Resurgent Housing Seen Cushioning U.S. From World Woes: Economy
January 28, 2015 —
Steve Matthews – Bloomberg(Bloomberg) -- Real estate developer Crescent Communities in Charlotte, North Carolina, expects to sell 1,000 new homes this year across the Southeast U.S. and Texas, double the number of two years ago.
“Demand is the strongest since the recession” that ended in June 2009 and stemmed from the collapse in housing, said Chief Executive Officer Todd Mansfield. “The economy is getting better and the labor market is getting better.”
Read the court decisionRead the full story...Reprinted courtesy of
Steve Matthews, BloombergMr. Matthews may be contacted at
smatthews@bloomberg.net
A Court-Side Seat: Butterflies, Salt Marshes and Methane All Around
November 16, 2020 —
Anthony B. Cavender - Gravel2GavelOur latest summary of some recent developments in the courts and the federal agencies includes a unique case involving salt marshes adjacent to San Francisco Bay.
THE FEDERAL COURTS
A Wolf Among the Butterflies
On October 13, 2020, the U.S. Court of Appeals for the District of Columbia Circuit decided the case of North American Butterfly Association v. Chad Wolf, Acting Secretary of the Department of Homeland Security. The National Butterfly Center is a 100-acre wildlife sanctuary located in Texas along the border between the United States and Mexico, and in 2017, the DHS exerted control over a segment of the sanctuary to construct facilities to impede unauthorized entry into the United States. It was alleged that the government failed to provide advance notice to the sanctuary before it entered the sanctuary to build its facilities. The Association filed a lawsuit to halt these actions for several reasons, including constitutional claims and two federal environmental laws (NEPA and the Endangered Species Act), but the lower court dismissed the lawsuit because of the provisions of the Illegal Immigration Reform and Immigrant Responsibility Act of 1996 (IIRIRA). That law forecloses the applicability of these laws if the Secretary of DHS issues appropriate declaration. On appeal, the DC Circuit held, in a 2 to 1 decision, that the lawsuit should not have been dismissed. The plaintiffs had standing to file this lawsuit, but the jurisdiction stripping provisions of the IIRIRA, when invoked, required that the statutory claims be dismissed as well as a constitutional Fourth Amendment search and seizure claim. However, the plaintiff’s Fifth Amendment claim that the government’s actions violated their right to procedural due process must be reviewed. The Center was given no notice of the government’s claims and no opportunity to be heard before these actions were taken. The dissenting judge argued that the court was being asked to review a non-final decision, which it should not do.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
World’s Biggest Crane Lifts Huge Steel Ring at U.K. Nuclear Site
January 25, 2021 —
Rachel Morison - BloombergThe world’s largest crane hoisted the first of three massive steel rings that will encase one of the reactors at Electricite de France SA’s nuclear construction site in the U.K., a key milestone in getting the project completed on time.
Operators of the 250-meter (820-foot) tall crane, affectionately known as “Big Carl,” lifted the ring that weighs as much as a jumbo jet overnight to take advantage of windless conditions.
Hinkley Point C is the U.K.’s first new nuclear power plant in more than two decades. Once up and running the reactor will generate electricity for six million homes by 2025.
It’s the largest and most advanced infrastructure project in the country and, when finished, will contain 3 million tons of concrete and 50,000 tons of structural steel, enough to build a railway line between London and Rome.
Read the court decisionRead the full story...Reprinted courtesy of
Rachel Morison, Bloomberg
You Cannot Always Contract Your Way Out of a Problem (The Case for Dispute Resolution in Mega and Large Complex Construction Projects)
September 16, 2024 —
Lisa D. Love - The Dispute ResolverMost experienced commercial transaction and construction attorneys strive to negotiate a concisely written and well-drafted contract that addresses all scenarios and issues that creative and highly contemplative professionals can conjure. Although contracts are extremely important in construction projects, “you can’t generally contract your way out of a problem,” states Michael Loulakis, a founder of Capital Project Strategies, LLC and a nationally recognized expert on project delivery systems in complex public sector design-build projects and public-private partnership programs. Loulakis adds, “the contract certainly matters. But particularly when the losses are big, litigators prosecuting the contractors often find effective ways to argue that facts and circumstances trump the contract.” However, “the difference between the best construction projects and the worst construction projects is not the written words of the contracts but how the parties have committed to engage collaboratively and with trust to complete the project,” notes Robynn Thaxton, an attorney and consultant with Thaxton Parkinson PLLC and Progressive Design-Build Consulting, LLC and one of the leading experts in construction law and alternative procurement on a national basis.[i]
In large, complex construction projects, the need for parties to collaboratively resolve disputes is highlighted by the judicial acceptance of the “Doctrine of the Contextual Contract”[ii] to interpret construction contracts. “As construction’s increasing technological and managerial complexity came to be recognized, some common law courts began turning away from strict interpretation of language within the four corners of a contract and moving toward recognizing in the enforcement of contracts the construction industry’s own experience, customs, practices and implied conditions and duties and the factual context underlying the contract. Courts [began the journey] along the road from ‘text’ to ‘context.’”[iii] Thus, the precise wording of the contract has become less important and industry practices and other conditions provide insight for resolving disputes. Consequently, despite the specific language of any construction contract and the clear allocation of responsibilities and risks, early dispute evaluation and resolution are critical to a successful project.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa D. Love, JAMS
Business Risk Exclusions (j) 5 and (j) 6 Found Ambiguous
April 22, 2019 —
Tred R. Eyerly - Insurance Law HawaiiReversing the district court's grant of summary judgment in favor of the insurer, the Tenth Circuit found that exclusions (j) 5 and (j) 6 were ambiguous as applied to the facts of the case. MTI, Inc. v. Emplrs. Ins. Co., 2019 U.S. App. LEXIS 2543 (10th Cir. Jan. 25, 2019).
Western Farmers Electrical Cooperative (WFEC) owned cooling towers which were serviced by MTI, Inc. Wausau provided a CGL policy to MTI.
In 2011, MTI found that anchor bolts in Cooling Tower 1 were corroded. WFEC hired MTI to make repairs by installing new anchor castings with anchor bolts and anchor adhesive.
On May 23, 2011, MTI employees removed all of the corroded anchor bolts in Tower 1. Because the adhesive applicator had not yet arrived, MTI did not immediately install new anchor bolts. On the night of May 24, strong winds struck the tower, causing it to lean and several structural components broke. Due to the extent of the structural damage, removal and replacement of the tower was determined to be the only viable option.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Cross-Motions for Partial Judgment on the Pleadings for COVID-19 Claim Denied
May 24, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied both parties' motions for partial judgment on the pleadings seeking clarification of the policy's contamination exclusion. Thor Equities, LLC v. Factory Mut. Ins. Co., 2021 U.S. Dist. LEXIS 62967 (S.D. N.Y. March 31, 2021).
Thor was a commercial landlord, renting properties across the country to hundreds of tenants, for use in a variety of businesses, including office space, retail stores, restaurants, and bars. When state governments began shutting down businesses and issuing stay-at-home orders in March 2020, many of Thor's tenants had to close shop and sought abatements or other accommodations. Thor alleged it suffered significant business interruption as a result of the pandemic.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Following California Law, Federal Court Adopts Horizontal Allocation For Asbestos Coverage
May 19, 2014 —
Tred R. Eyerly – Insurance Law HawaiiFollowing California law, the federal district court adopted horizontal allocation to settle a dispute among carriers for an insured sued for selling asbestos products. New England Fire Ins. Corp. v. Ferguson Enterprises, Inc., Civil No. 3:12cv948 (D. Conn. April 8, 2014) [ruling here]
The insured was a California-based corporation that sold plumbing supply products that contained asbestos. The insured was named in numerous asbestos-related lawsuits that were filed largely in California.
The insured had primary and excess coverage for bodily injury claims. New England Fire Insurance issued an excess policy to the insured. The policy provided the insurer would be liable for the ultimate new loss in excess of the insureds underlying limit, which was defined as the amount equal to the limits of the underlying insurance, plus the applicable limits of any other underlying insurance collectible by the insured.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Law Alert: Builder’s Alternative Pre-litigation Procedures Upheld Over Strong Opposition
April 01, 2014 —
Steven M. Cvitanovic and Whitney L. Stefko - Haight Brown & Bonesteel, LLPLast week, the Court of Appeal, Fifth Appellate District, was tasked with evaluating the enforceability of provisions in home purchase contracts containing alternative pre-litigation procedures which differ from the standard Right to Repair Act procedures. The Court of Appeal, in McCaffrey v. Superior Court of Fresno, et al. ultimately upheld the contractual provisions, and in overturning the trial court's decision, preserved the rights of builders to contract around certain requirements set forth in the Right to Repair Act.
The McCaffrey Group, Inc. constructed single-family homes in a Fresno development. Plaintiffs consisted of 24 homeowners within the development who brought suit against McCaffrey for construction defects in their homes. The homeowners were comprised of three categories: (1) the original purchasers who bought their homes from McCaffrey before January 1, 2003 and had a 2001 version of McCaffrey's contract; (2) the original purchasers who bought their homes from McCaffrey on or after January 1, 2003 and signed a 2003 version of McCaffrey's contract; and (3) the subsequent purchasers who did not buy their homes directly from McCaffrey, but purchased their homes subject to either the 2001 or 2003 version of McCaffrey's home purchase agreement.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of