What is the Effect of an Untimely Challenge to the Timeliness of a Trustee’s Sale?
April 13, 2017 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogEver wonder what happens if a person challenges the timeliness of a trustee’s sale after the sale already occurred? Waiver of the argument of course! And, in the case of Wells Fargo Bank, N.A. v. Waltner, the affirmance of an eviction judgment.
In the Waltner case, Wells Fargo Bank, N.A., as Trustee for WaMu Mortgage Pass-Through Certificates, Series 2005-PR4 Trust (the “Bank”), purchased a residential property at a trustee’s sale in September 2015. The Bank gave the occupant of the house, Sarah Waltner (“Waltner”), notice to vacate the property, but she did not do so. Accordingly, the Bank filed a summary action to evict Waltner, which the trial court ultimately granted.
After the trial court granted the Bank relief, Waltner filed a motion to dismiss and a motion to vacate the eviction judgment arguing, among other things, that the judgment was void because the Bank conducted the trustee’s sale after the statute of limitations expired. Both motions were denied, and Waltner appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Project-Specific Policies and Products-Completed Operations Hazard Extensions
May 31, 2021 —
Jeremiah M. Welch - Saxe Doernberger & Vita1. Understanding the “Products-Completed Operations Hazard”
ISO commercial general liability (“CGL”) policies use the term “products-completed operations hazard” (“PCOH”) to define a category of risk which is treated specially by certain exclusions within the policy and often subject to separate limits of insurance. In construction, we think about PCOH as being about coverage for completed work.
Bodily injury and property damage arising out of completed work is a significant construction risk. Most construction contracts include warranty and indemnity obligations for completed work. All states allow lawsuits to be brought alleging bodily injury or property damage because of completed work based on common law. Contract and common law claims are subject to statutes of limitation – laws which define the time in which suits must be brought. Most states provide exceptions to their statutes of limitation for common law claims – the most common example is an extension to file a lawsuit based on a latent defect until the defect is discovered. Most states also have “statutes of repose” – laws that set a date after which suit may no longer be brought, no matter what the circumstances are. A construction contractor, therefore, has potential liability until the statute of repose period has expired. Thus, a contractor looks to ensure that it has coverage for the PCOH for its full statute of repose liability period.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremiah M. Welch, Saxe Doernberger & VitaMr. Welch may be contacted at
JWelch@sdvlaw.com
California’s Labor Enforcement Task Force Continues to Set Fire to the Underground Economy
February 16, 2016 —
Evelin Y. Bailey – California Construction Law BlogIf you’re a fan of the Hunger Games trilogy, either the books or the movies, you’re likely familiar with “The Hob,” the black market in District 12 where people buy and sell banned items. It’s where bow-wielding protagonist Katniss Everdeen and her childhood friend Gale Hawthorne sell their poached game and where, in the movie but not the book (what can we say, we’re fans), Katniss obtains the “mockingjay” pin which she is later associated with. While The Hob is largely ignored by soldiers of the totalitarian “Capitol,” in the third book Catching Fire, the Hob is reduced to a pile of rubbish and ash by the Capital as an example to punish the insurrectionists led by Katniss.
The Labor Enforcement Task Force (LETF), a joint task force composed of several of California’s agencies including the Contractors State License Board, Department of Industrial Relations and Employment Development Department is also setting fire, at least figuratively, to California’s underground economy. See our earlier post Joint Labor Task Force Targets Underground Economy for further background on LETF.
Read the court decisionRead the full story...Reprinted courtesy of
Evelin Y. Bailey, Wendel Rosen Black & Dean LLPMs. Bailey may be contacted at
ebailey@wendel.com
Contractual Setoff and Application When Performance Bond Buys Out of its Exposure
July 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesThe theory of “setoff” is an important theory in construction disputes. Florida’s Fourth District Court of Appeal recently provided worthy discussion on contractual setoffs:
Setoffs in contract claims are governed by [Florida Statute] section 46.015(2), which provides that if a plaintiff has released “any person in partial satisfaction of the damages sued for, the court shall [setoff] this amount from the amount of any judgment to which the plaintiff would be otherwise entitled at the time of rendering judgment.” The setoff statute intends to prohibit plaintiffs from getting double recoveries.
A setoff requires that settling and non-settling parties be jointly and severally liable. The settled damages must also be the same damages for which the setoff is sought; stated differently, a setoff is not proper where the trial damages to be setoff are separate and distinct from the settled damages.
Close Construction, LLC v. City of Riviera Beach Utility Special District, 49 Fla.L.Weekly D1184d (Fla. 4th DCA 2024) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Deference Given To Procuring Public Agency Regarding Material Deviation
April 10, 2019 —
David Adelstein - Florida Construction Legal UpdatesDeference will be given to a procuring public agency in a bid protest, particularly when the issue involves whether a bid is non-responsive and constitutes a material deviation from the solicitation. You do not believe me? Perhaps you will after this holding in Biscayne Marine Partners, LLC v. City of Miami, Florida, 44 Fla.L.Weekly D467a (Fla. 3d DCA 2019):
Consequently, no principle of law is clearly established…as to any obligation of the trial court (and, by analogy, an administrative hearing officer) [in a bid protest] to decide or to defer [whether a bid constitutes a material deviation from the solicitation]. If anything, the existing and clearly established principle of law inclines toward judicial deference in public agency competitive bidding disputes when the agency has exercised it discretion absent illegality, fraud, oppression or misconduct.
I do not know about you, but that last underlined sentence is pretty strong language regarding judicial deference!
In this case, Miami (the procuring public agency) issued a Request for Proposals (RFP) for the redevelopment and lease of waterfront property, for the operation of a marina, boatyard, restaurant, wet slips, and a dry storage facility on the property. Miami issued five addenda to the RFP. There were three bidders.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Chicago Debt Document Says $8.5B O'Hare Revamp May Be Delayed
October 26, 2020 —
Jeff Yoders - Engineering News-RecordThe $8.5-billion revamp of O'Hare International Airport may have to be delayed because of COVID-19 related economic impacts, according to documents included in paperwork to refinance existing airport debt. The city forcefully disagreed with that summation, however, and says the project will move forward and is not endangered.
Reprinted courtesy of
Jeff Yoders, Engineering News-Record
Mr. Yoders may be contacted at yodersj@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Ten Newmeyer & Dillion Attorneys Selected to the Best Lawyers in America© 2019
September 17, 2018 —
Newmeyer & DillionNEWPORT BEACH, Calif. – AUGUST 15, 2018 – Prominent business and real estate law firm Newmeyer & Dillion LLP is pleased to announce that ten of the firm's Newport Beach attorneys were recently recognized in their respective practice areas in The Best Lawyers in America© 2019.
Attorneys named to The Best Lawyers in America, include:
Jason M. Caruso
Personal Injury Litigation - Plaintiffs
Product Liability Litigation – Plaintiffs
Michael S. Cucchissi
Real Estate Law
Jeffrey M. Dennis
Insurance Law
Gregory L. Dillion
Commercial Litigation
Construction Law
Insurance Law
Litigation - Construction
Litigation - Real Estate
Joseph A. Ferrentino
Litigation - Construction
Litigation - Real Estate
Thomas F. Newmeyer
Commercial Litigation
Litigation - Real Estate
John O'Hara
Litigation - Construction
Bonnie T. Roadarmel
Insurance Law
Jane Samson
Real Estate Law
Carol Sherman Zaist
Commercial Litigation
Best Lawyers is the oldest peer-review publication within the legal profession with a history of over 35 years. Attorneys are selected through exhaustive peer-review surveys in which leading lawyers confidentially evaluate their professional peers. Their listings are published in 75 countries worldwide and are recognized for their reliable and unbiased selections.
Newmeyer & Dillion is immensely proud of these lawyers and looks forward to their continued contributions to the firm, and the Orange County community as a whole.
About Newmeyer & Dillion
For almost 35 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of cybersecurity and privacy, corporate, employment, real estate, construction, insurance law and trial work, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Partner John Toohey and Senior Associate Sammy Daboussi Obtain a Complete Defense Verdict for Their Contractor Client!
December 11, 2023 —
Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to share that Newport Beach attorneys John Toohey and Sammy Daboussi obtained a complete defense verdict after years-long litigation in favor of their concrete contractor client.
This lawsuit arises from a claim made by Plaintiff for construction defects in a high-end single-family home. Our client was hired to perform concrete work on the foundations of the home. It was alleged that the home’s foundation was incorrectly built. It was further alleged that the construction defects/errors led to delays and substantial expenses. We argued that our client relied on the certifications provided to them by design professionals and the City. We further argued that our client, like any reasonable concrete/foundation subcontractor, has no responsibility or obligation, contractual or otherwise, to review and recheck the work completed by a licensed professional.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP