Substituting Materials and Failure to Comply with Contractual Requirements
November 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is important to remember that if you are going to substitute materials from those specified, you need to make sure there is proper approval in doing so–make sure to comply with the contractual requirements to substitute materials. Otherwise, you could be in a situation where you are contractually required to remove the installed substituted materials and replace with the correct specified materials. This is not the situation you want to find yourself in because this is oftentimes a costly endeavor. This was the situation in Appeal-of-Sauer, Inc., discussed below, on a federal project. The best thing that you can do is comply with the contractual requirements if you want to substitute materials. If you are in the situation where it is too late, i.e., you already installed incorrect materials, you want to demonstrate the substituted materials are functionally equivalent to the specified materials and/or come up with an engineering solution, as required, that could be less costly then ripping out the installed material and replacing with the correct material. Even doing so, however, is not a “get out of jail free card” and does not necessarily mean there is not a strong basis to require you to install the correct specified material.
In Appeal of- Sauer, Inc., ASBCA 61847, 2021 WL 4888192 (ASBCA September 29, 2021), a federal project’s engineering requirements required cast iron piping for the above ground sanitary system. However, the prime contractor installed PVC piping instead of cast iron piping. The prime contractor believed it had the appropriate approval through its submittal. The government, through its contracting officer, directed the prime contractor to remove installed PVC piping to replace with cast iron. The government did not believe PVC piping was the functional equivalent of cast iron piping for the above ground sanitary system due to its concern with the noise level of waste materials flowing through the piping. The prime contractor submitted a claim for its removal and replacement costs which was denied by the contracting officer. On appeal with the Armed Services Board of Contract Appeals, the Board agreed with the contracting officer explaining: “While we agree that a design change could be approved by the designer of record and brought to the attention of the government before being incorporated into the design documents, the [prime contractor’s] task order required that such a design change meet the minimum requirements of the solicitation and accepted proposal. The plumbing submittal [the prime contractor] issued here, showing the use of PVC instead of cast iron for the above ground waste piping, did not meet the minimum requirements of the solicitation.” Appeal of-Sauer, Inc., supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
PulteGroup Fires Exec Accused of Defamation By Founder’s Heir
January 17, 2023 —
Patrick Clark - BloombergPulteGroup Inc. fired a senior executive for violating the company’s code of conduct two days after the grandson of the homebuilder’s founder sued the executive for alleged defamation.
The company, which is the third-largest US homebuilder, said in a statement Friday that it had terminated Brandon Jones after the results of an independent investigation. Jones had been slated to assume the role of chief operating officer in January.
Bill Pulte, 34, filed a lawsuit on Wednesday in Palm Beach County, Florida, alleging that Jones had used anonymous Twitter accounts to smear members of the Pulte family. The lawsuit accused the executive of impersonating a business journalist and making a false claim that Pulte manipulated his grandfather.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, Bloomberg
U.S. Steel Invoking Carnegie’s Legacy in Revival Strategy
July 23, 2014 —
Sonja Elmquist – BloombergIn March 2013, Mario Longhi lobbed an unexpected question into a roomful of 150 U.S. Steel Corp. managers: Who here would buy the company’s stock, tomorrow?
He gave them three seconds, and “only a few reacted in that time frame positively,” Longhi said.
Since that meeting, Longhi has been promoted to chief executive officer, and nine months into his tenure he’s closed one plant permanently, two more are temporarily idled and he’s planning to overhaul another. It’s all part of his plan to transform the 144-year-old company into a lean, modern steel producer. Investors are taking note, with the shares up 53 percent since he took over.
Read the court decisionRead the full story...Reprinted courtesy of
Sonja Elmquist, BloombergMs. Elmquist may be contacted at
selmquist1@bloomberg.net
Subcontract Should Flow Down Delay Caused by Subcontractors
December 21, 2020 —
David Adelstein - Florida Construction Legal UpdatesA general contractor’s subcontract with its subcontractor should include a provision that entitles it to flow down liquidated damages assessed by the owner stemming from delays caused by the subcontractor. Such a provision does not mean the general contractor does not have to prove delays caused by the subcontractor or can arbitrarily allocate the amount or days it claims the subcontractor is liable. The general contractor still will need to reasonably establish the delays the subcontractor caused the critical path of the schedule, i.e., delayed the job. In addition to the right to flow down liquidated damages, the subcontract should also entitle the general contractor to recover its actual extended general conditions caused by the subcontractor’s delays (regardless of whether the owner assesses liquidated damages). The objective is that if the subcontractor delays the job, the subcontractor is liable for liquidated damages the general contractor is liable to the owner for in addition to the general contractor’s own delay damages. This is an important subcontractual provision so that the risk of delay caused by subcontractors is clearly flowed down to them in the subcontract.
In a 1987 case, Hall Construction Co., Inc. v. Beynon, 507 So.2d 1225 (Fla. 5th DCA 1987), the subcontract at-issue contained language that stated, “The parties hereto agree that a supplier who delays performance beyond the time agreed upon in this Purchase Order shall have caused [general contractor] liquidated damages in the amount required of [general contractor] by their contract per day for each day such delay continues which sum the supplier hereby agrees to pay.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Contract Clauses Which Go Bump in the Night – Part 1
November 10, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The first in a multi-part series, here are some other important construction contract clauses you may (or may not realize you should) be losing sleep over.
Provision: Incorporation and Flow-Down Provisions
- Typical Provision: “The term ‘Contract Documents’ shall include, without limitation, the Prime Contract, drawings, specifications and other agreements between Contractor and Owner, insofar as they relate in any way, directly or indirectly, to Subcontractor’s Work under this Agreement, and are hereby incorporated by reference. Subcontractor agrees to be bound to Contractor in the same manner and to the same extent as Contractor is bound to Owner under the Contract Documents. Where, in the Contract Documents, reference is made to Contractor, and the work and specifications therein pertain to Subcontractor’s trade, craft, or type of work, such work or specifications shall be interpreted to apply to Subcontractor rather than Contractor.”
- What it Means: An incorporation provision literally “incorporates” another document or documents into a contract by merely referring to them by title or description and it is not uncommon for a lower-tiered contractor to never see those documents.
A flow-down provision requires a lower-tiered contractor to comply with all obligations which a higher-tiered contractor, typically a direct contractor, owes to a higher-tiered party, typically, the owner. The intent of the provision to ensure that a lower-tiered subcontractor has no greater rights against a direct contractor has against the owner.
- What You Can Do: Lower-tiered contractors should obtain a copy of all documents to be incorporated into their contract and review them to ensure that they understand the obligations and any limitations to their rights.
Lower-tiered contractors should also seek to include language requiring that a higher-tiered contractor assume toward the lower-tiered contractor all obligations and limitations on their rights that the owner assumes toward or is subject to with respect of the general contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Changes in the Law on Lien Waivers
November 16, 2020 —
Alan Paulk - Autry, Hall & Cook, LLPAmong many things to look forward to in 2021, we can add a new lien law to the list. Effective January 1, 2021, Georgia’s Lien Statute will be modified so that lien waivers and releases are limited to “waivers and releases of lien and labor or material bond rights and shall not be deemed to affect any other rights or remedies of the claimant.” O.C.G.A. 44-14-366(a). This would mean that lien waivers only waive lien or bond rights and do not waive contractual rights to collect payment.
The new law is in reaction to a decision from the Georgia Court of Appeals in ALA Constr. Servs., LLC v. Controlled Access, Inc., 351 Ga. App. 841 (2019). In that case, a contractor signed an interim lien waiver at the time it submitted an invoice. The contractor did not receive payment, and it failed to timely record an affidavit of non-payment or a claim of lien. Subsequently, the contractor filed suit for breach of contract. The Georgia Court of Appeals held that the statutory form lien waiver was binding against the parties “for all purposes” and not just the purpose of preserving the right to file a lien. By such sweeping logic, the contractor’s breach of contract claim was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Alan Paulk, Autry, Hall & Cook, LLPMr. Paulk may be contacted at
paulk@ahclaw.com
Texas Shortens Cut-Off Date for Suits Against Homebuilders Who Provide a 6-Year Written Warranty
June 26, 2023 —
Kim Altsuler - Peckar & Abramson, P.C.Summary of the new law as it pertains to builders of new homes:
The existing 10-year statute of repose for builders of new homes (the ultimate cut-off date for filing suit) has been shortened to 6 years if the builder provides a 1-2-6 written warranty (1-year workmanship and materials; 2-year plumbing, electrical and HVAC; 6-year structural).
Extended time to bring suit if written claim presented during the period of repose:
If a written claim for damages, contribution, or indemnity is presented to the builder during the applicable limitations period and the 6-year statute of repose applies, the time to sue is extended one year from the date the claim is presented. In practical effect, this means that if a written claim is presented and the statute of repose expires before suit is filed, suit may still be filed provided it is within one year of the date the written claim was made.
When the new law goes into effect:
The new law is effective as of June 9, 2023 and applies to suits commenced on or after that date. However, if the contract under which the claim is brought was entered into before June 9, 2023, the former 10-year version of the statute of repose applies. In other words, the statute applies to contracts entered into on or after June 9, 2023, if the contract has at least a 1-2-6 warranty.
Read the court decisionRead the full story...Reprinted courtesy of
Kim Altsuler - Peckar & Abramson, P.C.Ms. Altsuler may be contacted at
kaltsuler@pecklaw.com
Shifting the Risk of Delay by Having Float Go Your Way
July 05, 2021 —
Christopher J. Brasco & Matthew D. Baker - ConsensusDocsCritical path delay plays a central role in allocating responsibility for project delay. The interrelated concept of concurrency is also frequently determinative of entitlement on a range of claims including by owners for liquidated damages and by contractors for delay damages. What constitutes critical/concurrent delay, however, is hotly debated by scheduling experts. The lack of real consensus regarding how critical/concurrent delay should be determined and analyzed has created significant uncertainty in scheduling disputes. Indeed, courts have adopted differing and at times conflicting theories of concurrency that can produce divergent outcomes for the parties. In an effort to reduce uncertainty, stakeholders have increasingly adopted specialized contractual provisions and scheduling techniques which have significant implications for the evaluation of the companion concepts of criticality and concurrency. One such mechanism is float sequestration. Regardless of whether float sequestration is ultimately in the construction industry’s broader interest, stakeholders must be able to recognize its use and appreciate the implications for delay disputes on their projects.
Simply defined, float is the number of days an activity can be delayed before affecting the project’s critical path (i.e., the longest chain of activities which determines the project’s minimal duration). Typically, only delays affecting the critical path can produce concurrent delay. Consequently, the concept of float is integral to understanding and resolving issues of both criticality and concurrency.
Reprinted courtesy of
Christopher J. Brasco, Watt, Tieder, Hoffar & Fitzgerald, LLP and
Matthew D. Baker, Watt, Tieder, Hoffar & Fitzgerald, LLP
Mr. Brasco may be contacted at cbrasco@watttieder.com
Mr. Baker may be contacted at mbaker@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of