Texas Shortens Its Statute of Repose To 6 Years, With Limitations
October 02, 2023 —
Jason Daniel Feld & Roni Most - Kahana FeldEffective June 9, 2023, Texas has shortened its statute of repose from the existing 10-year statute for builders of new homes to 6-years under specific conditions. The significantly shorter statute of repose bars suits against construction contractors of detached one-and two-family homes and townhomes, filed six years after the substantial completion of such homes, where the contractor also furnished a written warranty in compliance with the statute. Notably, projects including apartments, mixed-use, and hotels are not covered by the new law. It is also noted that a grey area in the law exists as to whether condominiums will be covered by the statute. The statute of repose strictly bars the filing of any action, claim or arbitration demand regardless of when the injury was actually discovered (latent defects) and is separate and distinct from any applicable statute of limitations.
The New Texas Statute of Repose Law
Under the
Texas Civil Practice & Remedies Code § 16.009, persons who construct or repair improvements to real property cannot be sued for defective or unsafe conditions of the property or deficiencies in the construction or repair of the improvement later than 10 years after substantial completion of the improvement, except in certain narrow circumstances. This statute is known as the “statute of repose.” The statute applies not only to suits for construction defects, but also personal injury, wrongful death, contribution, and indemnity.
Reprinted courtesy of
Jason Daniel Feld, Kahana Feld and
Roni Most, Kahana Feld
Mr. Feld may be contacted at jfeld@kahanafeld.com
Mr. Most may be contacted at rmost@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Will Claims By Contractors on Big Design-Build Projects Ever End?
February 27, 2023 —
Richard Korman - Engineering News-RecordIn the annals of construction disputes, it is a blip, not a blast.
After a Flatiron Construction-Zachry Group joint venture struck out on most of its arbitrated claims against engineering firm partners on the I-85/385 design-build interchange project in Greenville, S.C., and had others dismissed in court, the contractors had one more source from which to try to cover unexpected project costs: a contractor protective professional policy. Flatiron-Zachry filed a lawsuit last October in San Antonio federal court to try to force payment from Steadfast, a subsidiary of Zurich American Insurance Co.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Be Careful with Good Faith Payments
February 24, 2020 —
Christopher G. Hill - Construction Law MusingsSometimes doing the expedient thing and what looks good at the time can come back to bite you. Just ask 3M Company.
In Faneuil, Inc. v. 3M Co., the Virginia Supreme Court considered a customer services subcontract between Faneuil and 3M relating to a toll collection contract 3M entered into with ERC. The subcontract had a “pay if paid” clause in it requiring payment to 3M from ERC before ERC was required to pay Faneuil, a written change order provision and a base monthly payment to Faneuil for the services that could be reduced in the event of less than expected toll collections. Further, the subcontract stated that if either party settled 3rd party claims, that settlement would not bind the other party to the subcontract absent consent or Court order.
Faneuil was then alleged to have been required to provide “Special Services” relating to manual identification of license plates and other information necessary for toll billing due to 3M’s alleged failure to provide adequate imaging services. Faneuil requested (without written change order) and 3M promised to pay extra for these services. When 3M was slow to pay for the special services, Faneuil did what you would expect and threatened to stop providing them. Instead of contesting the right to the work, 3m made sporadic “good faith” payments to induce continued Special Services from Faneuil. Eventually 3M’s issues caused ERC to stop payments and thus 3M stopped paying Faneuil. 3M then settled the payment claims with ERC and still failed to pay Faneuil.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Ohio Does Not Permit Retroactive Application of Statute of Repose
October 08, 2014 —
Beverley BevenFlorez-CDJ STAFFDon Gregory of Kegler Brown Hill + Ritter (published in Association of Corporate Counsel) reported that while Ohio currently has a statute of repose, the Supreme Court of Ohio recently ruled in a case where the development was built in 1990 but the defects weren’t discovered until 2003 that the statute of repose did not apply since “Ohio had no enforceable statute of repose in 2003 (it had been declared unconstitutional).”
Gregory stated that “[t]his case means that some construction defect claims, by condo associations or others, may survive even though construction was completed more than a decade ago.”
Read the court decisionRead the full story...Reprinted courtesy of
Contractor’s Claim for Interest on Subcontractor’s Defective Work Claim Gains Mixed Results
April 27, 2020 —
John J. Gazzola, Associate, Pepper Hamilton LLP - ConsensusDocsThis case concerns calculation of a damages award to a general contractor, Skanska USA Building, Inc., on its claim for breach of contract against its masonry subcontractor, J.D. Long Masonry, Inc., arising from Long’s faulty construction of a masonry façade at a medical research facility in Baltimore. When the façade collapsed and Long failed to repair it, Skanska hired a replacement subcontractor, C.A. Lindman, to remediate Long’s defective work and filed suit against Long to recover the resulting damages. After the court granted Skanska’s motion for summary judgment as to liability, Skanska moved for summary judgment on the issue of damages, relying on the indemnification provision of the subcontract to seek compensatory damages, pre- and post-judgment interest, and litigation fees. In the subcontract, Long agreed to indemnify and hold Skanska harmless from all claims, losses, costs and expenses, including attorneys’ fees, arising before or after completion of Long’s work, caused by, arising out of, resulting from, or occurring in connection with Long’s performance of the work or breach of the subcontract.
The court first applied the terms of this provision to award Skanska compensatory damages, holding that Skanska was, as a matter of law, entitled to recover the amount of the Lindman subcontract and general conditions incurred to supervise remediation of Long’s work. The court, however, denied Skanska’s claim for pre-judgment interest on the entirety of these damages. Skanska asserted that it was entitled to pre-judgment interest on the full award, calculated from the date on which it first paid Lindman. The court disagreed, explaining that, under Maryland law, a claimant is entitled to an award of pre-judgment interest as of right only when the amount due is certain, definite and liquidated by a specific date prior to judgment. The court reasoned that, because much of the Lindman subcontract value was composed of later-executed change orders, an award of pre-judgment interest could not be uniformly calculated back to the date of Skanska’s first payment to Lindman. And moreover, because Skanska continued to withhold sums due to Lindman pending resolution of certain issues, awarding Skanska pre-judgment interest on amounts it had not yet paid would result in a “windfall” to Skanska because there was no “use of income” loss to be compensated.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Gazzola, Pepper Hamilton LLPMr. Gazzola may be contacted at
gazzolaj@pepperlaw.com
Microwave Transmission of Space-Based Solar Power: The Focus of New Attention
July 24, 2023 —
Robert A. James & William E. Fork - Gravel2Gavel Construction & Real Estate Law BlogScientists have long proposed that solar electricity generation in space could be an integral component of the world’s carbon-free future. In the 1970s, a U.S. Navy experiment showed that it might be possible to capture solar power and wirelessly transmit it from outer space using microwave beams. Progress stalled after that early test—the models used were at such a massive scale that creating a real-world system felt like science fiction. Recently, amid growing concerns about power grid security and intensifying legislation around carbon emissions, renewed attention focused on a smaller, more lithe microwave transmission system. This time around, the military is not the only interested party. Scientists around the world are conducting similar research. As investors and governments stand at the edge of a fresh green power opportunity, we look at microwave power transmission and some of the projects in this emerging field.
The basic premise of space-based solar power technology is simple enough: photovoltaic panels on a satellite in space convert the sun’s energy to electromagnetic waves at microwave frequencies. The satellite then beams the microwave energy to a receiver on Earth that transforms it into direct current. Until recently, this technique had been performed on the ground over short distances, but nobody had attempted to launch a solar panel into space. The status quo has shifted over the past few years as researchers have begun to send prototypes into orbit. In early 2023, CalTech was the first to report a breakthrough. Its model successfully beamed power from space back to their receiver atop a building in California.
Reprinted courtesy of
Robert A. James, Pillsbury and
William E. Fork, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Mr. Fork may be contacted at william.fork@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Fatal Crane Collapse in Seattle Prompts Questions About Disassembly Procedures
July 09, 2019 —
Jeff Rubenstone - Engineering News-RecordA tower crane being dismantled collapsed Saturday, April 27 in Seattle, killing four people, including two ironworkers on the crane and two bystanders on the street below. The jobsite, located in a Google office development in Seattle's bustling South Lake Union neighborhood, is adjacent to a busy intersection where traffic had not been blocked off during the crane’s disassembly. It is the first fatal crane accident in the Puget Sound region since a crane collapse in Bellevue, Wash., in 2006 that killed one person.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Rubenstone, ENRMr. Rubenstone may be contacted at
rubenstonej@enr.com
McCarthy Workers Test Fall-Protection Harnesses Designed to Better Fit Women
November 09, 2020 —
Corinne Grinapol - Engineering News-RecordAt project sites in Dallas, Houston and Atlanta, 27 McCarthy Building Co. women employees are testing a harness better suited to fit a diversity of body types than the more ubiquitous harnesses generally available at construction sites.
Reprinted courtesy of
Corinne Grinapol, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of