New York Bars Developers from Selling Condos due to CD Fraud Case
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to GlobeSt, New York “Attorney General Eric T. Schneiderman has announced a settlement agreement that bars developers Joseph Scarpinito and Shiraz Sanjana—and five affiliated entities they own and operate—from offering or selling securities, including condo and coop sales, in or from New York State.”
The settlement is in “result of an investigation by the Attorney General’s real estate finance bureau into allegations of fraud by the developers of the Mirada, an eight-story Harlem condominium.” GlobeSt also stated that the agreement “provides for binding arbitration with the condo purchasers for alleged construction defects, and requires the developers to pay $500,000 in penalties and fines to New York State.”
Read the court decisionRead the full story...Reprinted courtesy of
General Contractor’s Intentionally False Certifications Bar It From Any Recovery From Owner
November 03, 2016 —
Masaki James Yamada – Ahlers & Cressman PLLCIn a public works dispute in Massachusetts, a Massachusetts Court judge ruled that a general contractor could not recover any of its over $14 million claim against a public owner because it had violated its contract with the Owner by certifying that it had paid its subcontractors in full and on time when in fact it had not.[i] The case involves a contract dispute arising from a state and federally-funded project to design and construct a fiber optic network in western Massachusetts. The Owner was a state development agency established and organized to receive both state and federal funding to build a 1,200–mile fiber optic network known as MassBroadband123 in Western Massachusetts (the Project). Of that amount, $45.4 million was awarded pursuant to the American Recovery and Reinvestment Act of 2009 (ARRA). One of the stated goals of ARRA was (as its title suggests) to create jobs in the wake of the 2008 recession and to provide a direct financial boost to those impacted by the economic crisis. In the context of the instant case, that meant that, if there were to be subcontractors on the job providing labor and materials, they needed to be paid on a timely basis in keeping with the statutory purpose of stimulating the economy.
Read the court decisionRead the full story...Reprinted courtesy of
Masaki James Yamada, Ahlers & Cressman PLLCMr. Yamada may be contacted at
myamada@ac-lawyers.com
On-Site Supersensing and the Future of Construction Automation – Discussion with Aviad Almagor
September 06, 2021 —
Aarni Heiskanen - AEC BusinessFor
this episode of WDBE Talks, we sat down with Aviad Almagor of Trimble Ltd. to discuss sensor technology in the modern built environment. Our conversation touched on the on-site implementation of robotics and AI-based solutions, the importance of data capture, and the challenges facing the sector today and in the years ahead.
Aviad Almagor is the Division Vice President of Emerging Technologies with Trimble Ltd., a California-based hardware, software, and tech company that specializes in the development of Global Navigation Satellite Systems (GNSS) and recently collaborated with Boston Dynamics to automate construction processes.
“AI in construction is a very exciting topic though the industry is traditionally not very well-equipped to adopt technology in a very effective way. AI is an enabling technology that can be used to support and augment work. This means we can automate processes; predict delays in schedule; cost changes; even design issues and prescribe and provide decision-makers with the right information to be efficient and to make the right choices for projects.” Aviad noted in our interview.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Construction Defect Reform Dies in Nevada Senate
May 10, 2013 —
CDJ STAFFNevada’s SB161 has failed to move out of the Senate Judiciary Committee. The bill would have reduced the time in which homeowners could file suits and also would have forbidden the inclusion of attorney’s fees as damages. A similar bill remains active in the Nevada House.
Read the court decisionRead the full story...Reprinted courtesy of
CA Supreme Court Permits Insurers to Bring Direct Actions Seeking Reimbursement of Excessive Fees Against Cumis Counsel Under Limited Circumstances
August 19, 2015 —
David W. Evans & Valerie A. Moore – Haight Brown & Bonesteel LLPThe California Supreme Court held in Hartford Casualty Insurance Company v. J.R. Marketing, L.L.C. (Squire Sanders) (8/10/2015 - #S211645) that if Cumis counsel, operating under a court order which such counsel drafted and which expressly provided that the insurer would be able to recover excessive fees, sought and received fee payments from the insurer that were fraudulent or otherwise manifestly and objectively useless and wasteful when incurred, Cumis counsel have been unjustly enriched at the insurer’s expense and the insurer will be permitted under such limited circumstances to seek reimbursement directly from Cumis counsel.
Certain Hartford insureds who had been issued commercial general liability policies were sued in multiple proceedings for a variety of claims, including unfair competition, defamation and intentional misrepresentation. Hartford disclaimed a duty to defend or to indemnify the defendants on the grounds that the acts complained of occurred prior to Hartford’s policy, and that some of the defendants were not Hartford insureds. A coverage action was filed by some of the insureds against Hartford; they were represented by the Squire Sanders law firm. Although Hartford subsequently agreed to defend several of the defendants subject to a reservation of rights, it declined to pay defense expenses incurred prior to the date of such agreement. Some months later, the trial court entered a summary adjudication order, finding that Hartford had a duty to have defended the liability action on the date it was originally tendered; the order required Hartford to fund the insured’s defense with independent counsel (i.e., so-called “Cumis” counsel; see San Diego Federal Credit Union v. Cumis Insurance Society, Inc. (1984) 162 Cal.App.3d 358). The insureds retained Squire Sanders as their Cumis counsel.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Waive Too Much In Your Mechanic’s Lien Waiver
December 22, 2019 —
Christopher G. Hill - Construction Law MusingsIn the past few years, the Virginia General Assembly has, with certain caveats, precluded pre-furnishing waiver of mechanic’s lien rights. While this essentially outlawed the types of mechanic’s lien waiver clauses that pervaded construction contracts in Virginia, the key to the previous sentence is “pre-furnishing.” What the General Assembly left intact were the usual waivers of mechanic’s lien rights typically required to be provided to Owners and others in the payment chain in exchange for payment.
These lien waivers come in a few “flavors” from conditional to unconditional, partial to full. Their terms usually include an acknowledgement of receipt of payment (we’ll get to this later), and a statement that the one seeking payment knows of no possible claims by lower tier subcontractors and then waives all mechanic’s lien rights against the property for work performed and included in the request for payment. Often over my years as a Virginia construction attorney, I have noticed that these waivers are often signed without comment or review. They are just part of the process and more often than not are not even an issue for most projects. Of course, if they are an issue they can be a big one, and their terms can come back to bite a claimant that has not properly vetted them.
The first potential issue is waiving lien rights while acknowledging receipt prior to actual receipt of the check or wire. Many of the waiver forms that are out there list a payment amount, or possibly simply state that the waiver is in exchange for some small payment, and then state “receipt of which is acknolwedged” or something similar. The issue here is that receipt may not have happened yet because these lien waivers are submitted as part of the payment package in order to get paid in the first place. In short, should you sign the waiver prior to payment, you may have acknowledged a non-event and in the event of non-payment have a written document stating that you waived your claim to a lien for that money. What a court would do with this, I am unsure, but why risk it? My advice, be sure your waiver is contingent on actual clearance of payment as well as receipt.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
SCOTUS to Weigh Landowners' Damage Claim Against Texas DOT
November 13, 2023 —
Mary B. Powers - Engineering News-RecordThe U.S. Supreme Court has agreed to hear a case this term that could affect whether states must pay compensation to landowners whose property was damaged by public project execution. Payments also could extend to state owned utilities and others.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
How Fort Lauderdale Recovered a Phished $1.2M Police HQ Project Payment
May 13, 2024 —
Richard Korman - Engineering News-RecordJan. 25th was a happy day for the city of Fort Lauderdale, Fla., as Mayor Dean Trentalis and Police Chief William Schultz announced in a press conference the recovery of a $1.162-million electronic payment meant for Moss Construction that had been stolen in September via an email phishing fraud.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of