New York Appellate Court Expands Policyholders’ Ability to Plead and Seek Consequential Damages
February 27, 2019 —
Michael S. Levine & Joshua S. Paster - Hunton Andrews KurthIn a huge win for policyholders, a New York appellate court, in D.K. Property, Inc. v National Union Fire Insurance Company of Pittsburgh, Pa., held that an insured need not provide a detailed factual description or explanation for why consequential damages are recoverable at the pleading stage. Rather, an insured’s complaint must only (i) specify the types of consequential damages claimed; and (ii) allege that those damages reasonably were contemplated by the parties prior to contracting.
Here, D.K. Property’s building was damaged as a result of construction on an adjoining building, and it timely filed a claim with National Union under a policy that covers “direct physical loss or damage to” the building. National Union neither paid the claim nor disclaimed coverage. Instead, according to D.K. Property, National Union made unreasonable and increasingly burdensome information demands over a three-year period, which it alleges was a “tactic” to make pursuing the claim so expensive that D.K. Property would abandon the claim. As a result of the delay, D.K. Property alleges the structural damage to its building has worsened.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joshua S. Paster, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Paster may be contacted at jpaster@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Toddler Crashes through Window, Falls to his Death
January 24, 2014 —
Beverley BevenFlorez-CDJ STAFFTwo-year old Alijah Glenn fell 17 stories to his death after crashing through “a floor-to-ceiling window” at the Crystal Tower apartments in East Cleveland, Ohio, on January 13th, according to The Plain Dealer. Solandra Wallace, East Cleveland’s building and housing manager, told The Plain Dealer that “the city inspects the building whenever a complaint is filed and does not have regular inspections.” The apartment complex “was built in 1966 and would have to adhere to that era's building code standards,” according to the article.
The Plain Dealer reports that three complaints have been filed at the Crystal Tower since 2010. A resident complained in 2012 that “her apartment was falling apart, causing water damage and emitting a foul odor,” however, by the time an inspector arrived the ceiling was being fixed. In 2011, an “unspecified roof leak” turned out to be “condensation from a hot pipe.” An elevator was reported inoperable in 2010, however the claim was deemed “invalid” since the elevator worked when inspectors arrived.
The Cuyahoga County Medical Examiner ruled Glenn’s death accidental.
Read the court decisionRead the full story...Reprinted courtesy of
Unqualified Threat to Picket a Neutral is Unfair Labor Practice
January 08, 2019 —
Wally Zimolong - Supplemental ConditionsOn December 27, 2018, the National Labor Relations Board enforced a decades old policy that a union’s unqualified threat to picket a neutral employer at a “common situs” a/k/a a construction site is a violation of the National Labor Relations Act.
Background
The case involved area standards picketing by the IBEW of a project owned by the Las Vegas Convention and Visitors Authority (LVCVA). The IBEW sent a letter to various affiliated unions who were working on the project advising them of its intent to engage in area standards picketing at the project directed to the merit shop electrical subcontractor performing work there. The IBEW also sent a copy of the letter to the LVCVA.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Sinking Buildings on the Rise?
July 01, 2019 —
Jason M. Adams - Gibbs GidenBy now everyone in the construction and insurance industries is familiar with the 58-story Millennium Tower building in San Francisco that has sunk 17 inches and tilted another 14 inches to the northwest. Another recent New York lawsuit alleges that a 58-story luxury Manhattan condo high-rise is also sinking and causing significant damage. With construction booming in the Southeast and other areas with questionable soils, sinking building cases may be on the rise. Given this reality, the issue of subsidence should be of paramount importance to every construction and insurance professional when insuring a project.
Most insurance carriers will include a subsidence and/or other earth movement exclusion on a commercial general liability ("CGL") quote for insurance as a matter of course. Construction professionals (owners/developers, general contractors, and subcontractors) or their brokers may be under the mistaken impression that they have no choice but to accept these subsidence exclusions as part of a standard construction policy. This is not the case. To the contrary, most insurance carriers are willing to remove subsidence exclusions if the underwriters are provided with acceptable geotechnical/soils reports when considering the project.
The insured construction professional often pushes back on the insurance carrier's request for soils reports because the insured sees the request as an unnecessary hassle, expense or unwelcome interference in the job. However, the carrier's soils review is designed to benefit everyone. If potential soils issues are discovered during the underwriting process they can be addressed at the outset of the project rather than after the project is built, which will typically cost substantially more to remedy. Moreover, a thorough analysis of the condition of the soils at the outset of the project allows the risk management team to recognize any potential issues and ensure that the proper coverage is obtained in order to provide protection down the road. Even if the insurance carrier charges more money to sign off on questionable soils after a review of the reports, the slight increase in premium is likely a worthwhile investment in the event of a subsidence loss.
The lesson is that the insured should not blindly accept a subsidence exclusion and should negotiate its removal. The insured should provide its broker and the insurance carrier the information they need in order to make a fully-informed decision as it pertains to the soils. Once the insurance carrier has had the opportunity to review and sign off on the condition of the soil, the carrier should feel comfortable enough to remove any subsidence exclusions or other similar earth movement limitations.
Subsidence is a relatively straightforward issue to deal with as long as the project team’s lawyers, brokers, risk managers and insurance company underwriters are working together toward the common goal of properly evaluating the risk and adequately insuring the project. This simple cooperative process between the entire risk management team could mean the difference between being covered or not covered in the event of a loss related to earth movement.
Jason M. Adams, Esq. is Senior Counsel at Gibbs Giden representing construction professionals (owners/developers, contractors, architects, etc.) in the areas of Construction Law, Insurance Law and Risk Management, Common Interest Community Law (HOA) and Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms. Mr. Adams can be reached at jadams@gibbsgiden.com.
The content contained herein is published online for informational purposes only, may not reflect the most current legal developments, verdicts or settlements, and does not constitute legal advice. Do not act on the information contained herein without seeking the advice of licensed counsel. The transmission of information by email, or any transmission or exchange of information over the Internet, or by any of the included links is not intended to create and does not constitute an attorney-client relationship. This publication may not be reproduced or used in whole or in part without written consent of the author. Copyright 2019 ©
Read the court decisionRead the full story...Reprinted courtesy of
California Contractor Tests the Bounds of Job Order Contracting
March 01, 2021 —
Garret Murai - California Construction Law BlogMost contractors have heard of design-bid-build, design-build, construction manager at risk, and even public private partnerships, various project delivery methods, which, at their heart, focus on balancing the interests of the various parties involved in a construction project, from owners, to design professionals, to contractors. There’s one project delivery method you may not be as familiar with though: Job Order Contracting, also known by its acronym JOC.
JOC contracting is a project delivery method used on public works projects and has been authorized to be used by California K-12 school districts, community colleges, CalState universities, and the Judicial Council of California, which, among other things, is responsible for the construction of California state courts. It is intended to be used on smaller, independent, long-horizon project typically involving maintenance, repair and refurbishment. Think periodic maintenance of facilities.
JOC contracts are administered by public entities issuing a request for proposals. The public entity then awards a JOC contract to the lowest responsible bidder. The lowest responsible bidder then enters into a JOC contract with the public entity. JOC contracts typically have a duration of one (1) year and are limited to a total construction value of $4.9 million increased annually based on the Consumer Price Index. When entering into a JOC contract, a JOC contractor agrees to perform work at prices set forth in a Construction Task Catalog also known as a unit price book which includes current local labor, material and equipment costs. Unit prices are then adjusted by a “bid adjustment factor” based on the JOC contractor’s bid. When work is needed, the public entity will then issue a job order to the JOC contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Additional Insured Prevails on Summary Judgment For Duty to Defend, Indemnify
October 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiOn summary judgment, the insured general contractor prevailed not only on the duty to defend, but also the duty to indemnify. Wausau Underwriters Ins. Co. v. Old Republic Gen. Ins. Co., 2015 U.S. Dist. LEXIS 103954 (S.D. N. Y. Aug. 7, 2015).
170 Broadway entered into a construction management agreement with McGowan Builders Inc. to serve as its construction manager for a hotel being built in Manhattan. Under the agreement, McGowan obtained a general liability policy from Old Republic naming 170 Broadway as an additional insured. 170 Broadway also secured its own policy from Wausau.
Adam Burawski, an employee of a security company, came to the 170 Broadway site to meet with McGowan about provided security services for the project. Before the meeting, Burawski tripped and fell, sustaining a serious injury.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Google’s Floating Mystery Boxes Solved?
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFGarret Murai, on his California Construction Law blog, reported how “a four story structure made up of shipping containers” had been mysteriously erected on a barge in the middle of San Francisco Bay. Later, it was determined that Google was behind the strange structure, though they were keeping silent as to what the building-on-the-barge would be used for.
Construction stopped after the San Francisco Bay Conservation and Development Commission determined that the mysterious barge required a permit—which would require Google to file “publicly available documents.” Google chose to move the barge to Stockton, California rather than obtain a permit.
Google finally released a comment stating that they are “exploring using the barge as an interactive space where people can learn about new technology.” However, Murai believes that this statement may be a “distraction device” and the true use of the barge has yet to be revealed.
Read the court decisionRead the full story...Reprinted courtesy of
Record Keeping—the Devil’s in the Details
July 30, 2015 —
Craig Martin – Construction Contract AdvisorAnother court has found that poor record keeping will prevent recovery on a claim. The court in Weatherproofing Tech., Inc. v. Alacran Contracting, LLC found that a contractor’s documents were a mess and that no reasonable jury could base a verdict on the contractor’s records.
The underlying project involved the construction of an army training facility. The total project cost approximated $13 million. Alacran, the general contractor, subcontracted about $3 million of the work to Weatherproofing Tech. Alacran paid Weatherproofing $700,000 for its work, even though Weatherproofing submitted invoices of more than $2 million. Alacran justified its refusal to pay Weatherproofing on the grounds that the parties had agreed to split the profit and loss on the project and the project was out of money. Not surprisingly, Weatherproofing sued Alacran for the amount owed.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com