Best Practices for ESI Collection in Construction Litigation
October 05, 2020 —
Kelley J. Halliburton - Construction ExecutiveThe construction business has always been heavy on records and data but now more than ever much of that information is stored electronically. Gone are the days of just a trailer full of drawings and paper documents.
Construction projects now have huge amounts of electronically stored information (ESI) including contract documents; drawings in both CAD, PDF and other formats; schedule files such as Primavera; spreadsheets; photos; job cost control software files; formal correspondence; and an ever-expanding amount of email communications. Successful collection of this ESI can be critical to the success of litigation in construction cases, where often very complex facts will need to be gathered to support a claim or defense.
The best first step to a successful ESI collection is to build a solid foundation before trouble arises with prepared policies and procedures in place. Implementing and enforcing a document management plan on a project basis will make sure documents are kept in an organized fashion so that materials can be accessed quickly and easily. Document management is important for types of ESI that are not handled well by word-searches, including Primavera schedules, photos and videos.
Reprinted courtesy of
Kelley J. Halliburton, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Do You Have the Receipt? Pennsylvania Court Finds Insufficient Evidence That Defendant Sold the Product
December 23, 2024 —
Gus Sara - The Subrogation StrategistIn State Farm Fire & Cas. Co. v. Coway USA, Inc., No. 22-cv-3516, 2024 U.S. Dist. LEXIS 192849, the United States District Court for the Eastern District of Pennsylvania (District Court) considered whether the plaintiff produced sufficient evidence to establish that the defendant sold and/or marketed a product and, thus, could be held liable for an alleged defect in the product. The plaintiff, a subrogating insurance carrier, brought strict product liability and breach of warranty claims against the defendant—the installer of a bidet in its insured’s home—claiming that the defendant also marketed and sold the bidet. The sole evidence to support a finding that the defendant sold the bidet was the homeowner’s testimony that she bought the product from the installer. The court found that the insured’s testimony, without any documentation or other corroborating evidence, was insufficient to establish that the defendant sold the product. Since proof of a sale is a required element for strict product liability and breach of warranty claims, the District Court granted the defendant’s motion for summary judgment, dismissing the case.
This case involved a water loss to the Pennsylvania residence of Mikyung Kim and her husband Adrian Kim (collectively, the Kims) that was discovered in April 2021. An investigation revealed that the water loss originated from the failure of a bidet for a toilet in the second-floor bathroom. The Kims alleged that defendant, Coway USA, Inc. (Coway), sold the bidet and installed it around 2010. An employee of the plaintiff’s liability expert, a materials engineer, opined that a T-connector—a plastic valve that regulates the flow of water to and through the bidet—failed due to overtightening of the connector during the manufacturing process.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
North Carolina Learns More Lessons From Latest Storm
October 16, 2018 —
Pam Radtke Russell - Engineering News-RecordThere’s no big wall planned to protect North Carolina’s coast from storm surge. There’s no massive tunnel system proposed to keep floodwaters away from populated areas. There are no grant-funded resilience competitions to help the state plan to manage water more effectively.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMs. Russell may be contacted at
Russellp@bnpmedia.com
Partner Jonathan R. Harwood Obtained Summary Judgment in a Case Involving a Wedding Guest Injured in a Fall
December 30, 2019 —
Jonathan R. Harwood - Traub Lieberman PerspectivesOn September 30, 2019, Traub Lieberman partner Jonathan Harwood obtained summary judgment in an action involving a guest injured in a fall at a wedding. Traub Lieberman’s client owned the property where the fall occurred. Plaintiff fell while exiting a row of seats after the bridal party had recessed down the aisle. Plaintiff claimed that she tripped over the raised side of a paper runner that had been placed in the aisle at the property. Plaintiff brought an action against Traub Lieberman’s client (the owner of the building) and the florist that had provided the runner. The owner had provided the bridal party with access to the property but did not assist in the set up for the wedding or have any employees present during the ceremony. The florist had supplied the runner for the wedding. The florist commenced a third-party action against the bride, whose wedding party had actually placed the runner in the aisle. Plaintiff asserted that the runner had become bunched and crumpled during the ceremony, creating a dangerous condition. She further asserted that the owner was responsible for her injuries since the dangerous condition existed on its property and it should have an employee present to insure no dangerous conditions existed.
During the course of discovery, Mr. Harwood established that no one representing the owner was present during the wedding, had any involvement in the placement of the runner or had received any complaints about the runner. In support of the motion for summary judgment Mr. Harwood introduced pictures showing, in conjunction with deposition testimony, that there were no problems with the runner minutes before plaintiff’s fall. Mr. Harwood also argued that the alleged defect did not involve the property itself, absolving the owner of any obligation to plaintiff. In granting the motion for summary judgment, the court held that evidence and testimony showed that the owner neither created the condition nor had actual or constructive notice that any dangerous condition existed. The court also held that there the owner did not have any duty to have a representative present during the wedding since the property itself was not dangerous or defective. Finally, the court held that the condition of the runner was open and obvious and not inherently dangerous.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan R. Harwood, Traub LiebermanMr. Harwood may be contacted at
jharwood@tlsslaw.com
Boston Developer Sues Contractor Alleging Delays That Cost Millions
November 01, 2021 —
James Leggate - Engineering News-RecordA Miami developer is suing the general contractor it hired to build a 22-story mixed-use tower in Boston’s trendy Seaport District, alleging construction delays cost it $4.9 million in lost revenue.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Shutdowns? What A Covid-19-Safe Construction Site Looks Like
April 20, 2020 —
ENR Editors - Engineering News-RecordThere’s no end to published opinions about construction project shutdowns where the widely different types of jobsites are reduced to a single Dickensian nightmare crying out to be closed during this COVID-19 pandemic.
ENR Editors
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Clean Water Act Cases: Of Irrigation and Navigability
January 06, 2020 —
Anthony B. Cavender - Gravel2GavelThe federal courts have recently decided two significant Clean Water Act (CWA) cases: State of Georgia, et al. v. Wheeler, where the US District Court for the Southern District of Georgia held that the 2015 rulemaking proceeding of EPA and the U.S. Army Corps of Engineers redefining the term “Waters of the United States” in the CWA violated the Act as well as the Administrative Procedure Act; and the Ninth Circuit’s decision in Pacific Coast Federation of Fishermen’s Associations, et al. v. Glaser, where the appeals court ruled that the lower court erroneously interpreted a CWA NPDES permitting exception involving agricultural return flows.
An Absence of Navigability: State of Georgia, et al. v. Wheeler
Decided on August 21, 2019, the district court, one of the few courts to grapple with the rule’s compliance with the CWA and the Administrative Procedure Act (APA), held that the agencies’ redefinition of the terms “Interstate Waters,” “Tributaries” and “Adjacent Waters” violated the CWA by reading “navigability” out of the new definitions, or by failing to adhere to the Supreme Court’s rulings in the 2005 case of Rapanos v. United States, in particular Justice Kennedy’s concurrence regarding the application of the “significant nexus” in case-by-case adjudications as to whether a particular body of water was covered by the Act. Moreover, some provisions of the rule conflicted with the APA because they were not a logical outgrowth of the rules proposed by the agencies in 2014, and on which they solicited comments, and other determinations were not supported by a reasonable explanation. In addition, without a clear statement from Congress that it supported the rule’s effect of increasing the nature and extent of enhanced federal jurisdiction over waters subject to the CWA, the court was loathe to approve the rule. Accordingly, the rule was remanded to the agencies for additional review consistent with this decision.
This decision is of particular importance as it may well be the first case to subject this new EPA rule—the linchpin of much of EPA’s regulation under the CWA—to extended review. (Other courts have only been asked to enjoin the rule, which involves a different type of review.)
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Want to Stay Up on Your Mechanic’s Lien Deadlines? Write a Letter or Two
March 22, 2017 —
Christopher G. Hill – Construction Law Musings90 days. 150 days. 6 months. 30 days. Do these numbers sound familiar? If you read Construction Law Musings regularly, they should be. These are various deadlines relating to the recording and enforcement of mechanic’s liens in Virginia.
90 days from your last work performed (or from the last date of the last month of work in the correct circumstances) sets the outside limit on when a construction company can record a lien on a construction project. 150 days is the “look back” period for what work’s value can be included in that lien. 6 months is the statute of limitations for the filing of an enforcement suit. Finally, 30 days amount of time after your start of work within which you, as a construction professional, must notify a mechanic’s lien agent of your presence on a residential project. Of course, there are always nuances to these rules that need to be taken into account, preferably with the help of your friendly neighborhood construction attorney, before deciding how to proceed in this very picky and “form over function” area of construction law.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at