Texas Court of Appeals Conditionally Grant Petition for Writ of Mandamus to Anderson
April 25, 2011 —
Beverley BevenFlorez CDJ STAFFThe Texas Court of Appeals conditionally grant mandamus relief to Anderson Construction Company and Ronnie Anderson (collectively “Anderson”)… from the trial court in a construction defect lawsuit filed by Brent L. Mainwaring and Tatayana Mainwaring. See Tex. Prop. Code Ann. 27.001-.007 (West 2000 & Supp. 2010). Relators contend the trial court abused its discretion by compelling discovery while the case was abated by operation of law.
The Court of Appeals opinion describes what led up to the proceedings: “The Mainwarings’ original petition identified certain defects in their Anderson-constructed home. Those defects concerned the roof trusses and framing, air conditioning, mortar and masonry, exterior doors and windows, and weep holes. With respect to the five areas of defects identified in their original petition, the Mainwarings gave Anderson the statutorily required notice on January 13, 2010. After implementing agreed extensions, Anderson made an offer of settlement for the defects the Mainwarings identified in their notice. Almost eight months later, the Mainwarings filed an amended petition adding defects they had not included in their original petition and notice. The additional defects the Mainwarings included in their amended petition had not been addressed by Anderson’s offer of settlement.”
Following these events, Anderson claimed the Mainwarings did not respond in writing to their settlement offer. “Anderson filed a verified plea in abatement on December 2, 2010. In the trial court, Anderson claimed that the Mainwarings failed to respond in writing to Anderson’s settlement offer, as required by Section 27.004(b) of the RCLA. See Tex. Prop. Code Ann. 27.004(b)(1). The Mainwarings moved to compel discovery responses from Anderson. The Mainwarings alleged that they rejected Anderson’s settlement offer, and that if their response was insufficient, they contend that Anderson’s offer was rejected by operation of law on the twenty-fifth day after the Mainwarings received it. See Tex. Prop. Code Ann. 27.004(i). The Mainwarings’ motion to compel was not supported by affidavit. See Tex. Prop. Code Ann. 27.004(d)(2). On January 13, 2011, Anderson filed a verified supplemental plea in abatement. Anderson alleged that the Mainwarings failed to provide written notice concerning the newly alleged defects and complained the Mainwarings were attempting to circumvent the inspection and resolution procedure of the RCLA. Over Anderson’s objection that the lawsuit had been abated, the trial court granted the Mainwarings’ motion to compel discovery.”
After listening to both sides, the Court of Appeals offered this reasoning for their opinion: “The parties do not dispute that Anderson inspected the property before the Mainwarings alleged the existence of additional defects in their amended pleading, nor do the Mainwarings claim that Anderson has been given an opportunity to inspect the additional defects the Mainwarings identified in their amended pleadings. We conclude the trial court did not have the discretion to deny or lift the abatement until the Mainwarings established their compliance with the statute. In other words, the Mainwarings are required to provide Anderson a reasonable opportunity to inspect the additional defects identified by their amended pleading, which will allow Anderson the opportunity to cure or settle with respect to the newly identified defects.”
The Court of Appeals spoke directly on the issue of mandamus relief: “The Mainwarings contend that mandamus relief is not available because the trial court’s ruling does not prevent Anderson from making settlement offers during the discovery process. ‘An appellate remedy is “adequate” when any benefits to mandamus review are outweighed by the detriments.’ In re Prudential Ins. Co. of Am., 148 S.W.3d 124, 136 (Tex. 2004). The failure to abate a case is typically not subject to mandamus. See In re Allstate Cnty. Mut. Ins. Co., 85 S.W.3d 193, 196 (Tex. 2002) (citing Abor v. Black, 695 S.W.2d 564, 567 (Tex. 1985)). In this case, however, the case was abated by operation of law. By ignoring the statutory abatement, the trial court interfered with the statutory procedure for developing and resolving construction defect claims. See In re Kimball Hill Homes Tex., Inc., 969 S.W.2d 522, 525 (Tex. App. Houston [14th Dist.] 1998, orig. proceeding) (An appeal provides an inadequate remedy for the trial court’s failure to observe automatic abatement pursuant to the RCLA.). The benefits of mandamus review are not outweighed by the detriments of mandamus review in this case.“
In conclusion, “The trial court had no discretion to compel discovery while the case was abated, and Anderson, who has been compelled to respond to discovery during a period the case was under an automatic abatement, has no adequate remedy on appeal. Accordingly, we conditionally grant the petition for writ of mandamus. The writ will issue only if the trial court fails to vacate its order of February 3, 2011, and fails to refrain from proceeding with the case until a motion to reinstate is filed that establishes compliance with the notice and inspection requirements of the Residential Construction Liability Act.”
Read the trial court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Not to Miss at This Year’s Archtober Festival
October 15, 2014 —
Carrie Hojnicki – BloombergNew York architecture fanatics everywhere can rejoice: Archtober has arrived. In its fourth annual iteration, the monthlong festival throws a spotlight on the importance of architecture and design in the five boroughs, calling special attention to the city’s rich built history and exciting future. In addition to a lineup of lectures, openings, and workshops, the American Institute of Architects (AIA) New York Chapter–sponsored initiative highlights a “Building of the Day,” with on-site tours led by the architects themselves.
Here are five events not to miss this Archtober.
1. AIA’s New York chapter puts its own spin on the architecture tour: a boat ride. Guides from the AIA will share their wisdom as the cruise circles the tip of Manhattan, passing architectural marvels aplenty. October 3, 10 am and 1:30 pm, Classic Harbor Line
Read the court decisionRead the full story...Reprinted courtesy of
Carrie Hojnicki, Bloomberg
Million-Dollar U.S. Housing Loans Surge to Record Level
July 30, 2014 —
Alexis Leondis – BloombergBanks are handing out mortgages of as much as $10 million to the wealthy in record numbers while first-time homebuyers struggle to get loans.
Erin Gorman, managing director at Bank of New York Mellon Corp., said she’s fielding more requests for home loans of at least $2 million than ever before. She recently provided a mortgage of more than $6 million for a client’s purchase of a second property in Colorado.
“These high-net-worth borrowers do act differently than first-time buyers, who borrow because they have to,” said Gorman, who serves as the national mortgage sales director at Bank of New York Mellon’s wealth management group based in Boston. “High-net-worth borrowers don’t have to borrow. They choose to, so they’re very strategic about what, why, and when they borrow.”
Read the court decisionRead the full story...Reprinted courtesy of
Alexis Leondis, BloombergMs. Leondis may be contacted at
aleondis@bloomberg.net
When to Withhold Retention Payments on Private or Public Projects
August 29, 2018 —
Nicholas Karkazis - Gordon & Rees Construction Law BlogTo ensure that construction contractors and subcontractors receive timely progress and retention payments, the California Legislature enacted statutes that impose deadlines and penalties on owners and direct (general) contractors who delay payments. (Cal. Civ. Code, §§ 8800, 8802, 8812, 8814; Pub. Contract Code, §§ 7107, 10262.5; Bus. & Prof. Code, § 7108.5.) However, there is an exception to these deadlines and penalties on both private and public projects. The exception allows an owner or direct contractor to withhold payment1 when there is a good faith dispute between an owner and a direct contractor or between a direct contractor and a subcontractor. (Civ. Code, §§ 8800, subd. (b), 8802, subd. (b), 8812, subd. (c), 8814, subd. (c); Pub. Contract Code, §§ 7107, subds. (c), (e), 10262.5, subd. (a); Bus. & Prof. Code, § 7108.5, subd. (a).)
But the term “good faith dispute” has been a source of confusion where direct contractors owe subcontractors retention payments, but want to withhold the payment because of a dispute.2 California appellate courts were split, with one court finding that any type of bona fide dispute justified withholding, and another finding that only disputes related to the payment itself justified withholding. (Compare Martin Brothers Construction, Inc. v. Thompson Pacific Construction, Inc. (2009) 179 Cal.App.4th 1401 [any bona fide dispute could justify withholding] with East West Bank v. Rio School Dist. (2015) 235 Cal.App.4th 742 [disputes related to the payment itself may justify withholding].) In May 2018, the California Supreme Court clarified that for a direct contractor to withhold a retention payment on a private project, the good faith dispute must somehow relate to the payment itself. (United Riggers & Erectors, Inc. v. Coast Iron & Steel Co. (2018) 4 Cal.5th 1082, 1097-1098.)
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Karkazis, Gordon & Rees Scully MansukhaniMr. Karkazis may be contacted at
nkarkazis@grsm.com
Alexander Moore Promoted to Managing Partner of Kahana Feld’s Oakland Office
May 08, 2023 —
Alexander R. Moore - Kahana FeldKahana Feld is pleased to announce that Alexander R. Moore, Esq., has been promoted to Managing Partner of our Oakland office. Mr. Moore has been at Kahana Feld since 2021 and is a member of the construction defect and general liability practice groups.
Mr. Moore has over 23 years of experience representing individual and commercial clients in complex disputes arising out of construction contracts, construction defect allegations, premises liability matters, landlord-tenant disputes, and contractual disputes arising out of various business relationships involving financial services companies, technology companies, telecommunications companies, real estate brokerages, non-profits, and a range of small businesses. When not focused on litigation, Mr. Moore enjoys consulting on transactional matters including the development of construction and business contracts. He has extensive experience evaluating rights and obligations under construction contracts and related insurance programs. He also assists clients in the implementation of pre-litigation risk management strategies.
Read the court decisionRead the full story...Reprinted courtesy of
Alexander R. Moore, Kahana FeldMr. Moore may be contacted at
amoore@kahanafeld.com
Court Grants Insurer's Motion for Summary Judgment After Insured Fails to Provide Evidence of Systemic Collapse
April 15, 2024 —
Tred R. Eyerly - Insurance Law HawaiiWith the insurer conceding that there was evidence of potential collapse at portions of eight specific building locations, the court granted the insurer's motion for partial summary judgment in determining no additional buildings suffered from collapse. Exec. 1801 LLC v. Eagle W. Ins. Co., 2024 U.S. Dist. LEZXIS 5923 (D. Or. Jan. 11, 2024).
Executive 1801 owned a group of six buildings with eighty-six residential units. The court previously granted partial summary judgment on Executive 1801's rain damage claim, leaving only claims regarding collapse. Eagle insured "the property for direct physical los or damage to Covered Property . . . caused by or resulting from any Covered Cause of loss." The policy further provided, "We will pay for direct physical loss or damage to Covered Property, caused by collapse of a building or any part of a building insured under this policy, if the collapse is caused by . . . hidden decay."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Certificate of Merit to Sue Architects or Engineers Bill Proposed
May 03, 2011 —
CDJ STAFFNorth Carolina may become the twelfth state to require a Certificate of Merit to sue an architect or engineer. If North Carolina Senate Bill 435 (SB435) passes, then plaintiffs when filing a complaint will need to also attach an affidavit of a third-party licensed professional engineer or architect stating that the case has merit.
SB435 is a short two pages in its current form. The bill states that the “third-party licensed professional engineer or licensed architect shall (i) be competent to testify and hold the same professional license and practice in the same area of practice as the defendant design professional and (ii) offer testimony based upon knowledge, skill, experience, education, training, and practice. The affidavit shall specifically state for each theory of recovery for which damages are sought, the negligence, if any, or other action, error, or omission of the design professional in providing the professional service, including any error or omission in providing advice, judgment, opinion, or a similar professional skill claimed to exist and the factual basis for each such claim. The third-party licensed professional engineer or licensed architect shall be licensed in this State and actively engaged in the practice of engineering or architecture respectively.”
A few of the amendments allude to disciplining design professionals who certify civil actions that are without merit. The bill has been referred to the Committee on Judiciary I.
While North Carolina is considering enacting a Certificate of Merit law, eleven other states already require one, including Arizona, California, Colorado, Georgia, Maryland, Minnesota, New Jersey, Oregon, Pennsylvania, South Carolina, and Texas. Christopher D. Montez, a partner with Thomas, Feldman & Wilshusen, LLP, has written a useful summary for each state’s certificate of merit scheme.
Read the text of SB435
Track the progress of SB435
Read more from Christopher D. Montez’s article on Thomas, Feldman & Wilshusen, LLP site
Read the court decisionRead the full story...Reprinted courtesy of
Brazil’s Former President Turns Himself In to Police
July 22, 2019 —
Mario Sergio Lima - BloombergBrazil’s former President Michel Temer handed himself in to police following a court ruling that’s unlikely to cause upheaval in domestic politics.
Temer turned himself in on Thursday afternoon, after federal court judges ordered his detention on charges of corruption, embezzlement, money laundering and conspiracy. The former head of state was initially arrested on March 21 but released four days later. Temer’s lawyers did not immediately respond to a request for comment. The 78-year old’s party, the MDB, issued a note condemning the “unreasonable” decision.
Read the court decisionRead the full story...Reprinted courtesy of
Mario Sergio Lima, Bloomberg