Triable Issue of Fact Exists as to Insurer’s Obligation to Provide Coverage Under Occurrence Policy
March 08, 2021 —
Valerie A. Moore & Kathleen E.M. Moriarty – Haight Brown & Bonesteel LLPIn Guastello v. AIG Specialty Ins. Co. (No. G057714. filed 2/19/21 ord. pub. 2/23/21), a California appeals court held that triable issues of material fact exist which precluded summary judgment for an insurer seeking to disclaim coverage on the basis that the “occurrence” pre-dated the policy period where a dispute exists as to the timing of the subject “occurrence.”
In Guastello, a subcontractor built retaining walls from 2003 to 2004 for a housing development in Dana Point, California. In 2010, one of these retaining walls collapsed causing damage to a residential lot owned by Thomas Guastello.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Kathleen E.M. Moriarty, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com
Ms. Moriarty may be contacted at kemoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Termination Issues Part 4: What to Do When They Want to Fire You, the Architect or Engineer
August 14, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaWhat if you are told that your own design services are no longer needed or welcome on a project? Can they do that? What happens then? How do you protect yourself.
As you probably realize, while rare, the Owner does have the legal right to fire you “for cause”. See B101 §9.4, as long as the Owner gives you 7 days written notice. In fact, the Owner can terminate your contract for any reason at all (maybe you root for the wrong basketball team?) by terminating you for convenience (i.e., for any reason whatsoever) under B101 §9.5, again with 7 days written notice.
As with
Contractor terminations, the money you get when fired for convenience is much greater than when you are terminated for cause. If you are fired “for convenience”, you get paid for all services previously rendered as well as termination expenses, including anticipated profit on the value of services not performed. See B101 §9.7.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Failing to Adopt a Comprehensive Cyber Plan Can Lead to Disaster
January 13, 2020 —
Richard Volack - Construction ExecutiveDespite being aware of cyber risk, and even frightened by it, a shocking number of companies in the construction industry have neither a cyber insurance policy nor a basic cyber security plan to deal with a hack or breach into their computer systems. Once breached, companies with no plan in place become, essentially, a rudderless ship subject to the whims of criminal tides.
A proper cyber plan lays out at least the following:
- the criteria for when a plan would be triggered (i.e., in the event of a breach or a hack);
- which persons inside the company (in-house counsel, IT personnel, executive, project managers) and which persons outside the company (attorney with knowledge of cyber issues and ideally construction law as well; forensic computer experts, crisis management experts; and an insurance broker familiar with cyber policies) should be involved;
- the chain of command and communication in this type of situation and the distinct roles each of the above players will fulfill (Note: this is not the same as the normal corporate chain of command); and
- the various available options to address the breach situation, which will all depend upon the facts at issue—such as the type and extent of the breach and how much of what particular kind of information was lost, stolen or exfiltrated.
Reprinted courtesy of
Richard Volack, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Volack may be contacted at rvolack@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Capitol View-Corridor Restrictions Affect Massing of Austin’s Tallest Tower
October 17, 2023 —
David M. Brown - Engineering News-RecordThe stepped-back profile of a 66-story skyscraper in Austin, which will be the state capital’s tallest building when completed this fall, is a consequence of the city's height and massing limits to keep the view corridor to the capitol's dome unblocked.
Reprinted courtesy of
David M. Brown, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Fixing That Mistake
October 25, 2021 —
Patrick Barthet - Construction ExecutiveSomeone once said, more people could learn from their mistakes if they weren’t so busy denying that they made them in the first place.
In the construction industry, mistakes are not uncommon. Addressing them, however, can be complicated. What should a contractor do when the project owner says some aspect of the project is not satisfactorily completed or isn’t performing as it should? Should the contractor wait, hoping it may get resolved without having to do anything? Or should the contractor take on the repair or replacement as soon as practically possible?
Doing nothing may be easy but can expose the contractor to significant subsequent liability. Dealing with the issue, on the other hand, could result in the destruction of what might later be required evidence in any litigation which develops. Considered “spoliation,” such manipulation or elimination of evidence is a consequence to be avoided. Even though done with the best of intentions to fix a problem, the process can wind up exposing one to liability and damages.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Former Superintendent Sentenced in Rhode Island Tainted Fill Case
July 05, 2023 —
James Leggate - Engineering News-RecordA federal judge sentenced a contractor’s former superintendent June 20 for misleading officials about the source of fill and quality of contaminated fill used on the $410 million Route 6/10 interchange project in Rhode Island.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Landmark Montana Supreme Court Decision Series: Trigger and Allocation
January 24, 2022 —
Lorelie S. Masters, Patrick M. McDermott & Rachel E. Hudgins - Hunton Insurance Recovery BlogIn one of the top insurance-coverage decisions of 2021, the Montana Supreme Court at the end of the year handed down a landmark decision adopting the continuous trigger of coverage and “all sums” allocation, finding a duty to defend and ruling that the qualified, or “sudden and accidental” pollution exclusion did not apply. Nat’l Indem. Co. v. State, 499 P.3d 516 (Mont. 2021). The Supreme Court affirmed in part and reserved in part the rulings entered by the trial court, largely upholding a $98,000,000 judgment for the State against its CGL insurer for the policy years 1973 to 1975. The ruling thus helps ensure coverage for the hundreds of claims alleging that the State had failed to warn claimants of the dangers of asbestos exposures to workers in vermiculite mining and milling operations in Libby, Montana, operated by W. R. Grace (the “Libby Mine”).
Representing amicus curiae United Policyholders (“UP”), Hunton Andrews Kurth supported the position of the policyholder, the State of Montana, on the key rulings on trigger of coverage, allocation, and the pollution exclusion, with the court specifically citing to the Hunton brief in adopting all-sums allocation. This first post in our series covering the Montana Supreme Court’s decisions will address the court’s rulings on trigger of coverage and allocation.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth,
Patrick M. McDermott, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. McDermott may be contacted at pmcdermott@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Addressing the Defective Stucco Crisis
November 28, 2018 —
Wally Zimolong - Supplemental ConditionsI received several emails regarding the expose by Caitlin McCabe and Erin Arvedlund in the Philadelphia Inquirer titled “Rotting Within.” The story outlines the epidemic of defective stucco and other “building envelope” issues in Southeastern Pennsylvania that is causing homes to literally rot from within. Having litigated several of these cases, they are frustrating for both the attorneys that handle them and the homeowners who must deal with the reality that their home is rotting away. The story points to the multiple (and all too common) causes for the epidemic: unskilled subcontractors, lack of oversight and care, and poor construction drawings. The is no quick solution to the crisis and litigation regarding these defects is sure to proliferate.
However, there is one potential solution that the story does not cover and which could help alleviate some of the challenges homeowners face in recovering damages for their claims. The Pennsylvania Legislature must act to change the insurance laws in Pennsylvania to make defective construction covered by a developer’s, contractor’s, and subcontractor’s commercial general liability policy (“CGL”). Most homeowners and many attorneys incorrectly assume that defective construction is covered by insurance. This assumption makes sense. If someone operates a car in a negligent manner and hits your car and causes damage, the negligent driver’s insurance company with cover your loss. In reality, Pennsylvania courts follows a minority of states that holds that generally speaking defective workmanship is not a “covered occurrence” under an insurance policy. (There are several exceptions to this rule and thorough discussion is beyond this blog post and would probably bore you.)
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com