“Details Matter” is the Foundation in a Texas Construction Defect Suit
March 01, 2012 —
CDJ STAFFThe Court of Appeals of Texas has ruled in the case of Barzoukas v. Foundation Design. Mr. Barzoukas contracted with Heights Development to build a house. He subsequently sued Heights Developments and “numerous other defendants who participated in the construction of his house.” Barzoukas eventually settled with all but two defendants, one who went bankrupt and Foundation Design, the defendant in this case. In the earlier phase, Barzoukas made claims of “negligence, negligent misrepresentation, fraud, fraudulent inducement, conspiracy, and exemplary damages in connection with the foundation.”
Foundation Design had been hired to install 15-foot piers to support the foundation. The engineer of record, Larry Smith, sent a letter to Heights Development noting that they had encountered hard clay stone when drilling. Smith changed the specifications to 12-foot piers. Initially, the City of Houston called a halt to work on the home when an inspector concluded that the piers were too shallow. Heights Development later convinced the city to allow work to continue. Subsequently, experts concluded that the piers were too shallow.
Foundation Design filed a motion for summary judgment. The trial court granted this, “without specifying the basis for its ruling.” Barzoukas contends the court was in error. Foundation Design contends that “Barzoukas failed to proffer competent evidence establishing that their conduct proximately caused damages.” Further, they did not feel that Smith’s letter gave “rise to viable claims for fraud and fraudulent inducement.”
One problem the court had was a lack of evidence. The court noted that “the purported subcontract is entirely missing” in the pleadings. The court has no contract between Bazourkas and Heights Development, nor one between Heights Development and either Foundation Design or Smith. The court underscored the importance of this, writing, “details matter.” They found that “the details are largely missing here.” Without the contract, the court found it impossible to determine if “Smith or an entity related to him agreed to indemnify Heights Development for damages arising from Smith’s negligent performance.”
As the material facts are in dispute, the appeals court found that there were no grounds for a summary judgment in the case. “Pointing to the existence of a contract between Heights Development and Barzoukas, or to the existence of a subcontract, is the beginning of the analysis ? not the end.”
Foundation Design and Smith also claimed that Barzoukas’s expert did not proffer competent evidence and that the expert’s opinions were conclusory. The trial court did not rule on these claims and the appeals court has rejected them.
Finally, Barzoukas made a claim that the trial court should not have rejected his argument of fraud and fraudulent inducement. Here, however, the appeals court upheld the decision of the lower court. “Barzoukas did not present evidence supporting an inference that Smith or Foundation Design made a purposeful misrepresentation.
The court remanded the case to the trial court for reconsideration. One member of the panel, Judge Charles Seymore, upheld the entire decision of the trial court. He dissented with the majority, finding that the economic loss rule foreclosed the claim of negligence.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Third-Party Can Bring Common Law Bad Faith Claim
July 01, 2019 —
David Adelstein - Florida Construction Legal UpdatesA third-party claimant may bring a common law bad faith claim against a defendant’s liability insurer. Mccullough v. Royal Caribbean Cruises, 2019 WL 2076192, *2 (S.D.Fla. 2019). “A bad faith claim may be brought by a third party absent an assignment from the [defendant] insured.” Id. This can only be done in the third-party bad faith context with the argument that the insurer’s “bad faith” conduct resulted in a judgment against the defendant-insured in excess of the policy limits. However, in any third-party bad faith claim (and, really, bad faith claim in general), coverage must first be determined under the policy.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Is Your Contract “Mission Essential?” Recovering Costs for Performing During a Force Majeure Event Under Federal Regulations
May 10, 2022 —
Joneis M. Phan & Sarah K. Bloom - ConsensusDocsFederal contractors have faced unprecedented challenges performing during the COVID-19 pandemic. Additional costs have included delays and inefficiencies, site closures, quarantines, unavailability of supplies and materials, and full shutdowns of subcontractor operations. For contractors performing under fixed price contracts, the cost impact of COVID-19 was likely severe.
The Federal Acquisition Regulation (“FAR”) recognizes “epidemics” as a force majeure event that may excuse non-performance. Many federal contracts include some version of the Default clause, which prevents the government from terminating a contractor for default due to impacts of force majeure events that are beyond a contractor’s control, such as an epidemic. See, e.g., FAR 52.249-10. See also Pernix Serka Joint Venture v. Dep’t of State, CBCA No. 5683 (Apr. 20. 2020). The Default clause, however, operates as a shield from liability, not a sword authorizing recovery. Contractors are now left wondering whether any avenue exists to recover additional costs incurred after performing in the face of the COVID-19 pandemic.
In response to a likely influx of claims and requests for equitable adjustment due to COVID-19 impacts, the federal government largely took the position that contractors were entitled to extensions of time, but not to additional costs. This article explores the avenues that may be available for contractors to recover costs for performing during a force majeure event that would otherwise be non-compensable.
Reprinted courtesy of
Joneis M. Phan, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs and
Sarah K. Bloom, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs).
Mr. Phan may be contacted at jphan@watttieder.com
Ms. Bloom may be contacted at sbloom@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Nevada HOA Criminal Investigation Moving Slowly
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFSix years have passed since the FBI started investigating “allegations of the sweeping scheme to take over valley homeowners associations” in Nevada, according to Jeff German writing for the Las Vegas Review-Journal, however, “the public still doesn’t have the full story of how the scheme unfolded.” Defendants who plead guilty are still awaiting sentencing and no trial has been set for “former construction company boss Leon Benzer, the accused mastermind of the scheme” despite that he and ten others have already been indicted. The trial had been set for March, however, defense lawyers stated “they were overwhelmed by the massive amount of evidence and won’t be prepared for trial until well into 2015.”
Benzer, Nancy Quon (late construction defect attorney), and others allegedly “funneled more than $8 million through secret bank accounts to land the lucrative legal and construction defect contracts from the homeowners associations,” according to the Las Vegas Review-Journal. Quon committed suicide in 2012, and therefore was never charged in the case.
Read the court decisionRead the full story...Reprinted courtesy of
California Contractors: Amended Section 7141.5 Provides Important License Renewal Safety Net
July 25, 2021 —
Amy L. Pierce, Mark A. Oertel, John Lubitz & Adam B. Wiens - Lewis BrisboisUnder California’s Contractors State License Law, Cal. Bus. & Prof. Code §§ 7000 et seq., contractors’ licenses expire two years from the last day of the month in which the license was issued or two years from the date on which the renewed license last expired. The Contractors State License Board (CSLB) sends licensees a renewal application 60 to 90 days in advance of the date the license is set to expire. Even with various controls in place, mistakes happen and a renewal application filing deadline can be missed.
During the August 5-6, 2019 Executive, Licensing, and Legislative Committee Meetings, the CSLB discussed proposed amendments to Section 7141.5 to reduce both the burden on it to review applications for retroactive renewal of a license that had not been timely submitted and to provide contractors with some relief from the high burden to establish “the failure to renew was due to circumstances beyond the control of the licensee.” Not long after, the CSLB’s Board of Directors gave staff approval to seek an author for the bill and, on September 29, 2020, Governor Newsom signed Senate Bill 1474 into law, which includes the CSLB’s proposed amendments to Section 7141.5, effective January 1, 2021.
Reprinted courtesy of
Amy L. Pierce, Lewis Brisbois,
Mark A. Oertel, Lewis Brisbois,
John Lubitz, Lewis Brisbois and
Adam B. Wiens, Lewis Brisbois
Ms. Pierce may be contacted at Amy.Pierce@lewisbrisbois.com
Mr. Oertel may be contacted at Mark.Oertel@lewisbrisbois.com
Mr. Lubitz may be contacted at John.Lubitz@lewisbrisbois.com
Mr. Wiens may be contacted at Adam.Wiens@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
General Contractors Must Plan to Limit Liability for Subcontractor Injury
May 18, 2011 —
Douglas Reiser in the Builders Counsel BlogIt takes more than a hard hat, but safety checks, a good policy and a smart contract might save you some problems.If you are a general contractor, you will want to pay close attention to this article. A new Washington appellate decision showcases a general contractor’s liability to subcontractors who are injured on the job, when security barriers fail. But can a general limit this liability? Will its contract help?
In Wrought Corporation, Inc., Appellant V. Mario Interiano (quick note: this opinion is unpublished, but we are here to talk about an issue that was not determined on appeal – WISHA compliance), a subcontractor was injured when a security barrier failed and he fell into an elevator shaft.
A jury awarded a $1.56 million verdict against the general contractor, and the court of appeals affirmed on the basis that the general contractor has a non-delegable duty to ensure compliance with the Washington Industrial Safety and Health Act of 1973, codified under RCW 49.17 (WISHA).
Read the full story… Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Vermont Supreme Court Finds COVID-19 May Damage Property
November 07, 2022 —
Michael S. Levine & Lorelie S. Masters - Hunton Insurance Recovery BlogAs reported on this
blog, policyholders have long been of the view that the presence of substances like COVID-19 and its causative virus SARS-CoV-2, which render property dangerous or unfit for normal business operations, should be sufficient to trigger coverage under commercial all-risk insurance, as has been the case for more than 60 years.
However, many courts, federal courts in particular, despite decades of pro-policyholder precedent, have embraced the view that “viruses harm people, not [property].” Thirty-one months after the start of the pandemic, the first state high court has gone in a different direction, according greater weight to pro-policyholder precedent.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Lorelie S. Masters, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Masters may be contacted at lmasters@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
New York’s 2022 Comprehensive Insurance Disclosure Act: Significant Amendments to the C.P.L.R.
January 17, 2022 —
Ellen H. Greiper & Kristen Carroll - Lewis BrisboisNew York, N.Y. (January 4, 2022) - On December 31, 2021, New York State Governor Hochul signed into law the Comprehensive Insurance Disclosure Act.
The alleged justification for the act was to reduce the use of “delaying tactics” by compelling disclosure of the complete primary, excess, and umbrella policies implicated by the claim.
These amendments will be unduly onerous on both carriers and defense counsel—for a multitude of reasons. It imposes an obligation on the insurer to immediately identify excess policies, eroding policies, and other information or contracts that affect the available coverage.
Reprinted courtesy of
Ellen H. Greiper, Lewis Brisbois and
Kristen Carroll, Lewis Brisbois
Ms. Greiper may be contacted at Ellen.Greiper@lewisbrisbois.com
Ms. Carroll may be contacted at Kristen.Carroll@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of