Jury Convicts Ciminelli, State Official in Bid-Rig Case
August 14, 2018 —
Engineering News-RecordAfter a four-week trial but with less than two days of deliberation, a Manhattan federal jury convicted Louis Ciminelli, former head of the now-defunct Buffalo, N.Y., contractor LPCiminielli, and Alain Kaloyeros, the fired ex-head of SUNY Polytechnic Institute in Albany, N.Y., of fraud and conspiracy in a scheme to rig bids on a $750-million upstate New York manufacturing project.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
What ENR.com Construction News Gained the Most Views
January 09, 2023 —
C.J. Schexnayder - Engineering News-RecordAs the construction industry continued its ongoing recovery from the global pandemic in 2022, it also faced a number of formidable challenges—including staffing gaps, materials shortages, supply chain delays and the ongoing specter of inflation. Throughout the year, ENR editors reported on how these issues—and many more—were impacting the sector and how it responded.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
Mr. Schexnayder may be contacted at schexnayderc@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
New Mexico Holds One-Sided Dispute Resolution Provisions Are Unenforceable
November 05, 2024 —
Bill Wilson - Construction Law ZoneDispute resolution provisions that grant one party the unilateral right to choose either litigation or arbitration to resolve disputes are common in the construction industry. The main difference between the two forums is that courts are more likely to strictly enforce contract terms as written as well as the applicable law, while arbitrators make decisions on more equitable considerations, untethered to the contract terms and—to some degree—the law. The party with the sole discretion to select the dispute resolution procedure can select the process most beneficial to its interests based on the nature of the dispute, regardless of who brings the claims. In Atlas Electrical Construction, Inc. v. Flintco, LLC, 550 P.3d 881 (N.M. Ct. App. 2024), the Court of Appeals of New Mexico recently held that an arbitration provision in a subcontract, under which the contractor retained the exclusive right to choose whether disputes arising under the subcontract were litigated in court or arbitrated was unreasonably one-sided, substantively unconscionable, and unenforceable.
The Atlas Electrical case involved two sophisticated entities with equal bargaining strength to negotiate the terms of a subcontract. The parties agreed to a subcontract provision which provided in the relevant part:
In the event [contractor] and [subcontractor] cannot resolve the dispute through direct discussions or mediation … then the dispute shall, at the sole discretion of [contractor], be decided either by submission to (a) arbitration … or (b) litigation …
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
California Subcontractor Gets a Kick in the Rear (or Perhaps the Front) for Prematurely Recorded Mechanics Lien
October 21, 2019 —
Garret Murai - California Construction Law BlogCalifornia provides three statutorily recognized construction payment remedies: (1) mechanics liens; (2) stop payment notices; and (3) payment bond claims. Each is intended to provide payment protections for those who furnish labor, materials and services on a construction project. However, each is also different in important ways.
One of those differences has to do with timing. Specifically, when the statutory payment remedy may be used by a claimant. Stop payment notices can be served at any time during a project even before a claimant has completed its work. However, mechanics liens may only be recorded and payment bond claims may only be made after a claimant has completed or ceased performing its work.
In Precision Framing Systems, Inc. v. Luzuriaga, Case No. E069158 (August 29, 2019), the 4th District Court of Appeal examined whether a subcontractor had prematurely recorded a mechanics lien and, thereby, was prevented from filing a lawsuit to foreclose on its mechanics lien.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Understanding Entitlement to Delays and Proper Support
December 10, 2024 —
Andrew G. Vicknair - The Dispute ResolverIn a previous
post, we discussed delays on construction projects including (1) critical versus non-critical delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable delays. We also reviewed the common methods of delay analysis include (1) the Total Cost Method, (2) the Modified Total Cost Approach, and (3) the Measured Mile Method.
Once you have determined the type of delay and the method to be used to analyze and quantify the delay, it is important to understand the type of documents/evidence needed to support your claim for delay.
If a party determines that they are entitled to some type of recovery for the delay, the party making a claim for delay, such as a contractor, must have the proper documentation/evidence to assist in proving entitlement for damages from the delay. Without the proper back-up, contractors are generally unable to recover all of the additional costs and expenses associated with the delays or, at best, recover only an “equitable” amount. Generally, damages must be proved with reasonable certainty and may not be based on speculation or conjecture. Thus, it is crucial for a party asserting a delay to have the proper documentation to support a delay claim, if the goal is to recover the damages associated with the delay.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
Toll Brothers Surges on May Gain in Deposits for New Homes
June 01, 2020 —
Prashant Gopal - BloombergToll Brothers Inc. shares surged after the company posted profit that beat estimates and said deposits on new homes were up in recent weeks, a potential sign of optimism for the luxury housing market.
The homebuilder, which focuses on higher-end customers, has struggled during the pandemic. It reported orders for the second quarter that missed estimates and said the key metric had plunged starting March 16, when much of the economy shut down.
But investors shrugged off those results, focusing instead on a 13% year-over-year gain this month in deposits, which the company called a “leading indicator of current market demand.”
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, Bloomberg
FEMA Fire Management Assistance Granted for the French Fire
July 08, 2024 —
The Federal Emergency Management AgencyOAKLAND, Calif. – The Federal Emergency Management Agency's (FEMA) Region 9 Administrator authorized the use of federal funds on July 4 at 11:37 p.m. PDT / 2:37 a.m. EDT to assist the state of California to combat the French Fire burning in Mariposa County.
On July 4, the state of California submitted a request for a Fire Management Assistance Grant (FMAG). At the time of the request, the fire threatened approximately 1,019 homes in and around Mariposa, CA, population 1,300. 95% of the threatened homes are primary residences and 5% are secondary residences.
The fire started on July 4, 2024 and had burned more than 790 acres of State and private land. The fire was 0% contained. There are five large fires burning uncontrolled within the State.
FMAGs provide federal funding for up to 75 percent of eligible firefighting costs. The Disaster Relief Fund provides allowances for FMAGs through FEMA to assist in fighting fires that threaten to become a greater incident.
Eligible costs covered by FMAGs can include expenses for field camps, equipment use, materials, supplies and mobilization, and demobilization activities attributed to fighting the fire.
For more information on FMAGs, visit https://www.fema.gov/assistance/public/fire-management-assistance.
Read the court decisionRead the full story...Reprinted courtesy of
Miller Act Statute of Limitations and Equitable Tolling
July 11, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to a Miller Act payment bond claim, there is a one-year statute of limitations—“The Miller Act contains a statute of limitations provision that requires actions to ‘be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the claim.’” U.S. f/u/b/o Techniquex Specialty Flooring, Inc., v. Philadelphia Indemnity Ins. Co., 2022 WL 169070, *3 (M.D.Penn. 2022) (citing the Miller Act).
There is an argument, albeit a difficult one, to support an equitable tolling of the one-year statute of limitations. This would be an argument filed when the one-year statute of limitations expires, but there is reason for missing the statute of limitations caused typically by the overt misleading of the defendant (surety/bond-principal):
“Equitable tolling functions to stop the statute of limitations from running where the claim’s accrual date has passed.” “Equitable tolling is appropriate in three situations: (1) when the defendant has actively misled the plaintiff respecting the facts which comprise the plaintiff’s cause of action; (2) when the plaintiff in some extraordinary way has been prevented from asserting his rights; and (3) when the plaintiff has timely asserted his rights in the wrong forum.” The first ground for equitable tolling“appears to be the same, in all important respects” to equitable estoppel, which “excuses late filing where such tardiness results from active deception on the part of the defendant” and “what courts describe as ‘equitable tolling’ is encompassed by the latter two parts of our Circuit’s doctrine.” The extraordinary circumstances standard may be met “where the defendant misleads the plaintiff, allowing the statutory period to lapse; or when the plaintiff has no reasonable way of discovering the wrong perpetrated against her …”
Tehniquex, supra, at *5 (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com