Real Estate & Construction News Roundup (3/20/24) – Construction Backlog Falls, National Association of Realtors Settle Litigation, and Commercial Real Estate Market’s Effect on City Cuts
April 15, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, bad loans outweigh loss reserves at top six U.S. banks, the FCC announces a proposed rule aimed at “bulk billing,” office-to-multifamily conversion projects grow in major metro cities, and more!
- The National Association of Realtors has agreed to settle litigation that accused them of artificially inflating real estate commissions – a major decision that could reshape the housing market for buyers, sellers and agents. (Rachel Siegel, The Washington Post)
- An NYU professor considers the positives and negatives of cities cutting services or raising other kinds of taxes to offset the continued faltering of the commercial real estate market. (Alan Rappeport, The New York Times)
- Construction backlog fell in February for every size of contractor except for those with under $30 million in annual revenue, while, over the past year, the largest contractors – those with greater than $50 million in revenue – have experienced the greatest decline in backlog. (Sebastian Obando, Construction Dive).
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Thanks to All for the 2024 Super Lawyers Nod!
May 13, 2024 —
Christopher G. Hill - Construction Law MusingsIt is with humility and a sense of accomplishment that I announce that I have been selected for the seventh straight year to the
Virginia Super Lawyers in the Construction Litigation category for 2024. Add this to my recent election to the
Virginia Legal Elite in Construction and I’ve had a pretty good year. As always, I am thrilled to be included on these peer-elected lists.
So without further ado, thank you to my peers and those on the panel at Virginia Super Lawyers for the great honor. I feel quite proud to be part of the
5% of Virginia attorneys that made this list for 2024.
The full list of Virginia Super Lawyers will appear in the May edition of Richmond Magazine. Please check it out.
If you want to see the lists before then, a digital version of the Virginia Super Lawyers Magazine is
available here (click on the Virginia magazine).
Thanks again to all of you who participated in my nomination and election.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Credibility of Your Expert (Including Your Delay Expert) Matters in Construction Disputes
October 03, 2022 —
David Adelstein - Florida Construction Legal UpdatesHere is a quote from a judge in an order after the bench trial of a complex construction dispute between a prime contractor and subcontractor on a federal project:
The evidence received in this case demonstrates the dynamic nature of complicated construction projects. At every step, the details matter, and coordination and cooperation among the companies tasked with performing the job is essential. Thankfully, as even this case shows, most disagreements that arise as projects evolve are handled during construction, far away from a courthouse, by the professionals who know best how to achieve the ultimate goal of a completed project.
U.S. f/u/b/o McKenney’s, Inc. v. Leebcor Services, LLC, 2022 WL 3549980, *1 (E.D. Va. 2022).
This is a true statement. A statement that parties should remember as they navigate the nuances of a complicated construction project and dispute.
The facts of the case, however, would hardly be construed as a win for either party. Something else for parties to consider as they navigate the nuances of a complicated construction project and dispute.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Indiana Court of Appeals Rules Against Contractor and Performance Bond Surety on Contractor's Differing Site Conditions Claim
April 03, 2013 —
Brian M. Falcon - Frost Brown Todd LLCEarlier this year, the Indiana Court of Appeals issued an important opinion that impacts contractors and sureties alike. The decision should give contractors in Indiana pause before ceasing work while a dispute with the owner is pending. Sureties also have been placed on notice that strict compliance with the terms of their bonds is amongst their best defenses to claims made by owners and bond claimants.
In Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, 959 N.E.2d 369 (Ind. Ct. App. 2012), the contractor (“Dave’s”) was the successful bidder on a public sanitary sewer and water main extension project. Dave's procured a performance bond from Liberty Mutual to guarantee its performance obligations to the owner (the "City"). After encountering what it deemed different subsurface conditions—and indeed after having been previously granted a change order to use excavated materials as backfill in light of the subsurface conditions on site—Dave’s placed the project engineer on notice of a differing site conditions claim. The total claim amounted to an 84% increase in the total contract price. With the claim, Dave's advised the project engineer it was ceasing further work until the project engineer provided direction.
While the project engineer reviewed the claim, it reminded Dave's of its contractual obligation to "carry on the work and adhere to the progress schedule during all disputes or disagreements with the OWNER." A dispute immediately occurred regarding whether Dave's was required to continue to work while the project engineer resolved the differing site condition claim. After Dave's maintained its position that it was not required to continue to work, the project engineer placed it on notice of default and copied the letter to Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Brian M. FalconBrian M. Falcon can be contacted at http://www.frostbrowntodd.com/contact.html
Dispute Resolution in Your Construction Contract
February 07, 2022 —
David Adelstein - Florida Construction Legal UpdatesThere are important provisions in your construction contract that are geared towards dispute resolution. These are provisions you want to understand – not when a dispute arises, but BEFORE the dispute ever occurs.
Many times, dispute resolution provisions are cast aside or not appreciated until a dispute rears its ugly head. This can put you in a reactive stance versus a proactive stance, which you want to be in, because you want to proactively make sure all rights are preserved relative to the dispute. You want to proactively make strategic decisions based on the dispute resolution provisions and process in your contract.
Before your contract even gets signed, you may want to negotiate aspects of the dispute resolution process for many reasons. The process could be one-sided. It could be onerous. It could be complex. It could be unfavorable or costly with respect to how you want to progress a dispute. If you appreciate the dispute resolution process from the get-go, you will be in a more effective position to navigate the process while ensuring you are preserving your rights moving forward.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Claims Litigated Under Government Claims Act Must “Fairly Reflect” Factual Claims Made in Underlying Government Claim
November 27, 2023 —
Garret Murai - California Construction Law BlogUnlike horseshoes and hand grenades, close sometimes isn’t close enough.
In the next case, Hernandez v. City of Stockton, 90 Cal.App.5th 1222 (2023), the Third District Court of appeal found that a pedestrian who sued a public entity for personal injuries caused by an “uplifted sidewalk” was barred from pursuing his claim when it was revealed that he had in fact injured himself by falling into a hole left by an “empty tree well” (i.e., a tree well that did not contain a tree”). According to the Court, the pedestrian’s claim was barred because the factual basis for recovery asserted in his complaint was not “fairly reflected” in his government claim.
The Hernandez Case
In April 2018, pedestrian Manual Sanchez Hernandez injured himself while walking on a public sidewalk in Stockton, California. He submitted a government claim with the City of Stockton claiming that his injuries, which included injuries to his knee, hands and back, was caused by a dangerous condition on public property. In his government claim, Hernandez alleged that he tripped on an “uplifted sidewalk” at or near 230 E. Charter Way in Stockton, California and that his injuries were due because the City “negligently and recklessly designed, maintained and operated the subject property so as to cause [his] injuries.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Replacement of Defective Gym Construction Exceeds Original Cost
January 22, 2013 —
CDJ STAFFAustin, Texas has torn down a school gym, the Turner-Roberts Recreation Center at the Overton Elementary School, due to structural problems which became evident after the gym was completed four years ago. The cost of the new gym is $6.4 million, more than the cost of building the gym in the first place. The city is paying $3 million in repair costs with the rest of the money coming from the companies that designed and built the now demolished gym. According to the Austin Statesman, the total cost to the city will be about $8.6 million.
The Turner-Roberts Recreation Center cost $5.6 million to build, but soon after it opened, structural problems were discovered. Cracks formed in walls and glass doors buckled. The settlement with the designer, contractor, and engineering firm did not require the firms to admit fault as they paid $3.4 million to fix the situation. The Statesman was unable to get a breakdown of how much each firm paid. Tom Cornelius, president of the GSC, the architectural firm on the project told the Statesman that "the foundation issues were not caused by design defects."
Initially, the city sought to repair the gym, but early excavation determined that the defects were too extensive. In addition to the structural flaws, it was also determined that the HVAC system was faulty. Excavation also damaged plumbing work. Tearing down the gym turned out to be the most cost-effective response.
Read the court decisionRead the full story...Reprinted courtesy of
Mediation in the Zero Sum World of Construction
September 26, 2022 —
Christopher G. Hill - Construction Law MusingsConstruction is a zero sum game. What do I mean by that? I mean that even where you, a construction professional with a great construction lawyer, have reviewed and edited a subcontract presented to you or provided a well-drafted contract to the other party that contains an attorney fees provision, every dollar that you spend on litigation is a dollar less of profit.
Couple the fact that no construction company can or should bid or negotiate work with an eye toward litigation (aside from having a well written contract that will be enforced to the letter here in Virginia). Particularly on “low bid” type projects, contractors and subcontractors cannot “pad” their bids to take into account the possibility of attorney fees, arbitration, or litigation. Furthermore, the loss of productivity when your “back office” personnel are tied up dealing with discovery, phone calls, and other incidents of litigation that do nothing but rehash a bad project and increase the expense sap money from the bottom line. While the possibility of a judgment including attorney fees may soften this blow, you are still out the cash.
All of this said, if you are in commercial construction for any significant period of time disputes will arise and I have discussed the process in some detail at other places here at Construction Law Musings. As a construction litigator, I am fully aware of this fact of life. Efficient management of these disputes is key, particularly when they escalate to the point where some form of outside “help” (read arbitrator or judge) is necessary.