Construction Contract Basics: Attorney Fee Provisions
November 13, 2023 —
Christopher G. Hill - Construction Law MusingsI have discussed the need for
attorney fee provisions in your construction contracts in prior posts here at Construction Law Musings, but thought it merited a restatement of the reasons for the inclusion of such fee provisions (and changing of such provisions when presented) here with the second of my
construction contract basics posts.
Why would you want such a provision? The answer is that without it, or a statute specifically allowing for such fees, a Virginia court will not award your attorney fees without such a provision. Virginia, and a lot of other states, follow the so-called “American Rule” when it comes to attorney fees and costs. In short, that rule states that the parties to litigation pay their own way unless they agree otherwise. While it may seem unfair to make a successful litigant pay for the privilege of being right, that is the rule in Virginia. Throw in the fact that Virginia courts
strictly construe construction contracts and voila we have a situation where without a provision in the contract stating that one party or both will be able to collect attorney fees should that contractor or subcontractor prevail, a construction professional that gets sued (whether rightly or wrongly) will be left with a hefty attorney fees bill and no way to recoup those fees through the courts or any other method.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
No Coverage for Roof Collapse During Hurricane
January 29, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit affirmed the district court's determination that the insured's roof collapse was not covered. Exclusive Real Estate Inv., L.L.C. v. S.G.L. No. 1, Ltd., 2023 U.S. App. LEXIS 29368 (5th Cir. Nov. 3, 2023).
A building owned by Exclusive Real Estate partially collapsed during a rain-storm. The insurer, SGL, inspected the roof and determined that there was no coverage. Exclusive sued SGL for breach of contract and bad faith. SGL moved for summary judgment, which was granted by the district court. Exclusive appealed.
The poicy covered "direct physical loss to the property" caused by windstorms. Exclusions, however, precluded coverage for losses "caused by rain, snow, sleet, sand or dust unless the direct force of wind or hail damages the building causing an opening in a roof or wall and the rain, snow, sleet, sand or dust enters through this opening."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Close Enough Only Counts in Horseshoes and Hand Grenades
March 08, 2021 —
Garret Murai - California Construction Law BlogIn
State Farm General Insurance Company v. Oetiker, Inc., Case No. B302348 (December 18, 2020), a manufacturer sued in subrogation action under the Right to Repair Act almost got away. Almost.
The Oetiker Case
James and Jennifer Philson’s home was substantially completed, and a notice of completion was recorded, in 2004. In 2016, the Philsons tendered a claim to their homeowner’s insurance carrier, State Farm General Insurance Company, after their home experienced significant water damage due to a defective stainless steel ear clamp.
In 2018, after paying the Philson’s claim, State Farm filed a subrogation action against the manufacturer of the ear clamp, Oetiker, Inc. State Farm’s complaint, which included causes of action for negligence, strict products liability and breach of implied warranty, alleged that the home was “damaged by a water leak from the failure of a defective stainless steel ear claim on a water PEX fitting” and that the ear clamp was “defective when it left the control of [Oetiker].”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Wilke Fleury Attorneys Awarded Sacramento Business Journal’s Best of the Bar
September 30, 2019 —
Dan Egan, Steve Williamson & David Frenznick - Wilke FleuryWilke Fleury congratulates attorneys Dan Egan, Steve Williamson and David Frenznick on their inclusion in the Sacramento Business Journal 2019 Best of the Bar!
The Sacramento Business Journal annually honors the region’s top attorneys after a rigorous process of selection. To be awarded the Best of the Bar, attorneys are nominated by fellow attorneys and then vetted by a panel of peers.
Reprinted courtesy of Wilke Fleury attorneys
Dan Egan,
Steven J. Williamson and
David A. Frenznick
Mr. Egan may be contacted at degan@wilkefleury.com
Mr. Williamson may be contacted at swilliamson@wilkefleury.com
Mr. Frenznick may be contacted at dfrenznick@wilkefleury.com
Read the court decisionRead the full story...Reprinted courtesy of
$109-Million Renovation Begins on LA's Willowbrook/Rosa Parks Station
October 02, 2018 —
Greg Aragon - Engineering News-RecordThe Los Angeles County Metropolitan Transportation Authority (Metro), along with the Los Angeles office of Stantec, recently began work on the $109-million Willowbrook/Rosa Parks Station Improvement Project in Los Angeles.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Aragon, ENRENR may be contacted at
ENR.com@bnpmedia.com
Leveraging the 50-State Initiative, Connecticut and Maine Team Secure Full Dismissal of Coverage Claim for Catastrophic Property Loss
March 23, 2020 —
Regen O'Malley - Gordon & Rees Insurance Coverage Law BlogOn behalf of Gordon & Rees’ surplus lines insurer client, Hartford insurance coverage attorneys Dennis Brown, Joseph Blyskal, and Regen O’Malley, with the assistance of associates Kelcie Reid, Alexandria McFarlane, and Justyn Stokely, and Maine counsel Lauren Thomas, secured a full dismissal of a $15 million commercial property loss claim before the Maine Business and Consumer Court on January 23, 2020. The insured, a wood pellet manufacturer, sustained catastrophic fire loss to its plant in 2018 – just one day after its surplus lines policy expired.
Following the insurer’s declination of coverage for the loss, the wood pellet manufacturer brought suit against both its agent, claiming it had failed to timely secure property coverage, as well as the insurer, alleging that it had had failed to comply with Maine’s statutory notice requirements. The surplus lines insurer agreed to extend the prior policy several times by endorsement, but declined to do so again. Notably, the insured alleged that the agent received written notice of the non-renewal prior to the policy’s expiration 13 days before the policy’s expiration. However, the insured (as well as the agent by way of a cross-claim) asserted that the policy remained effective at the time of the loss as the insured did not receive direct notice of the decision not to renew coverage and notice to the agent was not timely. Although Maine’s Attorney General and Superintendent intervened in support of the insured’s and agent’s argument that the statute’s notice provision applied such that coverage would still be owed under the expired policy, Gordon & Rees convinced the Court otherwise.
At issue, specifically, was whether the alleged violation of the 14-day notice provision in Section 2009-A of the Surplus Lines Law (24-A M.R.S. § 2009-A), which governs the “cancellation and nonrenewal” of surplus lines policies, required coverage notwithstanding the expiration of the policy. The insured, the agent, and the State of Maine intervenors argued that “cancellation or nonrenewal” was sufficient to trigger the statute’s notice requirement, and thus Section 2009-A required the insurer to notify the insured directly of nonrenewal. In its motion to dismiss, Gordon & Rees argued on behalf of its client that Section 2009-A requires both “cancellation and nonrenewal” in order for the statute to apply. Since there was no cancellation in this case – only nonrenewal – Gordon & Rees argued that Section 2009-A is inapt and that the insurer is not obligated to provide the manufacturer with notice of nonrenewal. Alternatively, it argued that the statute is unconstitutionally vague and unenforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Regen O'Malley, Gordon & ReesMs. O'Malley may be contacted at
romalley@grsm.com
Statutory Time Limits for Construction Defects in Massachusetts
November 27, 2013 —
CDJ STAFFConstruction defect claims are governed by a section of the Massachusetts laws and allow for three years after the work was completed, unless the defect is “inherently unknowable,” according to a post by John Shaffer on the web site of his firm, Marcus, Errico, Emmer & Brooks, a New England law firm that specializes in condominium law. Those “inherently unknowable” defects fall into the six-year statute of repose.
If, for example, a roof doesn’t show “significant water leakage” until after the end of the statutory period, “the association is out of luck and the responsible parties are off the hook,” writes Mr. Shaffer. “Even if the association could prove conclusively that the roof was improperly constructed and caused significant damage, the association’s claim will be barred.”
One problem condominium associations can face is that defects in the earliest phases of building can sometimes become apparent while the developer still controls the board. “While a developer in control of a board has the same fiduciary obligation as owner-elected trustees to protect the association’s interests, it is probably safe to assume that few developers will be inclined to sue themselves.” Here, Mr. Shaffer notes that owners can join together and either “hasten the transition to owner control of the association” or “convince them to correct the identified deficiencies.”
Mr. Shaffer notes that some questions concerning the statute of repose haven’t been answered by the Massachusetts courts. He does assure readers that “developers will no doubt argue that the statute of limitations has expired on defects because the association discovered or ‘should have discovered’ their existence more than three years before the lawsuit was started.” He advises condominium associations to calculate “their filing deadlines as conservatively as possible.”
Read the court decisionRead the full story...Reprinted courtesy of
Allocating Covered and Uncovered Damages in Jury Verdict
March 01, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen a liability insurer defends an insured from a third-party claim, they oftentimes do so under a reservation of rights. A reservation of rights letter is issued to the insured that identifies certain coverage exclusions or reservations relative to the insurance policy that may impact the insurer’s duty to indemnify the insured for damages. In other words, just because the insurer is defending its insured does not mean it will be indemnifying its insured for damages asserted in the third-party claim.
Under Florida law, the party claiming insurance coverage has the initial burden to show that a settlement or judgment represents damages that fall within the coverage provisions of the insurance policy. An insured’s inability to allocate the amount of a judgment between covered and uncovered damages is therefore generally fatal to its indemnification claim. However, the burden of apportioning or allocating between covered and uncovered damages in a general jury verdict may be shifted to the insurer if the insurer did not adequately make known to the insured the availability and advisability of a special verdict.
QBE Specialty Ins. Co. v. Scrap Inc., 806 Fed.Appx. 692, *695 (11th Cir. 2020) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com