Construction Termination Part 3: When the Contractor Is Firing the Owner
August 07, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaLast week we discussed an Owner terminating a Contractor “for cause.” Today, it’s time for a 180: what is your role as the architect when the Contractor is quitting?
First, be aware that there are valid reasons for a contractor to quit within the contract itself. Most of these have to do with either (a) time delays/stand stills or (b) failure of the Owner to make payments as required.
The Contractor can suspend or terminate a contract with the Owner for cause, provided a 7 day written notice is given to Owner and Architect. See A201§14.1.3. (This can be an
email notice as all AIA notice clauses now allow).
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Hunton Andrews Kurth’s Insurance Recovery Practice, Partners Larry Bracken and Mike Levine Receive Band 1 Honors from Chambers USA in Georgia
June 14, 2021 —
Walter J. Andrews - Hunton Insurance Recovery BlogThe 2021 Chambers and Partners rankings for Georgia insurance recovery practices and lawyers are out and Hunton Andrews Kurth has received top honors. The rankings include Hunton Andrews Kurth’s Insurance Recovery practice and partners Lawrence J. Bracken II and Michael S. Levine, with all receiving Band 1 honors – the organization’s top-tier ranking. “The top-level ranking of our practice in Georgia, and the work that Larry and Mike bring to our clients in Georgia, specifically, is emblematic of the work our team is doing nationwide,” said Insurance Recovery Practice Head, Walter J. Andrews. “The Firm and I could not be more proud,” he added.
Chambers and Partners is an independent research company operating across more than 200 jurisdictions delivering detailed rankings and insight into the world’s leading lawyers. Its rankings are viewed as one of the most credible and reliable industry benchmarks.
Read the court decisionRead the full story...Reprinted courtesy of
Walter J. Andrews, Hunton Andrews KurthMr. Andrews may be contacted at
wandrews@HuntonAK.com
Architectural Firm, Fired by School District, Launches Lawsuit
October 01, 2013 —
CDJ STAFFEl Associates Architects and Engineers is suing the Boyertown School District after the district fired them for underestimating the cost of an expansion project. The school district, located in Pennsylvania, was seeking to increase student capacity. El Associates estimate lead to a $55 million budget, but D’Huy Engineering, the district’s construction management firm, estimated $70 million for the project.
After the Boyertown School District hired KCBA Architects, El Associates filed suit. El Associates contends that it had followed the contract requirements and that the school district was in violation of the contract’s provisions on terminating the agreement.
Read the court decisionRead the full story...Reprinted courtesy of
A Primer on Insurance for Construction Projects
November 30, 2020 —
Garret Murai - California Construction Law BlogPeople who live in glass houses should have insurance (in addition to not throwing stones). So too should your construction project.
The risks inherent on a construction project are many and varied, ranging from property damage to personal injury to pollution remediation costs, and wise contractors and project owners know that one of the best ways to mitigate these risks is through insurance. So, here’s a primer on what you need to know about insurance on construction projects.
Commercial General Liability Insurance (CGL)
What it Covers:
- Property damage.
- Bodily injury.
- Personal and advertising injury (e.g., libel and slander).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Charges in Kansas Water Park Death
March 28, 2018 —
David Suggs - CDJ STAFFCaleb Schwab, a 10-year old boy was killed by decapitation on a water slide at a Kansas City water park, Schlitterbahn in 2016. Thirteen other people had suffered injuries on the ride prior to Caleb’s death ranging in severity from broken toes to concussions. Schlitterbahn employees have since claimed that park officials covered up past occurrences of water slide injuries.
Three people have been indicted in this case according to a CNN report by Marlena Baldacci, Sheena Jones and Hollie Silverman. Jeffrey Henry, the co-owner of the Schlitterbahn water park, Tyler Austin Miles, the park’s former director of operations and John Schooley.
Charges include second-degree murder, involuntary manslaughter, aggravated battery and aggravated child endangerment. Caleb suffered a fatal injury when the raft that he and the two women who were riding with him became airborne and contacted the netting attached overhead.
Investigators have found maintenance issues and ride design flaws that violate safety standards leading to lack of prevention of rafts becoming airborne during the ride. Caleb’s family will receive nearly $20 million in the settlement. Caleb’s father Scott, released a statement about placing full trust in the Attorney General Derek Schmidt who is presiding over the investigation and indictments.
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Updates: You May Be Affected
July 19, 2017 —
Louis “Dutch” Schotemeyer – Newmeyer & Dillion LLPGovernor Brown Signs Legislation Increasing Cal/OSHA Fines
Cal/OSHA has increased its maximum fines for the first time in more than twenty years pursuant to legislation recently signed into law by Governor Brown. The changes nearly double the maximum fines and have brought California in line with the Federal standard. The increase in fines will not be isolated to this year, as fines will now be automatically increased annually based on the percentage increase in the Consumer Price Index for All Urban Consumers (CPI-U). Additionally, any employer who repeatedly violates any occupational safety or health standard, order, or special order, or Section 25910 of the Health and Safety Code, can no longer receive any adjustment of a penalty assessed based on the good faith or the history of previous violations. Such adjustments were previously commonplace.
Specific increases are listed below (all increases refer to maximum fines, Cal/OSHA has discretion as to the amount of the fine when issuing the citation):
- Section 6427 of the Labor Code was amended to increase fines, not of a serious nature, from $7,000 for each violation to $12,471 for each violation.
- Section 6429 of the Labor Code has increased fines for repeat violations; raising the maximum fine from $70,000 to $124,709 for each violation. Additionally, Section 6429 also raised the minimum fine for repeat violations from $5,000 to $8,908.
- Section 6431 raised fines for posting or recordkeeping violations from $7,000 to $12,471 per violation.
Full text of the penalty section of the labor code may be found
here
California OSHA Emergency Action Plan elements revised; California now more consistent with Federal Standards
Revisions to General Safety Orders section 3220(b) became effective on June 5, 2017 and contain two minor changes for California employers with regards to Emergency Action Plans (EAP).
The first change requires that an employer’s EAP be more detailed in describing the type of evacuation that is to be performed, not just the route for an evacuation. The previous element of the EAP simply required that the plan contain, “[e]mergency escape procedures and emergency escape route assignments.” The current element of the EAP requires that, “[p]rocedures for emergency evacuation, including type of evacuation and exit route assignments,” be identified.
The second change clarifies the language surrounding employees performing rescue or medical duties. Previously the only requirement in the EAP regarding rescue and medical duties was for employees that performed rescue and medical duties. The current version requires that the EAP contain, “[p]rocedures to be followed by employees performing rescue or medical duties. The use of the word and created potential gaps in plans as it is likely that employees may not be performing both rescue and medical duties, instead performing just rescue or medical duties. Plans must now include procedures to be followed by employees who perform either rescue or medical duties.
It is recommended that your EAP be in writing and updated to comply with the revised General Safety Orders section 3220. The full text of General Safety Orders section 3320 can be seen
here. Please contact us if you would like further details regarding your Emergency Action Plan.
Deadline for Electronic Submission of OSHA 300 Log Records for Injuries and Illnesses Delayed
On May 12, 2016, the Federal Occupational Safety and Health Administration (OSHA) published a rule entitled “Improve Tracking of Workplace Injuries and Illnesses” which required certain employers subject to Federal OSHA regulations to submit the information from their completed 2016 Form 300A to OSHA via electronic submission no later than July 1, 2017. On June 28, 2017, OSHA, via a
Notice of Proposed Rule Making, has proposed a December 1, 2017 deadline for the electronic reporting; the electronic reporting system is scheduled to be available on August 1, 2017.
Per the California Department of Industrial Relations, California employers are not required to follow the new requirements and will not be required to do so until "substantially similar" regulations go through formal rulemaking, which would culminate in adoption by the Director of the Department of Industrial Relations and approval by the Office of Administrative Law.
Cal/OSHA drafted a proposed rulemaking package to conform to the revised federal OSHA regulations by amending the California Code of Regulations, title 8, sections 14300.35, 14300.36, and 14300.41; these are currently under review with the State.
It is currently unclear what, if any, impact the delay by OSHA will have on the proposed amendments to the California Code.
We will keep you posted as to the changes in California recordkeeping requirements. Please contact Louis “Dutch” Schotemeyer with any questions regarding Cal OSHA or your safety program. Dutch is located at Newmeyer & Dillion’s Newport Beach office and can be reached at dutch.schotemeyer@ndlf.com or by calling 949.271.7208.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
DoD Issues Guidance on Inflation Adjustments for Contractors
August 15, 2022 —
Jennifer Harris & Abby Salinas - ConsensusDocsThe Department of Defense (“DoD”) recently issued a memorandum to contracting officers (“COs”) guiding the use of economic price adjustment (“EPA”) clauses to address inflation-related cost increases. The memorandum, entitled Guidance on Inflation and Economic Price Adjustments, comes as the year-over-year inflation rate rose to 8.6% in May, and contractors with fixed-price contracts seek ways to recover their rising costs. EPA clauses allow the parties to mitigate cost risks that present themselves as a result of circumstances beyond the contractor’s control, e.g., inflation and supply chain price fluctuations. Generally, an EPA clause will dictate that the Government bear the cost risk up to a mutually agreed-upon ceiling. EPA clauses apply to the cost portion of a contract, but do not normally apply to the profit. DFARS PGI 216.203-4.
Memorandum: No CO Authority to Grant Contractual Relief Absent an EPA Clause
The memorandum states that absent an existing EPA clause, COs do not have the authority to provide contractual relief for unanticipated inflation under a firm-fixed-price contract.
Reprinted courtesy of
Jennifer Harris, Peckar & Abramson, P.C. (ConsensusDocs) and
Abby Salinas, Peckar & Abramson, P.C. (ConsensusDocs)
Ms. Harris may be contacted at jharris@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Contract’s Definition of “Substantial Completion” Does Not Apply to Third Party for Purposes of SOL, Holds Court of Appeal
June 15, 2020 —
Garret Murai - California Construction Law BlogThose of you in the construction industry know that the two primary statutes of limitation are the 4-year year statute of limitations for patent defects and 10-year statute of limitations for latent defects. Both statutes begin to run on “substantial completion.”
In Hensel Phelps Construction Co. v. Superior Court of San Diego, Case No. D076264 (January 22, 2020), the 4th District Court of Appeal examined whether the term “substantial completion,” as used in Civil Code section 941, which applies to residential construction, can be defined by the parties’ contract and applied to third-parties.
The Hensel Phelps Case
Hensel Phelps Construction Co. entered into a prime construction contract with the owner and developer of a mixed-use project in San Diego. Hensel Phelps was the general contractor on the project. The project included a residential condominium tower which would eventually be managed and maintained by Smart Corner Owners Association. Smart Corners was not a party to the contract.
Read the court decisionRead the full story...Reprinted courtesy of