Contract Change #8: Direct Communications between Owners and Contractors (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaAs the Engineer or Architect of Record, you probably have frequently experienced Owners and Contractors communicating directly, in direct contravention of the language of the contract that requires them to endeavor to route all communications through the design team. With the latest version of the 201,
direct communication is now authorized, to recognize both the reality of what was happening on the ground and to recognize that sometimes Owners and Contractors may need to communicate without waiting for the design team.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
Court Strikes Expert Opinion That Surety Acted as a “De Facto Contractor”
November 27, 2023 —
David Adelstein - Florida Construction Legal UpdatesDesignating and admitting experts is a vital component of any construction dispute. Many construction disputes require experts. Many construction disputes can only be won with the role of an expert. Thus, experts and construction disputes go hand-in-hand. No doubt about it! Time needs to be spent on developing the right expert opinions to support your burden of proof. This means you want to designate the right expert that can credibly and reliably render an expert opinion.
It is common for one party to move to strike the testimony and expert opinions of another party. This is referred to as a Daubert motion. Sometimes the motion is about gamesmanship. Sometimes it is to see how the judge rules on the issue. Sometimes there is a legitimate reason associated with the expert opinion. And, sometimes, it is a combination of the above. Regardless of the reason, parties know the weight expert opinions can have and, therefore, treat the opinions seriously prompting the Daubert motion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Can an Owner Preemptively Avoid a Mechanics Lien?
May 25, 2020 —
William L. Porter - Porter Law GroupVarious sections of the California Civil Code, beginning with section 8000, protect the right of contractors, subcontractors and suppliers in the construction industry to obtain payment for work performed and materials supplied to construction projects. Under these statutes, unpaid claimants are entitled to use mechanics liens, stop payment notices and other methods to protect their right to payment. Mechanics liens allow unpaid claimants to sell the property where the work was performed in order to obtain payment. Stop payment notices force the owner or the bank to set money aside to pay unpaid claimants. Article XIV of our California Constitution even elevates the mechanics lien remedy to a “constitutional right”. The system generally works well, and claimants are paid.
As someone who practices and teaches construction law, I have noticed a seldom used statutory tool that seems to provide a mechanism for property owners under certain circumstances to prevent subcontractors and suppliers from imposing enforceable mechanics lien on property where work was performed. Under California Civil Code section 8520, it appears that all that an owner of property need do to avoid a mechanics lien on its property is to give a proper notice (per Civil Code section 8100 et seq.) to a person who has a mechanics lien right (a subcontractor or supplier) that the owner is invoking Civil Code section 8520 and that if the claimant is unpaid for work performed or materials supplied to the owner’s property that the claimant must either provide the owner with a stop payment notice or forfeit the right to a mechanics lien on the owner’s property. This would allow an owner to avoid a mechanics lien on its property if the claimant failed to send a stop payment notice to the owner.
Providing the “notice” under Civil Code section 8100 appears to be easy. It can be sent by “registered or certified mail or by express mail or by overnight delivery by an express service carrier”. It can even be by “hand delivery”. As far as the notice itself, it would seem that it can be very simple and easily performed under the process described below, which can be implemented within the office of any owner or developer.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Idaho Business Review Names VF Law Attorney Brittaney Bones Women of the Year Honoree
July 31, 2023 —
VF LawMeridian, Idaho: June 23, 2023 –
VF Law, a full-service law firm with offices across the Pacific Northwest and the Southwest, is pleased to announce that associate
Brittaney Bones has been recognized as an honoree for the 2023 Idaho Business Review Women of the Year Awards. The distinguished recognition celebrates 50 female leaders across Idaho who have made their mark while continuing to pave the path of leaders for the future.
When reviewing the applications, the judges considered excellence in leadership and a willingness to advance mentorship opportunities among the other considerations. In her work with the Community Associations Institute (CAI) Idaho, Bones currently serves as Vice Chair for the Legislative Action Committee. She monitors state legislation coming out of Boise. Accordingly, Bones seeks to educate lawmakers specifically on how pending legislation will affect the lives of people living and working throughout the Gem State. She also mentors students at the College of Idaho and has donated her time to the Rock Bottom Foundation, which provides meals to the unhoused.
Bones’s other accolades include an International Law Writing Award from Davis Wright Tremaine (DWT) for her 2020 article “Potential Solutions to Concerns over the Treatment of U.S. Investment in China: The Need for a U.S.-China Bilateral Investment Treaty.” She frequently speaks at CAI events, helping to prepare her fellow legal professionals for challenges in the field—and those yet to come.
About VF Law
VF Law is a full-service, multi-state law firm. At VF, we believe that experience and knowledge are crucial; that’s why every attorney on our staff maintains a high level of expertise to ensure client success. VF possesses unmatched experience in providing HOA guidance, planning for healthy buildings from the ground up, helping small businesses and corporations run smoothly, handling real estate transactions and disputes, creating wills and trusts, and more. Visit www.vf-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
Bank Window Lawsuit Settles Quietly
October 02, 2013 —
CDJ STAFFThe Federal Reserve Bank of St. Louis has filed a motion to dismiss its breach of contract lawsuit over the windows McCarthy Building installed in the bank’s building. The bank alleged that the 498 windows were defective and needed to be replaced at a cost of about $1.5 million.
But on September 11, the bank acted to dismiss the suit following a settlement with the defendants. The terms of the settlement was not disclosed. All parties will be covering their own legal costs.
Read the court decisionRead the full story...Reprinted courtesy of
ASCE and Accelerator for America Release Map to Showcase Projects from Bipartisan Infrastructure Law
November 15, 2022 —
The American Society of Civil EngineersRESTON, Va. – The American Society of Civil Engineers (ASCE) in partnership with Accelerator for America today announced the release of a new map which features projects that are getting underway with funding from the Infrastructure Investment and Jobs Act (IIJA), otherwise known as the Bipartisan Infrastructure Law (BIL). As the one year anniversary of the BIL approaches on November 15th, funding has been steadily making its way to state and local agencies across the nation, and now it is possible to track how communities are benefiting from investments.
The Bipartisan Infrastructure Law invests in all 17 of the infrastructure categories included in ASCE's 2021 Report Card for America's Infrastructure, which was released eight months before official passage of the law and had assigned our nation's infrastructure a cumulative grade of 'C-'. Communities are now benefiting from replaced lead service lines, safer roads and bridges, and new transit connections.
To view the map, please visit https://infrastructurereportcard.org/bil-project-map/.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of
Montrose Language Interpreted: How Many Policies Are Implicated By A Construction Defect That Later Causes a Flood?
March 17, 2011 —
Shaun McParland BaldwinThe Court of Appeals of Indiana recently addressed the “Montrose” language added to the CGL ISO form in 2001 in the context of a construction defect claim where a fractured storm drain caused significant flooding a year after the drain was damaged. The insuring agreement requires that “bodily injury” or “property damage” be caused by an “occurrence” and that the “bodily injury” or “property damage” occur during the policy period. The Montrose language adds that the insurance applies only if, prior to the policy period, no insured knew that the “bodily injury” or “property damage” had occurred in whole or in part. Significantly, it also states that any “bodily injury“ or “property damage” which occurs during the policy period and was not, prior to the policy period known to have occurred, includes a continuation, change or resumption of that “bodily injury” or “property damage” after the end of the policy period.
In Grange Mutual Cas. Co. v. West Bend Mut. Ins. Co., No. 29D04-0706-PL-1112 (Ct. App. IN March 15, 2011), http://www.ai.org/judiciary/opinions/pdf/03151109ehf.pdf, Sullivan was the General Contractor for a school construction project. Its subcontractor, McCurdy, installed the storm drain pipes. One of the storm pipes was fractured in 2005 while McCurdy was doing its installation work. More than a year later, the school experienced significant water damage due to flooding. It was later discovered that the flooding was due to the fractured storm drain. Sullivan’s insurer paid $146,403 for the water damage. That insurer brought a subrogation claim against McCurdy and its two insurers: West Bend and Grange. West Bend had issued CGL coverage to McCurdy while the construction was ongoing , including the date in which the storm pipe was fractured. Grange issued CGL coverage to McCurdy at the time of the flooding. Those two carriers jointly settled the subrogation claim and then litigated which insurer actually owed coverage for the loss. Significantly, the loss that was paid included only damages from the flooding, not any damages for the cost of repairing the pipe.
Read the full story...
Reprinted courtesy of Shaun McParland Baldwin of Tressler LLP. Ms Baldwin can be contacted at sbaldwin@tresslerllp.com
Read the court decisionRead the full story...Reprinted courtesy of
Housing Starts Surge 23% in Comeback for Canadian Builders
July 15, 2019 —
Theophilos Argitis - BloombergCanadian housing starts unexpectedly surged in April, in another sign of recovery for the nation’s battered real estate market.
Builders started work on an annualized 235,460 units last month, the highest level in 10 months and up 23 percent from 191,981 units in March, the Canada Mortgage and Housing Corp. reported Wednesday. The gain was driven by new multi-unit construction in Toronto and Vancouver.
Read the court decisionRead the full story...Reprinted courtesy of