor for construction defects and damage relating to the construction of 35 townhouses. Contractor then brought third-party claims against more than 20 subcontractors for breach of contract and indemnity. Before trial, contractor settled with all but one subcontractor. The subcontract contained an indemnity provision requiring subcontractor to indemnify contractor for losses arising out of subcontractor’s work, including losses caused in part by contractor’s own negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Masaki James Yamada, Ahlers & Cressman PLLCMr. Yamada may be contacted at
myamada@ac-lawyers.com
Earth Movement Exclusion Precludes Coverage
July 20, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Federal District Court, District of Hawaii, found the earth movement exclusion barred coverage for the contractor when a landslide damaged the property. North River Ins. Co. v. H.K. Constr. Corp., 2020 U.S. Dist. LEXIS 90110 (D. Haw. May 22, 2020).
Bruce and Yulin Bingle sued HK for damage caused to the Bingle property. HK was hired as the contractor for the construction of a new residence and improvements on their property in Kaneohe. HK excavated near the boundary of the neighbors' and the Bingle's property in order to cut the existing slope to build a retaining wall. Due to the excavation work, the slope on the Bingle property failed and soil eroded away. At the time, the Bingles were selling their property. Due to the landslide, the buyer decided not to buy the property.
The Department of Planning and Permitting issued a Notice of Violation for failure to obtain a grading permit. HK notified its carrier, North River. North River agreed to defend under a reservation of rights, but then filed suit against HK for a declaratory judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com