Contractors Pay Heed: The Federal Circuit Clarifies Two Important Issues For Bid Protestors
September 13, 2021 —
Andrew Balland - ConsensusDocsThe United States Court of Appeals for the Federal Circuit (Federal Circuit) recently decided two cases that are relevant to many disappointed offerors considering a bid protest. One decision rendered in March 2021 confirmed the authority of the United States Court of Federal Claims (COFC) to hear a protest based on an agency’s breach of an implied-in-fact contract. A second decision issued in February 2021 reversed a COFC decision from last year regarding the timeliness requirements to obtain a CICA stay and their interplay with Department of Defense (DoD) enhanced debriefing regulations.
Federal Circuit Confirms The Court Of Federal Claims’ Jurisdiction Over Procurement-Related Implied Contract Claims
When a contractor’s bid protest is denied by the Government Accountability Office (GAO), the unsuccessful protestor may challenge the GAO’s decision as arbitrary and capricious in an action before the COFC. While 28 U.S.C. § 1491(b)(1) authorizes the COFC to hear such procurement-related challenges, § 1491(a) also permits the court to adjudicate claims against the United States based on any express or implied contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew Balland, Watt, Tieder, Hoffar & Fitzgerald, LLP
World's Longest Suspension Bridge Takes Shape in Turkey
November 29, 2021 —
Aileen Cho - Engineering News-RecordIt was a long-standing dream—not only of Ersin Arıoğlu, but of a nation. Could a suspension bridge someday cross the Dardanelles Strait in Turkey and provide another link between Europe and Asia? “To build a highway suspension bridge over the Çanakkale Strait has been on the agenda of the Turkish Ministry of Public Works for the last 20 years,” Arıoğlu, co-founder of contractor Yapi Merkezi, wrote in a technical paper. That was in 1994.
Reprinted courtesy of
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Window Installer's Alleged Faulty Workmanship On Many Projects Constitutes Multiple Occurrences
May 10, 2017 —
Tred R. Eyerly - Insurance Law HawaiiLawsuits filed for recovery due to the faulty design and installation of doors and windows by homeowners across the country were found to allege multiple occurrences. Pella Corp. v. Liberty Mut. Ins. Co., 2017 U.S. Dist. 53631 (C.D. Iowa March 31, 2017).
The underlying lawsuits alleged that Pella Corporation's windows were defectively designed, manufactured, or installed, and allowed water intrusion to buildings that resulted in third-party property damage or personal injury.
Pella sued Liberty Mutual for declaratory judgment and filed a motion for partial summary judgment to determine how many occurrences the underlying cases presented. Pella sought a determination that each of the 15 underlying cases presented one "occurrence" as the term was defined in the CGL policies issued by Liberty Mutual. Liberty Mutual argued that only three or four occurrences were presented, relying on common fact patterns.
Pella argued that there were separate and distinct causes of different injuries and damage and thus, each underlying case constituted a separate occurrence. Liberty Mutual, on the other hand, highlighted language within the definition of "occurrence," which stated that an "occurrence" included "continuous or repeated exposure to the same general harmful conditions." The "substantially the same general harmful conditions" language dictated that the scope of "occurrence" be understood to be broad, such that various instances of damage-causing water intrusion in different times and places constituted "substantially the same general harmful conditions."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Traub Lieberman Partner Bradley T. Guldalian Wins Summary Judgment
November 19, 2021 —
Bradley T. Guldalian - Traub LiebermanOn September 14, 2021, Traub Lieberman Partner Bradley T. Guldalian secured summary judgment on behalf of a City which operated a park containing a natural bathing spring in Sarasota County, Florida. The underlying loss occurred when the Plaintiff went to the park, entered the spring without incident, swam for more than an hour, then exited the spring and was returning to the area where she had stored her belongings when she slipped and fell on mud and grass, sustaining an open angulated fracture of her right tibia and fibula. The Plaintiff was rushed to the hospital where she underwent open reduction, internal fixation surgery on her right leg which consisted of implantation of a metal rod into the medullary cavity of her tibia that was secured by two proximal and two distal interlocking screws. She was in the hospital for four days. Upon discharge, the Plaintiff was placed in a walking boot and confined to a wheelchair for several months. The Plaintiff incurred nearly $100,000 in medical expenses. The Plaintiff filed a premises liability action against the City claiming it failed to maintain its premises in a reasonably safe condition. The Plaintiff also alleged that the City failed to warn her that the area where she had stored her belongings had become saturated and slippery proximately causing her fall and resulting injuries.
After the close of discovery, Mr. Guldalian filed a Motion for Summary Judgment on behalf of the City arguing the wet grass and mud upon which the Plaintiff fell and injured herself was a byproduct of patrons going in and out of the water and walking to and from the area where they stored their belongings, was open and obvious, and did not constitute a dangerous condition as a matter of law. Citing to case law from the Florida Supreme Court which held that it is common knowledge that walks adjacent to, leading to, or surrounding a bathing area generally have water constantly thrown upon them and are in a slippery condition, as well as deposition testimony from the Plaintiff confirming she had been swimming at the spring for the past eighteen plus years and was “very familiar” with the park, the spring, and the area where she normally stored her belongings, Mr. Guldalian argued that some injury-causing conditions, like wet grass and mud surrounding a swimming area, are simply so open and so obvious that they cannot be held, as a matter of law, to give rise to liability as dangerous conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley T. Guldalian, Traub LiebermanMr. Guldalian may be contacted at
bguldalian@tlsslaw.com
Termination of Construction Contracts
November 30, 2020 —
Stuart Rosen - Construction ExecutiveLately, in view of the COVID-19 pandemic, there is a heightened concern that some construction projects will not proceed as planned. Therefore, it is important to review each party’s right to terminate a construction contract and to examine some of the resulting consequences.
While the parties to a construction contract can, as always, agree to other mutually acceptable terms and provisions, in broad terms, a typical construction contract includes four triggering events that can lead to termination.
First, an owner can terminate a construction contract if the contractor defaults and thereafter fails to cure such default, which may include, without limitation, the failure to remediate deficient work, the failure to meet the construction schedule, the failure to pay subcontractors and the failure to comply with applicable law. A contractor must be mindful of the fact that in the case of such termination by the owner for cause, the vast majority of construction contracts provide that the contractor will not be entitled to receive any further payment for work performed by the contractor until the work is finished.
Reprinted courtesy of
Stuart Rosen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Rosen may be contacted at
srosen@proskauer.com
Speculative Luxury Homebuilding on the Rise
April 08, 2014 —
Beverley BevenFlorez-CDJ STAFFForbes reported that there is a “comeback in speculative building of luxury homes in centers of wealth across the country.”
“The appearance of spec homes in the upper price range is an indication of the maturation of the housing cycle,” Stuart Gabriel, director of the Ziman Center for Real Estate at UCLA, told Forbes. “It’s an indication of increasing levels of confidence on the part of home builders.”
Dana Kuhn, of the Corky McMillin Center for Real Estate at San Diego State University, stated that she “would expect luxury buyers to want more design control than can be afforded them if the house is mostly complete when they make their purchase.” But the article showed the flip side: Some luxury buyers are “too busy to bother with such involvement” and even prefer to buy the house fully furnished.
Read the court decisionRead the full story...Reprinted courtesy of
Would You Trade a Parking Spot for an Extra Bedroom?
August 23, 2021 —
Virginia Postrel - BloombergA bill wending its way through the California Legislature could suddenly make a lot more new housing economically feasible.
Known as AB 1401, the legislation would abolish local parking requirements for new residential and commercial developments near bus or train stops. It applies to counties with more than 600,000 residents and cities with more than 75,000 people.
The bill does not prohibit or restrict parking. It merely deregulates it, allowing developers to decide what works best for a given project. It opens up the possibility, for example, of providing parking in an off-site garage or lot. It permits tandem parking to save space or subsidized shared ride services. It doesn’t prescribe a one-size-fits-all solution to how buildings can best serve the people who use them, and it allows flexibility as transportation options evolve.
Most homeowners and tenants want some sort of parking, but local mandates can be extreme — and extremely expensive. Twenty-one California towns even require more than three parking places for a three-bedroom single-family home.
Read the court decisionRead the full story...Reprinted courtesy of
Virginia Postrel, Bloomberg
The Top 10 Changes to the AIA A201: What You Need to Know
May 24, 2018 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Melissa Dewey Brumback. Melissa is a construction law attorney with Ragsdale Liggett in Raleigh, North Carolina. Aside from the fact that she is a UNC grad and fan, she’s okay!
In 2017, as it does every ten years, the American Institute of Architects (AIA) updated most of its standard form contract documents, including the A201 General Conditions. This cycle, the contract changes are evolutionary in nature, not revolutionary. Even so, it is crucial to know the changes to avoid making a fatal mistake that could cost you money on a construction project. In reverse order, the top 10 changes you need to know include:
# 10: Differing Site Conditions
Prior editions of the A201 provided that upon encountering differing site conditions, the Contractor was to promptly provide notice to the Owner and Architect, before the conditions are disturbed, and in no event later than 21 days after the conditions were first observed. A201–2017 shortens the time for notice from 21 to 14 days.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com