Illinois Supreme Court Holds That the Implied Warranty of Habitability Does Not Extend to Subcontractors
March 04, 2019 —
Michael J. Ciamaichelo - The Subrogation StrategistThe implied warranty of habitability allows a homeowner to recover damages for latent defects that interfere with the intended use of a home. In Sienna Court Condo. Ass’n v. Champion Aluminum Corp., 2018 IL 122022, 2018 Ill. LEXIS 1244 (2018), the Supreme Court of Illinois held that buyers of new homes cannot assert claims for breach of the implied warranty of habitability against subcontractors involved in the construction of the homes because the subcontractors have no contractual relationship with the homeowners and the damages are purely economic. As the court explained, the implied warranty of habitability is a creature of contract (not tort) and, therefore, only exists when there is contractual privity between the defendants and the homeowners.
In Sienna, a group of condominium unit owners alleged that their new homes contained latent construction defects and asserted claims against the various parties involved in the construction and sale of the homes, including claims against the defendant subcontractors for breach of the implied warranty of habitability. The plaintiffs contracted with the property developer to purchase the homes, but the plaintiffs had no contractual relationship with the subcontractors involved in the construction of the homes. The Sienna court, overturning the decisions of the trial court and the appellate court, granted the subcontractors’ joint motion to dismiss the plaintiff’s claims for the implied warranty of habitability because the plaintiffs had no contractual relationship with the subcontractors and the damages were purely economic.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
California Fears El Nino's Dark Side Will Bring More Trouble
September 17, 2015 —
Brian K. Sullivan – BloombergA group of drought experts gathered in California this week, and it wasn’t long before the conversation turned to El Nino.
They weren’t touting it as the savior that will end the state’s four-year drought. Instead, they were looking at a darker scenario where the weather-changing phenomenon adds another year of dryness in the north while ravaging the south with floods.
“What do you say when the governor asks you what to do? ‘You prepare for flood and drought because there is a possibility you can get both,”’ said Mike Anderson, state climatologist.
Read the court decisionRead the full story...Reprinted courtesy of
Brian K. Sullivan, Bloomberg
DE Confirms Robust D&O Protection Despite Company Demise
February 18, 2015 —
James Yoder, Michael Onufrak and Siobhan Cole – White and Williams LLPOn Feb. 5, 2015, the United States Bankruptcy Court for the District of Delaware, per Judge Brendan L. Shannon, entered proposed findings of fact and conclusions of law in favor of the former president and CEO of Ultimate Escapes Inc., James M. Tousignant, and its chairman, Richard Keith, after determining that Tousignant’s actions in negotiating and executing a controversial asset purchase agreement were protected by the business judgment rule, despite the demise of the company a short time later. The failure of a business strategy, in and of itself, does not create liability on the part of the former directors and officers of a bankrupt company.
Background
Ultimate Escapes was a luxury destination club that provided its members with access to high-end vacation residences around the world. Unfortunately, Ultimate Escapes’ business suffered greatly from the economic downturn that began in 2008, and on Sept. 20, 2010, Ultimate Escapes filed voluntary petitions for relief pursuant to Chapter 11 of the Bankruptcy Code.
Reprinted courtesy of White and Williams LLP attorneys
James Yoder,
Michael Onufrak and
Siobhan Cole
Mr. Yoder may be contacted at yoderj@whiteandwilliams.com
Mr. Onufrak may be contacted at onufrakm@whiteandwilliams.com
Ms. Cole may be contacted at coles@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Pentagon Has Big Budget for Construction in Colorado
January 17, 2013 —
CDJ STAFFThe Pentagon is an important source of construction contracts, and one place where they’re acutely aware of this in Colorado Springs, Colorado. Luckily for the town’s economy, the military awarded $400 million in construction contracts to Colorado, many of them in the town of Colorado Springs.
Projects in Colorado Springs include facilities for a helicopter unit at Fort Carson and renovations at the Air Force Academy. The new operation center for defense intelligence at Buckley Air Force Base will be built in nearby Aurora. The price tag on the operations center is $117 million. Meanwhile, the military has thousands of both civilian and military employees who will be using these facilities.
Read the court decisionRead the full story...Reprinted courtesy of
“Freelance Isn’t Free” New Regulations Adopted in New York City Requiring Written Contracts with Independent Contractors
June 15, 2017 —
Kevin J. O'Connor - Peckar & Abramson. P.C.Attacks on employers for alleged misclassification of workers—particularly independent contractors—are continuing unabated, and the risk of liability for employers operating in New York City just increased. New York City has just adopted sweeping regulations requiring written contracts with certain freelancers and independent contractors. Anyone doing business in that jurisdiction should take notice and take action to comply with the law.
New York City’s “Freelance Isn’t Free Act,” N.Y.C. Administrative Code §§ 20-927 et seq. (“FIFA”) went into effect on May 15, 2017. This new law substantially regulates the relationship between a business and an independent contractor or “freelancer” working in New York City.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. O'Connor, Peckar & Abramson. P.C.Mr. O'Connor may be contacted at
koconnor@pecklaw.com
Hawaii Supreme Court Finds Climate Change Lawsuit Barred by “Pollution Exclusion”
November 05, 2024 —
Jason Taylor - Traub Lieberman Insurance Law BlogOn October 7, 2024, the Hawaii Supreme Court answered the question of whether an “accident” includes an insured’s reckless conduct in emitting harmful greenhouse gases (“GHGs”) and whether such emissions are “pollutants” as defined in a general liability policy’s pollution exclusion. In Aloha Petro., Ltd. v. National Union Fire Insurance Co. of Pitt., PA, No., 2024 Haw. LEXIS 179 (Oct. 7, 2024), the Hawaii Supreme Court answered in the affirmative as to both certified questions from the United States District Court for the District of Hawaii, holding that an insured’s reckless conduct can be an “accident” and that GHGs are “pollutants” under the policies’ pollution exclusions.
In the underlying case, the County of Honolulu and the County of Maui (the “Counties”) sued Aloha Petroleum, Ltd. (“Aloha”) and several other fossil fuel companies for climate change-related harms. Namely, the Counties alleged that the fossil fuel industry knew that its products would cause catastrophic climate change, and rather than mitigating their emissions, defendants concealed such knowledge, promoted climate science denial, and increased their production of fossil fuels. Aloha was allegedly on notice that its products caused harmful climate change through its former parent company, Phillips 66, and its current parent company, Sunoco. Given this knowledge, the District Court determined that the Counties allegations constituted reckless conduct by Aloha.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Exploring the Future of Robotic Construction with Dr. Thomas Bock
November 06, 2023 —
Aarni Heiskanen - AEC BusinessIn
this episode of the AEC Business podcast, host Aarni Heiskanen interviews Dr. Thomas Bock, a renowned expert in construction robotics. With 45 years of experience in the field and multiple books on the topic, Thomas shares his insights and expertise.
Tune in to learn more about his professional journey and the advancements in construction robotics.
An unconventional professional journey
Thomas’s journey in construction robotics began when he built his own house as a student. The labor-intensive process led him to explore the potential of robotics in construction. He studied civil engineering and architecture simultaneously, gaining a multidisciplinary understanding of the field. His interest in robotics grew when he saw the first welding robot at a Daimler-Benz factory in Stuttgart. This encounter sparked his curiosity and led him to question why robots couldn’t be used for assembling walls and buildings.
The Illinois Institute of Technology (IIT) in Chicago was one of Thomas’s destinations during his journey. There he studied under professors who had worked on iconic architectural projects. He also learned about Japanese companies like Toyota and Sekisui, which were producing houses using innovative methods. Intrigued by these advancements, Thomas secured a scholarship to study in Japan, where he discovered that the country was ahead of what he had known in the United States.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Does the UCC Apply to the Contract for the Sale of Goods and Services
July 03, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhat governs the transaction for the hybrid contract that includes both goods and services–the Uniform Commercial Code (UCC) or the common law? A question that is asked in numerous disputes. A good example is the recent case out of the Eleventh Circuit Court of Appeals, Wadley Crushed Stone Company, LLC v. Positive Step, Inc., 2022 WL 1639011 (11th Cir. 2022), dealing with Alabama law.
In this case, the plaintiff (buyer) wanted to build a granite plant in Alabama that would process 500 tons of granite per hour. The plaintiff reached out to a defendant company to start the process of building a granite plant. The defendant company engaged vendors and professionals in the due diligence process to determine the equipment the plaintiff would need. After this due diligence, plaintiff and defendant entered into a contract that included equipment and services. Thereafter, the parties modified the contract to reduce the amount for the erection, installation, and electrical work (about $1.5 Million) as plaintiff planned to independently hire the contractor to perform that work. The modified contract was worth $4,059,224.43 of which there were 25 lines items for equipment totaling $3,887,274.43 with the balance (less than 5% of the contract amount) for engineering (done by a third party), installation, setup, and calibration of scales.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com