Recent Statutory Changes Cap Retainage on Applicable Construction Projects
March 11, 2024 —
Patrick McKnight - The Dispute ResolverRecent reforms to certain state retainage laws have reduced the lawful amount of withholding permitted on construction projects. In theory, retainage allows an owner to mitigate the risk of incomplete or defective work by withholding a certain portion of payment until the construction project is substantially complete. Recent statutory developments in Washington, New York, and Georgia represent significant changes in how much an owner may retain on applicable construction projects in those jurisdictions. The details of each state’s retainage laws vary in many important respects. Most states set caps at 5% or 10%, with important variations depending on the type of project and the amount of progress completed. Some states require retainage to be held in an escrow account, but most do not. Many federal construction projects allow up to 10% retainage, while other federal agencies do not require any retention. See 48 CFR § 52.232-5(e) - Payments Under Fixed-Price Construction Contracts.
The ongoing motivation for retainage reform is typically framed in terms of reducing delays in getting payment to subcontractors who complete their scope of work on time and free from defects.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Construction Contract Provisions that Should Pique Your Interest
September 30, 2019 —
Christopher G. Hill - Construction Law MusingsConstruction contracts are a big part of my legal practice and the drumbeat here at Construction Law Musings. Why? Because not only does your construction contract set the expectations and “rules of the game” for a construction project, it will be read strictly and literally by the Virginia courts should there be a dispute. For these reasons, construction professionals need to be alert for the language in certain key clauses in a construction contract to assure that these clauses are as balanced as possible and also well understood. Here are my “Top Five”:
- “Pay if Paid”- These clauses are almost always in the subcontracts between a general contractor and a subcontractor and are enforceable in Virginia if drafted correctly and under the proper circumstances.
- Change Orders- Whether work is subject to a change order and the required payment for any changed work are often a key source of contention (read legal fees). A properly drafted and followed change order provision can help avoid much of this contention.
- Indemnity- Much has been made in recent years about indemnity provisions and their enforceability. All parties in the construction payment chain can and should be aware of how to best draft their indemnity provisions to make them enforceable. Failure to do so can be catastrophic.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Strict Rules for Home Remodel Contracts in California
June 06, 2018 —
Daniel F. McLennon - Smith CurrieHome remodeling in California is governed by strict contracting laws intended to protect consumers. The Contractors State Licensing Board, (“CSLB”) is particularly concerned about contractors working without permits, contractors taking payment in excess of the value of the work complete–including deposits in excess of $1,000–and contractors refusing to complete projects. They are also concerned about contractors who fail to comply with the Home Improvement Contract (“HIC”) laws. At a minimum, it takes six pages of contract language for an HIC to comply with California law. Most contractors do not get it right, leaving themselves exposed to license discipline, misdemeanor criminal prosecution, and void contracts. The stakes are high, and contractors are advised to learn and comply with the HIC laws.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel F. McLennon, Smith CurrieMr. McLennon may be contacted at
dfmclennon@smithcurrie.com
Florida Accuses Pool Contractor of Violating Laws
June 28, 2013 —
CDJ STAFFOne customer said that after his pool was finished, he started having problems with the concrete and tiles. He’s still waiting for the $7,300 he was awarded at arbitration. Others have complained that Nationwide Pools dug up their back yards and didn’t finish the work. Construction defects were not repaired, despite promises. And even after the company stopped doing any work anywhere, they continued to charge their customers “progress payments.”
The State of Florida has stepped into this, seeking restitution for homeowners who were charged for partially built or defective pools, and preventing the company officials from ever working in the pool construction industry. According to the suit, customers who complained about delays were told “a series of lies and misrepresentations about ‘supply shortages’ and ‘damaged items’ in order to string them along.”
Read the court decisionRead the full story...Reprinted courtesy of
#10 CDJ Topic: Carithers v. Mid-Continent Casualty Company
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFCraig Martin of
Lamson Dugan and Murray, LLP on his
Construction Contractor Advisor blog used the Carithers case to demonstrate how “[w]hen you are involved in construction litigation, you have battles on several fronts, including those against subcontractors, owners, insurers and the court. Shoring up your defenses on each of these fronts is imperative, or you may lose the battle or, worse yet, the war.” Martin discusses the various “battle fronts” including the “Claim Against Contractor,” “Where Are You Litigating,” “Claim Against Insurance Company,” and “Damages.”
Read the full story...
In the article, “Duty to Defend Construction Defect Case Affirmed, Duty to Indemnify Reversed In Part,” attorney
Tred R. Eyerly also covered the Carithers case. Eyerly explained, “Determining whether there was coverage for the damages awarded required the court to decide which trigger applied. Examining the policy language, the court determined that property damage occurred when the damage happened, not when the damage was discovered or discoverable. Therefore, the district court did not err in applying the injury in fact trigger.”
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Sudden Death”
October 17, 2023 —
Daniel Lund III - LexologyIt’s not football, though. Rather, just when you thought it was safe in Louisiana to wait to file a garden-variety construction contract payment claim, an appellate court slams the door on it – applying a statute of “repose” to your claim.
“Personal actions” – such as an action on contract – are generally subject in Louisiana to a 10-year “liberative prescription,” the applicable statute of limitations pursuant to Louisiana Civil Code article 3499.
Like some other states, Louisiana has a statute of “repose” – imposing “peremption” rather than prescription for claims having to do with construction projects – limiting those claims (generally speaking) to five years post-completion. Like other statutes of “repose,” Louisiana Revised Statute 9:2772 provides that claims on construction projects may not be filed after five years, a duration which is not subject to interruption or extension.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
The Regulations on the Trump Administration's Chopping Block
August 02, 2017 —
Pam Radtke Russell - Engineering News-RecordThe Trump administration's next big step toward repealing the controversial Waters of the U.S. (WOTUS) rule is official, with a proposal to rescind the Obama-era regulation appearing in the Federal Register on July 27, setting off a relatively short comment period that will end Aug. 28.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMr. Russell may be contacted at
Russellp@bnpmedia.com
Five Frequently Overlooked Points of Construction Contracts
October 18, 2021 —
Craig H. O'Neill - White and Williams LLPThere is no shortage of articles addressing the key points of construction contracts. Just enter that phrase into any internet search engine and you will find plenty. It should go without saying that a construction contract should be in writing, it should clearly identify the scope of work to be performed and the sums to be paid for that work, and it should address the parties’ rights and responsibilities with regard to termination or suspension of the contract, correcting defective work, and handling claims and disputes—just to name a few. Of course, these items should receive their due consideration. Too often, however, other important aspects of the construction contract get shortchanged. This article aims the spotlight on five often overlooked aspects of construction contracts.
Project Schedules
Surprisingly, many construction contracts pay little attention to a central component of any construction project: the project schedule. Many contracts provide the dates of commencement and substantial completion but not much else. With the frequent use of project management techniques such as the Critical Path Method (CPM) and the associated software, it is easier than ever to identify which tasks should be prioritized and identify potential areas of delay. The owner’s contract with the general contractor should clearly define the scheduling methods used and provide measures to keep the parties informed of the progress of the work. By including basic scheduling requirements in the contract documents—such as the submission of “Baseline Project Schedules” (consistent with the contract time provisions), “Schedule Progress Updates” (comparing the progress of the work against the Baseline Project Schedule), and “Schedule Recovery Plans” (when Schedule Project Updates indicate projected delays)—the parties can avoid or reduce disputes over project delays that often lead to litigation.
Read the court decisionRead the full story...Reprinted courtesy of
Craig H. O'Neill, White and Williams LLPMr. O'Neill may be contacted at
oneillc@whiteandwilliams.com