They Say Nothing Lasts Forever, but What If Decommissioning Does?
June 10, 2019 —
Stella Pulman - Gravel2Gavel Construction & Real Estate Law BlogThe looming decommissioning liabilities of offshore energy producers have been a focus of the federal government in recent years. One recent case out of the U.S. Court of Federal Claims, Taylor Energy v. United States, highlights the tension between the federal government’s desire to maintain financial security for decommissioning activities, and that of an operator whose security is tied up indefinitely while the government awaits technological advances to allow for safe decommissioning.
The case relates to a trust agreement between Taylor Energy and the United States, established to secure Taylor’s decommissioning liabilities for 28 wells in the Gulf of Mexico. Taylor completed certain decommissioning work for which it was reimbursed by the trust. However, with over $400 million remaining in the trust, Taylor and the Bureau of Safety and Environmental Enforcement (BSEE) concluded that the ecological benefits of further decommissioning would be outweighed by the ecological risks. But despite recognizing that the limitations of current technology made the environmental impacts of further decommissioning work unjustifiable, the BSEE declined to release Taylor from its decommissioning obligations and instead decided to await “changes in technology and a better understanding of the undersea environment.” Because Taylor’s decommissioning obligations remained in place, the U.S. refused to release the remaining funds in the trust.
Taylor claimed that the United States should release the remaining funds in the trust because “decommissioning the remaining wells is not ‘currently technologically feasible.’” Taylor asserted that Louisiana law applied to the trust agreement, and that under Louisiana law every contract must be completed within an ascertainable term. By holding the trust funds until decommissioning was complete, Taylor argued that the government was essentially holding the funds in perpetuity given the technological infeasibility of completing decommissioning. Taylor also asserted that the agreement was premised on an impossibility (the full decommissioning of the wells), and/or a mutual mistake of the parties (that the wells could be decommissioned).
Read the court decisionRead the full story...Reprinted courtesy of
Stella Pulman, PillsburyMs. Pulman may be contacted at
stella.pulman@pillsburylaw.com
GIS and BIM Integration Will Transform Infrastructure Design and Construction
October 09, 2018 —
Nicolas Mangon - Engineering News-RecordAn unfortunate fact of the architecture and engineering professions and the construction industry is that, between every stage of the process—from planning and design to construction and operations—critical data is lost.
Read the court decisionRead the full story...Reprinted courtesy of
Nicolas Mangon, ENRENR may be contacted at
ENR.com@bnpmedia.com
Property Damage, Occurrences, Delays, Offsets and Fees. California Decision is a Smorgasbord of Construction Insurance Issues
November 21, 2017 —
Garret Murai - California Construction Law BlogOriginally published by CDJ on November 15, 2017
I read once that 97 percent of cases never go to trial. However, there are still the ones that do. And, then, there are the ones that do both. The following case, Global Modular, Inc. v. Kadena Pacific, Inc., California Court of Appeals for the Fourth District, Case No. E063551 (September 8, 2017), highlights some of the issues that can arise when portions of cases settle and other portions go to trial, the recovery of delay damages on a construction project through insurance, and the recovery of attorneys’ fees.
Global Modular, Inc. v. Kadena Pacific, Inc.
The U.S. Department of Veterans Affairs contracted with general contractor Kadena Pacific, Inc. (Kadena) to oversee construction of its Center for Blind Rehabilitation in Menlo Park, California. Kadena, in turn, contracted with subcontractor Global Modular, Inc. (Global) to construct, deliver and install 53 modular units totaling more than 37,000 square feet for a contract price of approximately $3.5 million.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
U.S. Firm Helps Thais to Pump Water From Cave to Save Boys
August 14, 2018 —
Dan Murtaugh - BloombergLike much of the world, Patrick Decker has been engrossed in the saga of 12 boys and their soccer coach who became trapped in a flooded cave in Thailand. Unlike most, Decker is in a position to do something about it.
As chief executive officer of Xylem Inc., one of the world’s top water technology firms, Decker spent much of last week reaching out to Thai officials and mobilizing his company of 17,000 employees to help. Decker said he sent four engineers to the cave site, and they assisted rescuers by boosting pumping power 40 percent. Thai Navy SEALs and international cave diving experts extracted eight boys over Sunday and Monday.
Read the court decisionRead the full story...Reprinted courtesy of
Dan Murtaugh, Bloomberg
Wisconsin Court of Appeals Re-affirms American Girl To Find Coverage for Damage Caused by Subcontractors
September 20, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court's finding of no occurrence and no property damage due to faulty workmanship was reversed by the appellate court. No. 5 Walworth v. Engerman Contracting, Inc., 2021 Wis. App. LEXIS 401 (Wis. Ct. App, July 30, 2021).
Engerman was the general contractor on a construction project at a residence. Engerman was hired to build a poll complex. Engerman subcontracted the project to Downes Swimming Pool Co., Inc. Downes purchased shotcrete (sprayed concrete) from Otto Jacobs Company LLC for the swimming poll walls and base.
After completion, the pool immediately began leaking. An investigation determined that the shotcrete material was not installed correctly, contributing to cracking in the pool walls and the steel reinforcing bars were not sufficient to prevent cracks in the pool walls. The owner demolished the pool and constructed a new one. Thereafter, the owner sued Engerman, its insurers (General Casualty Company of Wisconsin and West Bend Mutual Insurance Company) and Downes and its insurer. Downes filed a third-party complaint against Jacobs and its insurer (Acuity Mutual Insurance Company) alleging Jacobs negligently provided inferior shotcrete to Downes.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Revised Federal Rule Regarding Class-Wide Settlements
May 13, 2019 —
Edward M. Koch & Michael Jervis - White and Williams LLPThe United States Supreme Court recently approved and adopted amendments to Federal Rule of Civil Procedure 23 concerning class action practice as proposed by the Advisory Committee on Civil Rules. The amended rule went into effect on December 1, 2018. The amendments do not affect the core of the rule – the criteria for obtaining class certification. Instead, the changes are more subtle adjustments that update and modernize procedures and processes for notification to class members and obtaining approval of class settlements. Nonetheless, although the amendments are not breathtaking, there are important changes.
The first set of amendments apply to Rule 23(e), governing the process of settlement of a class action. First, the amendment makes explicit that the subsection applies not just to already certified classes, but also “a class proposed to be certified for purposes of settlement.” The changes also add some discretion of the court concerning when notice of a proposed settlement and settlement class should be provided. As part of the settlement approval process, the parties now are expressly required to give the court “information sufficient to enable it to determine whether to give notice of the proposal to the class.” The giving of notice is justified only if that information is sufficient to allow the court to determine it is likely to approve the proposed settlement and certify the class. Once notice is approved, the new rule recognizes modern developments by allowing that notice may be by “United States mail, electronic means, or other appropriate means.” The rule thus recognizes that in many cases traditional mail notice may still be best; in others e-mail notification might be the best way to reach class members.
Reprinted courtesy of
Edward M. Koch, White and Williams LLP and
Michael Jervis, White and Williams LLP
Mr. Koch may be contacted at koche@whiteandwilliams.com
Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Bad Faith Claim for Inadequate Investigation Does Not Survive Summary Judgment
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe insured's claim for bad faith investigation regarding their hail damage claim did not survive the insurer's motion for summary judgment. Amarillo Hospitality Tenant, LLC v. Mass. Bay Ins. Co., 2015 U.S. Dist. LEXIS 56228 (N. D. Tex. April 29, 2015).
A hailstorm caused damage to the Courtyard Marriot. The day after the storm, the insured inspected the roof of the hotel and observed damage to a sign and some aluminum vent tubes. No damage to the roof itself was observed. Subsequently, leaks were found on the tenth floor of the hotel. A public adjuster concluded that the roof had sustained damage during the hailstorm.
The insured filed a claim with Massachusetts Bay Insurance Company. The insurer paid for the cost of repairing the damaged sign. To determine whether the damage to the roof was caused by the hailstorm, the insurer hired Donna Engineering, who conducted two inspections of the roof. Both inspections concluded that the hailstorm did not cause damage to the roof. Consequently, the claim was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurance Attorney Gary Barrera Joins Wendel Rosen’s Construction Practice Group
July 26, 2017 —
Garret Murai - California Construction Law BlogWendel Rosen’s Construction Practice Group welcomes a new member to our band of merry men (and women), Gary Barrera.
Gary, an insurance attorney, has extensive experience with construction defect, property damage, professional liability and environmental claims. He has represented real estate developers and contractors in all aspects of construction defect litigation and has resolved insurance coverage disputes arising out of construction claims on behalf of policyholders. Prior to attending law school, Gary worked as a claims representative and examiner for several insurance carriers and third-party administrators.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com