Retroactive Application of a Construction Subcontract Containing a Merger Clause? Florida’s Fifth District Court of Appeal Answers in the Affirmative
September 07, 2017 —
Sanjo S. Shatley - Florida Construction Law NewsFlorida’s Fifth District Court of Appeal recently addressed the issue of retroactive application of a construction subcontract on the basis of a merger clause in Don Facciobene, Inc. v. Hough Roofing, Inc.[1]
In the case, in late 2010, Don Facciobene, Inc. (“DFI”), a licensed general contractor, contracted with Digiacinto Holdings, LLC, an owner of a home built in 1905 in Melbourne, Florida, known as the Nannie Lee House or the Strawberry Mansion, to perform various renovations in preparation for a restaurant to be opened on the premises. One of the renovations included a new roof. DFI subcontracted the roofing work to Hough Roofing, Inc. (“HRI”), a licensed roofing subcontractor. In mid-March 2011, HRI submitted an estimate and proposed statement of work to DFI. DFI’s project manager signed HRI’s proposal on April 5, 2011, as well as an additional expanded proposal six days later. According to the proposals, payment was due on completion. HRI began work on the roof on April 15, 2011, without a signed subcontract. However, DFI and HRI ultimately executed a subcontract on June 8, 2011, even though HRI had mostly finished its work by the end of May.
Read the court decisionRead the full story...Reprinted courtesy of
Sanjo S. Shatley, Cole, Scott & Kissane, P.A.Mr. Shatley may be contacted at
sanjo.shatley@csklegal.com
BKV Barnett, LLC v. Electric Drilling Technologies, LLC: Analyzing the Impact of Colorado’s Anti-Indemnification Statute
December 23, 2024 —
David M. McLain – Colorado Construction Litigation BlogIn the recent case of BKV Barnett, LLC v. Electric Drilling Technologies, LLC, the United States District Court for the District of Colorado dealt with significant legal issues concerning indemnification and insurance obligations in construction agreements. The ruling, handed down on September 26, 2024, serves as a crucial reminder of the limitations imposed by Colorado’s Anti-Indemnification Statute, C.R.S. § 13-21-111.5, and its implications for contracts in the construction industry.
This case arose from a Master Service Contract (“MSC”) between BKV Barnett, LLC (“BKV”) and Electric Drilling Technologies, LLC (“EDT”), in which EDT provided electrical services and equipment to an oil and gas lease wellsite in Texas. Following a lightning strike in early 2022 that damaged electrical infrastructure at the site, EDT dispatched Turn Key Utility Construction to repair the damage. During the repair work, an arc flash occurred, causing significant injuries to one of Turn Key’s employees, Matthew Lara, leading to a personal injury lawsuit filed by Lara in Dallas County, Texas. BKV sought indemnification, defense, and additional insured status from EDT under the terms of their MSC, which EDT contested.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Structure of Champlain Towers North Appears Healthy
August 04, 2021 —
Nadine M. Post - Engineering News-RecordThere is good news for the residents of the occupied Champlain Towers North, the 12-story residential condominium in Surfside, Fla., located a short distance up Collins Avenue from its near-twin Champlain Towers South, which failed unexpectedly June 24. The unstable remaining wing of the Champlain Towers South concrete structure was imploded July 4, after the partial progressive collapse that killed at least 94 people and left another 22 still missing.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Privity Problems Continue for Additional Insureds in the Second Circuit
November 08, 2017 —
Samantha M. Martino – Saxe Doernberger & Vita, P.C.On October 4, the Second Circuit held that Harleysville Insurance Company had no duty to defend or indemnify a project owner or general contractor as additional insureds under a sub-subcontractor’s commercial general liability (CGL) policy due to lack of direct contractual privity. 1
The underlying claim arose when an employee of The Kimmell Company, Inc. (Kimmell) was injured while repairing an HVAC system at a building owned by the University of Rochester Medical Center (UR). The injured employee sought damages for his injuries and fi led suit against (1) UR; (2) LeChase Construction Corp. (LeChase), the general contractor for the project; and (3) J.T. Mauro Co. Inc. (Mauro), a subcontractor hired by LeChase.
Mauro hired Kimmell as a sub-subcontractor to perform HVAC services at the project. The Mauro-Kimmel contract required Kimmel to add Mauro, UR, and LeChase as additional insureds under Kimmell’s CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Samantha M. Martino, Saxe Doernberger & Vita, P.C.Ms. Martino may be contacted at
smm@sdvlaw.com
Consequential Damage Claims for Insurer's Bad Faith Dismissed
April 22, 2019 —
Tred R. Eyerly - Insurance Law HawaiiPartial dismissal of the insured's complaint seeking consequential damages for the insurer's bad faith was granted by the court. Bryant v. General Cas. Co., 2019 U.S. Dist. LEXIS 15369 (N.D. N.Y. Jan. 30, 2019).
Bryant purchased from General Casualty Company of Wisconsin (GCCW) a commercial property and casualty policy to cover the insured premises. While the building was rented to a tenant who operated a restaurant, it sustained a collapse. GCCW refused to cover the loss. Bryant sued. In addition to the cost of repairing and replacing the damage to the property, Bryant alleged he was out the value of rental revenue from his tenant, which was forced to close the restaurant and relocated as a result of the unrepaired damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Georgia Court Rules that Separate Settlements Are Not the End of the Matter
October 14, 2013 —
CDJ STAFFThe Georgia Court of Appeals recently took up the question of how parties in a construction defect settlement relate to one another in terms of apportioning the settlement. Scott Murphy, writing on the Barnes & Thornburg blog clarifies the issues. The underlying construction defect case involved a newly-constructed hotel with mold and mildew problems. The owners sued the contractor (for negligent construction) and the architect (for negligent design). Separately, the owners settled with the contractor for $2.3 million and the architect for $100,000. Subsequently, the contractor sued the architect, attempting to recover part of the settlement the contractors had made with the owners.
At trial, the architect prevailed, obtaining a summary judgment that under Georgia law, “joint-tortfeasors can no longer assert contribution or non-contractual indemnity claims.” This was reversed by the Court of Appeals, determining that the two were not joint tortfeasors. Mr. Murphy notes that “the court rejected the parties’ attempt to disavow joint and several liability in their respective settlement agreements.” The court ruled that the contractor could proceed with their claims against the argument.
Read the court decisionRead the full story...Reprinted courtesy of
General Contractor Supporting a Subcontractor’s Change Order Only for Owner to Reject the Change
December 09, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe opinion in Westchester Fire Ins. Co, LLC v. Kesoki Painting, LLC, 260 So.3d 546 (Fla. 3d DCA 2018) leads to a worthy discussion because it involves a common scope of work occurrence on construction projects involving a general contractor and subcontractor. The contractor submits a subcontractor’s change order request to the owner and the owner rejects the change order. What happens next is a scope of work payment dispute between the general contractor and subcontractor. Yep, a common occurrence.
In this case, a general contractor hired a subcontractor to perform waterproofing and painting. A scope of work issue arose because the specifications did not address how the window gaskets should be cut and then sealed. The owner wanted the window gaskets cut at a 45-degree angle and the subcontractor claimed this resulted in increased extra work. The general contractor agreed and submitted a change order to the owner to cover these costs. The owner rejected the change order claiming it was part of the general contractor’s scope of work even though the cutting of window gaskets at a 45-degree angle was not detailed in the specifications.
After the subcontractor filed a suit against the general contractor’s payment bond surety, the project architect further rejected the change order because gasket cutting was part of the specification requirements. (Duh! What else was the architect going to say? It was not going to concede there was an omission that resulted in a change order to the owner, right?)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Dispute Review Boards for Real-Time Dispute Avoidance and Resolution
August 20, 2019 —
Neal J. Sweeney, Esq. - ConsensusDocsThe use of dispute tribunals generally referred to as Dispute Review Boards or DRBs on major projects has matured. Use of a DRB cannot guarantee elimination of post-project litigation, but when used properly, a DRB can be an enormously effective tool to avoid and resolve disputes rapidly and during construction.
The modest out-of-pocket costs of a DRB can pay big dividends. DRBs offer the opportunity to shorten the life cycle of a dispute by requiring the principals to confront and address the merits of their dispute, rather than simply hunkering down and focusing on posturing and preparing for arbitration or litigation. Even when a DRB cannot immediately resolve a dispute, the process can still facilitate subsequent settlement and cost-effectively prepare both parties for formal adjudication. DRBs can also enhance communications and help the parties avoid and resolve problems before they spiral into disputes.
DRBs were first and are most widely used on big civil and infrastructure projects, but the benefits of a DRB extend equally to major building projects, particularly hospitals, and industrial projects and should be used in those sectors.
Read the court decisionRead the full story...Reprinted courtesy of
Neal J. Sweeney, Esq., Jones Walker LLPMr. Sweeney may be contacted at
nsweeney@joneswalker.com