Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Is it the Dawning of the Age of Strict Products Liability for Contractors in California?
March 30, 2016 —
Garret Murai – California Construction Law BlogIt was the Age of Aquarius.
And everything was changing. Politically, socially . . . and legally.
Through the 19th Century the doctrine of caveat emptor, literally “let the buyer beware,” was the rule of law. Under the doctrine a buyer was expected to protect him or herself against both obvious and hidden defects in a product.
It wasn’t until the late 1800s that U.S. courts began to impose implied warranties – for merchantability and fitness for a particular purpose – to protect consumers. But implied warranties were premised on their being a contract between the manufacturer and the user of a defective product, and by the mid 20th Century it was increasingly uncommon for consumers to purchase products directly from a manufacturer.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Quick Note: Not In Contract With The Owner? Serve A Notice To Owner.
August 13, 2019 —
David Adelstein - Florida Construction Legal UpdatesA subcontractor or supplier not in direct contract with an owner must serve a Notice to Owner within 45 days of initial furnishing to preserve construction lien rights. Of course, the notice of commencement should be reviewed to determine whether the subcontractor or supplier has construction lien or payment bond rights so that it knows how to best proceed in the event of nonpayment. Serving a Notice to Owner should be done as a matter of course — a standard business operation; no exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Washington Supreme Court Sides with Lien Claimants in Williams v. Athletic Field
September 30, 2011 —
Douglas Reiser, Builders Council BlogThe Washington Supreme Court issued their opinion today on Williams v. Athletic Field, perhaps the most talked about construction law case in the past few years. I have discussed this case exhaustively here on Builders Counsel. Today we have a resolution.
In an unanimous opinion issued today, the high court sided with lien filers who followed a sample form provided in RCW 60.04.091. Additionally, the court found that a lien company - and presumably other persons - could sign the lien for the lien claimant, as an agent, without invalidating the lien.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
The Future of Construction Work with Mark Ehrlich
February 19, 2024 —
Aarni Heiskanen - AEC BusinessIn this episode of the AEC Business
podcast, I had the pleasure of speaking with Mark Ehrlich, a veteran of the construction industry from the USA and the author of “The Way We Build: Restoring Dignity to Construction Work.” Our conversation delved into the evolving landscape of construction work and the challenges faced by construction workers today.
Mark shared his extensive background, starting as a carpenter and rising through the ranks to become the head of a 25,000-member union organization. His experience spans decades, and he has authored three books and numerous articles on labor issues.
The historical labor shifts
We discussed the historical shift from a predominantly unionized construction workforce to the current bifurcated system in the US, where union strongholds in the north contrast sharply with the non-union, lower-wage environments in the south and other regions. Mark highlighted the issues of wage theft, declining safety standards, and the exploitation of undocumented workers.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Portion of Washington State’s Prevailing Wage Statute Struck Down … Again
July 04, 2023 —
Brett Hill & Mason Fletcher - Ahlers Cressman & SleightIn 2018, the Washington Legislature amended its prevailing wages statute adopting S.S.B 5493 and codified as RCW 39.12.015(3). RCW 39.12.015(3) changed how the Washington State Department of Labor and Industries’ industrial statistician set the prevailing wages for employees on public works projects, from a county-by-county basis to a “geographic jurisdiction” basis established in collective bargaining agreements (“CBA”) or if multiple CBAs, the CBA with the higher wage would prevail. This change proved problematic for contractors since it allowed a minority of employees to determine the prevailing wage through side agreements and limited meaningful wage negotiations by industry trade groups. Contrary to the previous rule wherein wages were set by the average or majority wage rate in a certain county (which was normally the collectively bargained wage) and provided some flexibility to the industrial statistician in determining the prevailing wage, now, RCW 39.12.015(3)(a) directs the industrial statistician to “establish the prevailing rate of wage by adopting the hourly wage … paid for the geographic jurisdiction established in [CBAs],” removing flexibility, and requiring the inclusion of CBA (which could encompass multiple counties) wage rates as a part of the prevailing wage formula.
Reprinted courtesy of
Brett Hill, Ahlers Cressman & Sleight and
Mason Fletcher, Ahlers Cressman & Sleight
Mr. Hill may be contacted at brett.hill@acslawyers.com
Mr. Fletcher may be contacted at mason.fletcher@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
Hunton’s Geoffrey Fehling Confirmed to DC Bar Foundation’s Young Lawyers Network Leadership Council
December 30, 2019 —
Michael S. Levine - Hunton Andrews KurthCongratulations to Hunton Andrews Kurth LLP insurance recovery lawyer,
Geoffrey Fehling, on his confirmation by the DC Bar Foundation’s Board of Directors to the organization’s Young Lawyers Network Leadership Council.
As the leading funder of civil legal aid in the District of Columbia, DCBF awards grants to the District’s legal services organizations that provide free civil legal services to low-income and underserved people in the District. Since its inception, DCBF has awarded more than $80 million in grants.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
NYC’s Next Hot Neighborhoods Targeted With Property Funds
August 20, 2014 —
Jonathan LaMantia – BloombergNew York’s real estate world is filled with tales of ordinary people who bought property decades ago and saw values skyrocket to the millions. Seth Weissman is seeking investors to get in early on the next hot neighborhoods.
The veteran of Goldman Sachs Group Inc. (GS) and hedge fund Perry Capital LLC started CityShares, which enables participants to reap rewards from increasing apartment demand in gentrifying areas. Investors who pledge at least $100,000 to one of the program’s neighborhood-focused funds become partial owners of a group of buildings and share in the rental income. The first pool is more than halfway toward its target of $5 million, which will be used to buy properties in Brooklyn’s Bedford-Stuyvesant.
Harlem in upper Manhattan is next, with a goal of as much as $20 million. Additional funds are planned for Bushwick, Crown Heights and Sunset Park, all in Brooklyn. Renters are pushing into those more-distant areas after getting squeezed out of the borough’s waterfront communities, where leasing costs rival Manhattan’s. CityShares is the first program of its kind and offers a way to invest in burgeoning markets that are poised to grow as New York’s workforce expands, Weissman said.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan LaMantia, BloombergMr. Lamantia may be contacted at
jlamantia1@bloomberg.net