The Indemnification Limitation in Section 725.06 does not apply to Utility Horizontal-Type Projects
February 07, 2018 —
David Adelstein - Florida Construction Legal UpdatesOne of the most important provisions in construction contracts is the indemnification provision. Appreciating contractual indemnification obligations are critical and certainly should not be overlooked. Ever!
Florida Statute s. 725.06 (written about here and here) contains a limitation on contractual indemnification provisions for personal injury or property damage in construction contracts. There should always be an indemnification provision in a construction contract that addresses property damage or personal injury. Always!
Section 725.06 pertains to agreements in connection with “any construction, alteration, repair, or demolition of a building, structure, appurtenance, or appliance, including moving and excavating associated therewith…” If the contract requires the indemnitor (party giving the indemnification) to indemnify the indemnitee (party receiving the indemnification) for the indemnitee’s own negligence, the indemnification provision is unenforceable unless it contains a “monetary limitation on the extent of the indemnification that bears a reasonable commercial relationship to the contract and is part of the project specifications or bid documents, if any.” It is important to read the statute when preparing and dealing with a contractual indemnification provision.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Contract Change #9: Owner’s Right to Carry Out the Work (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn prior versions of the General Conditions, if a contractor defaulted and the Owner (after giving notice) opted to cure by carrying out the work itself, an appropriate Change Order would be issued. However,
a Change Order is a contract that requires an agreement by both the Owner and Contractor, and, obviously, Contractors were reluctant to agree that they were in default and responsible for a deductive change order.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
Construction and Contract Issues Blamed for Problems at Anchorage Port
August 27, 2013 —
CDJ STAFFA third-party audit of the construction at the Port of Anchorage has found fault with the design provided by the engineers. In response, PND, the engineering firm involved, has claimed that it was not their design, but faulty construction of it that lead to an interruption in the construction project.
Separately, the Office of the Inspector General has called into question how MARAD, the agency which oversaw the port construction, handled the planning and contracts for the project.
Control of the project has been taken over by the Municipality of Anchorage, and they have called into question PND’s open cell sheet pile design and PND’s design of the dock infrastructure. Simpson, Gumpertz and Heger reviewed the design, comparing it to a design provided by CH2M Hill, and found that the PND design was inadequate. A contract was subsequently awarded to CH2M Hill.
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Supreme Court Tackles "Other Insurance" Issues
February 25, 2014 —
Tred Eyerly – Insurance Law HawaiiResponding to four certified questions from the Ninth Circuit, the Hawaii Supreme Court addressed various issues raised by competing "other insurance" provisions in two CGL policies. Nautilus Ins. Co. v. Lexington Ins. Co., 2014 Haw. LEXIS 59 (Haw. Feb. 13, 2014).
Coverage for a development on Maui was at issue. The developer, VP & PK (ML) LLC, was insured by Lexington. The other insurance provision in Lexington's policy provided it was excess over "any other primary insurance available to you covering liability for damages arising out of the premises . . . for which you have been added as an additional insured."
Kila Kila Construction was one of VP & PK's subcontractors. Kika Kila was not an additional insured under Lexington's policy. Kila Kila had its own CGL policy with Nautilus. The Nautilus other insurance clause stated the insurance was excess over "any other primary insurance available to you covering liability arising out of the premises or operations for which you ahve been added as an additional insured." An endorsement added VP & PK as an additional insured, but only for liability arising out of Kila Kila's negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Establishes a Registration Requirement for Contractors and Subcontractors Performing Public Works and Covered Private Projects
January 17, 2023 —
Christopher B. Kinzel, K. Greer Kuras, Aaron C. Schlesinger - Peckar & Abramson, P.C.By December 30, 2023, contractors and subcontractors bidding on public contracts and performing work on covered private projects in New York must register with the NYS Department of Labor, Bureau of Public Works, pursuant to the newly enacted Labor Law Section 220-i. The DOL has until June 28, 2023 to establish regulations to carry out the new law. There will be an online system where registrations and disclosures are publicly available.
The stated purpose of the law is to help enforce New York’s prevailing wage and other worker protection laws. The DOL will create an online system through which contractors and subcontractors will have to answer questions and submit documents about:
- the business entity and its owners and officers
- unemployment and workers’ compensation insurance
- any outstanding wage assessments
- debarment under New York or federal law, or any other state’s laws
- final determinations of a violation of any labor laws, employment tax laws, or workplace safety standards (including OSHA)
- association or signatory to an apprenticeship program
If the DOL approves the submission, the contractor will receive a registration certificate that remains valid for two years.
Reprinted courtesy of
Christopher B. Kinzel, Peckar & Abramson, P.C.,
K. Greer Kuras, Peckar & Abramson, P.C. and
Aaron C. Schlesinger, Peckar & Abramson, P.C.
Mr. Kinzel may be contacted at ckinzel@pecklaw.com
Ms. Kuras may be contacted at gkuras@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Packard Condominiums Settled with Kosene & Kosene Residential
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFResidents of the Packard Condominiums in Indianapolis, Indiana “have settled a two-year-old lawsuit with developer Kosene & Kosene Residential,” according to the Indianapolis Business Journal. The Homeowners association stated that “the agreement would lead to repayment of a construction loan and avoidance of a special assessment on residents.”
The association claimed to have spent “$3 million on ‘renovation and remediation’ of subpar construction of the condo building,” reported the Indianapolis Business Journal.
The article also declared that at least 25 subcontractors participated in the mediation.
Read the court decisionRead the full story...Reprinted courtesy of
ASCE Statement on Calls to Suspend the Federal Gas Tax
June 27, 2022 —
Tom Smith, Executive Director, American Society of Civil Engineers (ASCE)WASHINGTON, D.C. –
ASCE strongly opposes the recent announcement from the Biden Administration to suspend the current 18.4 cents-per-gallon federal gasoline tax for three months. Even at the same modest figure of 18 cents per gallon for over 25 years since 1993, the motor fuel tax has represented a reliable federal revenue source for communities to fix and modernize their network of roads, bridges, and transit systems.
Suspending the gas tax would result in the loss of billions in revenue from the Highway Trust Fund (HTF), significantly diminishing much of the progress made in the Bipartisan Infrastructure Law at a time when Americans expect improvements to the nation's roads, bridges, and transit systems. Replacing this lost revenue with funds from other sources is not a viable long-term solution and sets a damaging precedent. Encouraging states to follow suit will compound this bad idea and further exacerbate our nation's infrastructure funding challenges. Our transportation system, including roadways, bridge spans, and transit networks, can't rely on novel, unpredictable funding.
Further, there is little guarantee that motorists will see any real relief at the pump. Gas holidays aren't price controls; the manager at the gas station still gets to set their price. Oil producers have benefited significantly in the past from previous state-level gas tax holidays. There is no mechanism to ensure that these "savings" are passed on to consumers, but there is a virtual guarantee of disrupting transportation dollars and the HTF. While it sounds like an enticing solution when pocketbooks are strained, Congress knows that a variety of factors, including plain supply and demand, affect the prices that people see at fuel stations.
Now is the time to build on the momentum of the Bipartisan Infrastructure Law which, for the first time in decades, takes significant steps to revitalize our nation's aging infrastructure, improve public safety, strengthen our economy, and deliver well-paying jobs.
Read the court decisionRead the full story...Reprinted courtesy of
Impasse Over Corruption Charges Costs SNC $3.7 Billion, CEO Says
January 08, 2019 —
Frederic Tomesco - BloombergCanada’s failure to reach a negotiated settlement with SNC-Lavalin Group Inc. over past corruption charges has probably cost the company more than C$5 billion ($3.7 billion) in lost revenue and continues to damage its reputation internationally, Chief Executive Officer Neil Bruce said.
Read the court decisionRead the full story...Reprinted courtesy of
Frederic Tomesco, Bloomberg