Court Finds No Occurrence for Installation of Defective flooring and Explains Coverage for Attorney Fee Awards
January 05, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Navigators Specialty Ins. Co. v. Moorefield Const. (No.G050759, filed 12/27/16), a California appeals court held that the knowing installation of flooring over a vapor-emitting slab was not an accident or occurrence, entitling the insurer to reimbursement of money paid as damages to settle a construction defect suit. But the court further held that there was no right of reimbursement for the portion of money payable under the policy’s supplementary payments coverage as costs for contractual prevailing party attorney’s fees.
Navigators insured Moorefield, the general contractor for a Best Buy store. Testing in construction revealed a vapor emission rate from the concrete slab above the approved standard for the flooring. The contractor’s personnel testified that it was normal to install the flooring regardless. Notwithstanding, the contractor’s personnel testified that they consulted the owner and were directed to proceed. In doing so, the contractor also expressly released the flooring subcontractor from any warranty claims.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Court Clarifies a Limit on Payment Bond Claims for Public Projects
May 15, 2023 —
Bill Wilson - Construction Law ZoneIn All Seasons Landscaping, Inc. v. Travelers Casualty & Surety Co., No. DBD-CV21-6039074-S, 2022 WL 1135703 (Conn. Super. Ct. April 4, 2022) the plaintiff, a subcontractor on a state project, commenced a lawsuit against the surety who issued a payment bond on the project two years after the subcontractor last performed any original contract work on the project. The defendant surety moved to dismiss the action based on the one-year statute of limitation in Connecticut General Statute § 49-42. The plaintiff countered that it complied with that deadline because it also performed warranty inspection work after the contract was completed and within the limitation period in section 49-42. The issue of whether warranty work or minor corrective work can extend the limitations period in section 49-42 had not previously been addressed by a Connecticut court.
Section 49-42(b) governs the limitation period on payment bond claims on public projects. It provides in relevant part that “no … suit may be commenced after the expiration of one year after the last date that materials were supplied or any work was performed by the claimant.” Section 49-42 provides no guidance on what “materials were supplied or any work was performed” by the claimant means, nor is there any direct appellate-level authority in Connecticut on this issue. What is clear under well-established law in Connecticut is that the time limit within which suit on a payment bond must be commenced under Section 49-42 is not only a statute of limitation but a jurisdictional requirement establishing a condition precedent to maintenance of the action and such limit is strictly enforced. If a plaintiff cannot prove its suit was initiated within this time constraint, the matter will be dismissed by the court as untimely.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Replacement of Defective Gym Construction Exceeds Original Cost
January 22, 2013 —
CDJ STAFFAustin, Texas has torn down a school gym, the Turner-Roberts Recreation Center at the Overton Elementary School, due to structural problems which became evident after the gym was completed four years ago. The cost of the new gym is $6.4 million, more than the cost of building the gym in the first place. The city is paying $3 million in repair costs with the rest of the money coming from the companies that designed and built the now demolished gym. According to the Austin Statesman, the total cost to the city will be about $8.6 million.
The Turner-Roberts Recreation Center cost $5.6 million to build, but soon after it opened, structural problems were discovered. Cracks formed in walls and glass doors buckled. The settlement with the designer, contractor, and engineering firm did not require the firms to admit fault as they paid $3.4 million to fix the situation. The Statesman was unable to get a breakdown of how much each firm paid. Tom Cornelius, president of the GSC, the architectural firm on the project told the Statesman that "the foundation issues were not caused by design defects."
Initially, the city sought to repair the gym, but early excavation determined that the defects were too extensive. In addition to the structural flaws, it was also determined that the HVAC system was faulty. Excavation also damaged plumbing work. Tearing down the gym turned out to be the most cost-effective response.
Read the court decisionRead the full story...Reprinted courtesy of
America’s Infrastructure Gets a C-. It’s an Improvement Though
April 05, 2021 —
Garret Murai - California Construction Law BlogEvery four years the American Society of Civil Engineers (ASCE) issues a report card assigning a letter grade to the nation’s infrastructure. ASCE issued their 2021 Infrastructure Report Card earlier this month.
Our country’s grade in 2021? A disappointing C-.
It’s an improvement though. When ASCE issued their 2017 Infrastructure Report Card we didn’t even pass the class with a grade of D+.
In short, there’s room for improvement. A lot of room for improvement.
C- is just the cumulative grade however. ASCE’s Report Card is divided into industry segments with grades assigned to each segment. Individual grades for some, but not all, of the segments include the following:
- Aviation: The nation’s airports received a grade of D+. According to the Report Card, terminal, gate and ramp availability are not meeting the needs of a growing passenger base which has increased from 964.7 million to 1.2 billion per year and a has a 10-year shortfall of $111 billion.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Don’t Waive Too Much In Your Mechanic’s Lien Waiver
December 22, 2019 —
Christopher G. Hill - Construction Law MusingsIn the past few years, the Virginia General Assembly has, with certain caveats, precluded pre-furnishing waiver of mechanic’s lien rights. While this essentially outlawed the types of mechanic’s lien waiver clauses that pervaded construction contracts in Virginia, the key to the previous sentence is “pre-furnishing.” What the General Assembly left intact were the usual waivers of mechanic’s lien rights typically required to be provided to Owners and others in the payment chain in exchange for payment.
These lien waivers come in a few “flavors” from conditional to unconditional, partial to full. Their terms usually include an acknowledgement of receipt of payment (we’ll get to this later), and a statement that the one seeking payment knows of no possible claims by lower tier subcontractors and then waives all mechanic’s lien rights against the property for work performed and included in the request for payment. Often over my years as a Virginia construction attorney, I have noticed that these waivers are often signed without comment or review. They are just part of the process and more often than not are not even an issue for most projects. Of course, if they are an issue they can be a big one, and their terms can come back to bite a claimant that has not properly vetted them.
The first potential issue is waiving lien rights while acknowledging receipt prior to actual receipt of the check or wire. Many of the waiver forms that are out there list a payment amount, or possibly simply state that the waiver is in exchange for some small payment, and then state “receipt of which is acknolwedged” or something similar. The issue here is that receipt may not have happened yet because these lien waivers are submitted as part of the payment package in order to get paid in the first place. In short, should you sign the waiver prior to payment, you may have acknowledged a non-event and in the event of non-payment have a written document stating that you waived your claim to a lien for that money. What a court would do with this, I am unsure, but why risk it? My advice, be sure your waiver is contingent on actual clearance of payment as well as receipt.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Gilbane Project Exec Completes His Mission Against the Odds
January 19, 2017 —
Debra K. Rubin - Engineering News-RecordAfghanistan’s new Ministry of Defense headquarters in Kabul was supposed to symbolize the nation’s future—and U.S. support in that effort—as a self-sustaining, sophisticated structure akin to the Pentagon. But U.S. funding shortfalls stretched an anticipated 18-month project, which began in 2009, into years. While experienced in running projects in an underdeveloped country in which terror attacks and unstable regional politics are routine, Gilbane Building Co. Project Executive Michael P. Sousa wanted no part of this one in 2013, when he first toured it. “The structure was in a severe state of disrepair and riddled with poor construction,” he says, terming it “an embarrassment” to the U.S. government.
Read the court decisionRead the full story...Reprinted courtesy of
Debra K. Rubin, ENRMs. Rubin may be contacted at
rubind@enr.com
16 Wilke Fleury Attorneys Featured in Sacramento Magazine 2021 Top Lawyers!
September 20, 2021 —
Wilke Fleury LLPCongratulations to Wilke Fleury’s featured attorneys who made the Sacramento Magazine’s Top Lawyer List for 2021!
The voting for Professional Research Services’ survey to determine the top attorneys in 2021 for Sacramento Magazine was open to all licensed attorneys in Sacramento, Calif. Attorneys were asked whom they would recommend among 56 legal specialties, other than themselves, in the Sacramento area. Each attorney was allowed to recommend up to three colleagues in each given legal specialty. Once the online nominations were complete, each nominee was carefully evaluated on the basis of the survey results, the legitimacy of their license, and their current standing with the State Bar of California. Attorneys who received the highest number of votes in each specialty are reflected in the following list. – Sacramento Magazine
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury LLP
Insurer's Quote on Coverage for Theft by Hacker Creates Issue of Fact
December 16, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court found that the insurer's quote created an issue of fact on whether loss caused by a computer hacker would be covered. Metal Pro Roofing, LLC v. Cincinnati Ins. Co., 2019 Ind. App. LEXIS 355 (Ind. Ct. App. Aug. 9, 2019).
The insureds, Metal Pro Roofing, LLC and Cornett Restoration, LLC ("LLC's") discovered that their bank accounts had been hacked and over $78,000 stolen. They submitted claims to their insurer, Cincinnati. Coverage was denied, and the LLCs filed suit. Cross-motions for summary judgment were filed, and the court granted summary judgment to Cincinnati.
The "Forgery or Alternation" coverage applied to losses resulting directly from the "'forgery' or alteration of checks, drafts, promissory notes, or similar written promises, order or directions to pay a sum of money." "Forgery" was defined as "the signing of the name of another person or organization with the intent to deceive." The LLCs did not cite any evidence that the hacker "signed" anything, let alone that they signed "the name of another person or organization."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com