Study May Come Too Late for Construction Defect Bill
February 14, 2013 —
CDJ STAFFColorado State Senator Mark Scheffel removed his bill, Senate Bill 13-052, from the calendar of the Senate Judiciary Committee in anticipation of a study which he feels would be pertinent to the discussion. The bill would stop communities from suing developers over noise and vibration issues associated with transit facilities, and would also provide for developers fixing construction defects before being sued. Senator Scheffel said that the intent of his bill was to spur development near transit facilities.
The study, commissioned by the Denver Regional Council of Governments, would focus on the effects of the state’s construction defects law on housing. It might not come soon enough for the senator’s bill. The Denver Business Journal reports that the study, which will take four months to complete, doesn’t yet have a contract. The Legislature must adjourn by May 8, so it is not possible for the study to be concluded before the end of this legislative session.
Read the court decisionRead the full story...Reprinted courtesy of
Top Five Legal Mistakes in Construction
April 04, 2022 —
Jonathan A. Cass, Nicholas F. Morello & John A. Greenhall - Construction ExecutiveMany contractors repeatedly make the same mistakes in negotiating contracts. Here are the most common mistakes contractors make—and how they can be avoided.
1. Not Being Careful With Force Majeure Clauses
To protect themselves from liability in the event of unforeseen circumstances like fires, floods, wars, unusual delays in deliveries, strikes, pandemics or acts of God, contractors should ensure their contracts contain robust force majeure provisions. These provisions state that in the event of any extenuating circumstances outside of its control, the contractor is not liable for any damages that result from a delay to the project completion date and is entitled to a time extension. This clause has been critical in addressing COVID-19-related disruptions and the current material shortages. Contractors should be wary, however, of “no damage-for-delay” language, which often appears in conjunction with these clauses.
Reprinted courtesy of
Jonathan A. Cass, Nicholas F. Morello and John A. Greenhall, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Cass may be contacted at jcass@cohenseglias.com
Mr. Greenhall may be contacted at jgreenhall@cohenseglias.com
Mr. Morello may be contacted at nmorello@cohenseglias.com
Read the court decisionRead the full story...Reprinted courtesy of
Expanded Virginia Court of Appeals Leads to Policyholder Relief
January 29, 2024 —
Michael S. Levine & Olivia G. Bushman - Hunton Insurance Recovery BlogExercising its newly expanded jurisdiction that now permits Virginia’s intermediate appellate courts to hear insurance coverage disputes, the Court of Appeals recently reversed a lower court decision that allowed a two-year “Suits Against Us” provision to serve as a basis for an insurer’s refusal to reimburse repair and replacement costs incurred more than two years after the date of loss. Bowman II v. State Farm Fire and Casualty Co., Record No. 1256-22-3 (Nov. 21, 2023). CAV (unpublished opinion).
In the proceeding below, the circuit court found no justiciable controversy and dismissed the complaint where repairs to the policyholder’s fire-damaged home continued more than two years after the date of the fire. The circuit court relied on a two-year limitation in the policy that governed the period within which the policyholder must bring suit against the insurer.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Olivia G. Bushman, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Bushman may be contacted at obushman@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Janus v. AFSCME
July 18, 2018 —
Ryan Foltz – Gordon & Rees Construction Law BlogOn June 27, 2018, the Supreme Court of the United States issued its decision in Janus v. AFSCME1. By a 5-4 vote, SCOTUS ruled that public employee unions cannot require non-members to pay union dues, even if those employees are benefiting from the services provided by the union. 28 states already had “right-to-work” laws on the books, meaning that unions in those states were already precluded from collecting fees from non-union members. This ruling makes that ban a national standard.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan Foltz, Gordon & Rees Scully MansukhaniMr. Foltz may be contacted at
rfoltz@grsm.com
Cumulative Impact Claims and Definition by Certain Boards
June 21, 2024 —
David Adelstein - Florida Construction Legal UpdatesWhat is a cumulative impact claim? This is commonly referred to as the unforeseeable ripple effect of changes, i.e., the death by a thousand cuts. Cumulative impact claims refer to a disruption on productivity based on the cumulative impact of changes and their impact on unchanged work. Cumulative impact claims are difficult claims to prove, particularly based on the causation standpoint (and argument they could be released based on change order language). If pursuing or considering a cumulative impact claim, you will need to work with a consultant(s) and lawyer that understand the dynamic of these claims to best maximize your arguments and recovery from a causation and damages standpoint. Cumulative impact damages are real. They occur. But they are not damages you can just throw out there or use loosely and expect to develop traction on compensation.
Below is how cumulative impact claims are defined by certain Boards of Contract Appeals. The definitions are important.
In Appeal of Centex Bateson Construction, Co., Inc., 9901 BCA P 30153, VABCA 4613 (VABCA 1998), the Board explained:
Direct impact, as the immediate and direct effect of a change on unchanged work, is considered foreseeable.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Subcontractor Allowed to Sue Designer for Negligence: California Courts Chip Away at the Economic Loss Doctrine (Independent Duty Rule)
August 30, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCAn architect may have to pay over $1 million to a subcontractor who was contractually obligated to rely on the designer’s plans – even though the architect was not a party to the contract.[1] That was the ruling in U.S. f/u/b/o Penn Air Control, Inc. v. Bilbro Constr. Co., Inc.[2]
The dispute involved a $7.3 million design-build contract award to Bilbro Construction (“Bilbro”) to renovate a facility for the Naval Facilities Engineering Command in Monterey, California. Bilbro hired an architect (“FPBA”) to serve as the designer of record and provide all the architectural design services. FPBA’s design team included an acoustical sub-consultant (Sparling). The general contractor (design builder) also retained Alpha Mechanical (Alpha) as the mechanical electrical and plumbing (“MEP”) design/build subcontractor. Alpha, in turn, subcontracted the MEP design to Shadpour Consulting Engineers. During the design phase of this project, Alpha’s MEP design was reviewed by FPBA, Bilbro, and Sparling at the 35, 75, and 100 percent design completion levels. Alpha demonstrated that it regularly received direct communications during design development from Sparling and FPBA, including comments, changes, and revisions. One example Alpha cited was it raised some concerns about anticipated noise level in eight rooms. Sparling made several recommendations to Alpha and Shadpour that were implemented.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Worker’s Compensation Exclusivity Rule Gets “Trumped” by Indemnity Provision
October 27, 2016 —
Garret Murai – California Construction Law BlogSorry, I couldn’t help myself with the title.
The next case, Aluma Systems Concrete Construction of California v. Nibbi Bros., Inc., California Court of Appeals for the First District, Case No. A145734 (August 16, 2016), discusses the interplay between indemnity provisions and the worker’s compensation exclusivity rule.
The worker’s compensation exclusivity rule generally provides that worker’s compensation insurance is the exclusive remedy of employees for injuries or death arising out of the course and scope of their employment.
In the Aluma case, the California Court of Appeals, addressed what happens when a subcontractor’s employees are injured on a project, sue the general contractor, and the general contractor, pursuant to an indemnity provision in its subcontract, tenders the claim to the subcontractor whose worker’s compensation insurance has already paid the employees.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Waive Your Claim Goodbye: Louisiana Court Holds That AIA Subrogation Waiver Did Not Violate Anti-Indemnification Statute and Applied to Subcontractors
May 23, 2022 —
Gus Sara - The Subrogation StrategistIn 2700 Bohn Motor, LLC v. F.H. Myers Constr. Corp., No. 2021-CA-0671, 2022 La. App. LEXIS 651 (Bohn Motor), the Court of Appeals of Louisiana for the Fourth Circuit (Court of Appeals) considered whether a subrogation waiver in an AIA construction contract was enforceable and, if so, whether the waiver also protected subcontractors that were not signatories to the contract. The lower court granted the defendants’ motion for summary judgment based on the subrogation waiver in the construction contract. The plaintiffs appealed the decision, arguing that the subrogation waiver violated Louisiana’s anti-indemnification statute. The plaintiffs also argued that even if enforceable, the subrogation waiver did not apply to the defendant subcontractors since they were not parties to the contract. The Court of Appeals ultimately held that the subrogation waiver did not violate the anti-indemnification statute because the waiver did not shift liability, which the statute was intended to prevent. In addition, the Court of Appeals found that the contract sufficiently satisfied the required elements for the defendant subcontractors to qualify as third-party beneficiaries of the contract.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at