Arizona Court of Appeals Upholds Judgment on behalf of Homeowners against Del Webb Communities for Homes Riddled with Construction Defects
February 26, 2015 —
Law Offices of Kasdan Weber Turner LLPARIZONA COURT OF APPEALS UPHOLDS LOWER COURT DECISION APPROVING $13,703,039 JUDGMENT ON BEHALF OF 460 SUN CITY GRAND HOMEOWNERS AGAINST DEL WEBB COMMUNITIES, INC., A SUBSIDIARY OF PULTEGROUP, INC., FOR HOMES RIDDLED WITH CONSTRUCTION DEFECTS
--
In a separate case, an Arizona Superior Court awards $10,619,640 to another 279 Sun City Grand homeowners who sued Del Webb over construction defects, which Del Webb has appealed--
PHOENIX, Arizona – The Arizona Court of Appeals, Division One, [on Tuesday] issued a unanimous ruling upholding a lower court decision awarding $13,703,039 to 460 Sun City Grand homeowners who sued developer Del Webb Communities, Inc., a subsidiary of PulteGroup, Inc., for numerous construction defects that severely damaged the plaintiffs’ homes. Sun City Grand is an age-restricted community located in Surprise.
In a separate case, an Arizona Superior Court awarded $10,619,640 to another group of 279 Sun City Grand homeowners for multiple construction defects in their homes.
Stephen Weber, the managing partner in the Phoenix office of Kasdan Weber Turner LLP, which represents the homeowners, said that the case is based on construction defects that damaged the plaintiffs’ homes and took several years to resolve. The defects include defective windows, poorly installed stucco, expansive soil conditions that resulted in cracking of drywall, and deteriorating concrete foundation systems, among other problems.
“Del Webb placed an arbitration clause in the sales contracts and the homeowners honored it. The binding arbitration that includes the owners of 460 homes in Sun City Grand was completed in late 2011 when the arbitration panel unanimously awarded the homeowners $13,703,039. Del Webb then challenged the award in Superior Court and the Superior Court confirmed the award in full,” Weber explained. “Del Webb did not like the Superior Court ruling either and challenged it in the Court of Appeals. And now three justices of the Arizona Court of Appeals have unanimously affirmed the Superior Court order and the arbitration award stands. Now they will have the funds to repair their homes, restore their value, and live in comfort,” Weber said.
The $13,703,309 award includes amounts for home repairs, attorney fees, expert fees, court costs and pre-judgment interest. An additional $1,401,236 in post-judgment interest also accrued while the case was on appeal. The other construction defect case that awarded $10,619,640 to homeowners was not covered by binding arbitration.
Del Webb has also appealed that case which will now go through the appeals process. That could take two to three years and again the homeowners will have to wait for the final judgment, Weber noted.
Ken Kasdan, senior and managing partner of the Kasdan Weber Turner firm and one of the nation’s leading experts on construction defect litigation, said the defects are egregious. “The multiple defects rob them of pride of ownership,” he said. “A home is something that a homeowner wants to be proud of. Unfortunately, defective workmanship and poor construction have caused damage to the homes. Now these homes can be repaired and the homeowners will no longer have to deal with defective windows and cracked slabs. Developers need to understand that arbitration awards are final and binding,” Kasdan noted.
The Kasdan Weber Turner law firm has offices in Phoenix, Arizona and in Irvine, California and Walnut Creek, California. The firm represents property owners in major construction defect litigation. For more information on the firm, visit www.kasdancdlaw.com. Stephen Weber may be contacted at (602) 224-7800.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Industry Outlook: Building a Better Tomorrow
July 25, 2021 —
Michael Alberico - Construction ExecutiveCOVID-19 plunged the business world into one of the most challenging times not seen since the Great Depression. The construction industry, deemed an essential business, had to quickly innovate to find new ways of working to weather this storm. Several of these seemingly temporary solutions have spawned positive trends that are here to stay.
Not Just Green, But Healthy Too
The safety culture that exists on today’s jobsites helped contractors stay productive through the pandemic. However, because of the pandemic, project owners and construction firms are evaluating their sites from a new perspective. In a recent meeting, the construction head for a healthcare system stated he knows a safe jobsite but doesn’t know what he doesn’t know about a healthy site.
Reprinted courtesy of
Michael Alberico, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Alberico may be contacted at
malberico@assuranceagency.com
Real Estate & Construction News Roundup (10/04/23) – NFL Star Gets into Real Estate, DOJ Focuses on “Buyer-Broker Commissions”, and the Auto Workers’ Strike Continues
November 13, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, seller impersonation fraud becomes an issue in the United States, major retailers are closing over 3,000 stores nationwide, the Tampa Rays are set to construct a new $1.3 billion stadium, and more!
- NFL star Tyler Lockett is preparing for his life and career after football by becoming a real estate broker in both Washington state and Texas. (Brady Henderson, ESPN)
- Seller impersonation fraud has become a major scam in the United States with 73% of real estate firms reporting an increase in these schemes since the beginning of the year. (Diane Tomb, Fortune)
- “Buyer-broker commissions” are a focus for the U.S. Justice Department as they have filed a “statement of interest” in one case in Massachusetts while there are several other pending lawsuits in U.S. courts. (Mike Scarcella, Reuters)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Study May Come Too Late for Construction Defect Bill
February 14, 2013 —
CDJ STAFFColorado State Senator Mark Scheffel removed his bill, Senate Bill 13-052, from the calendar of the Senate Judiciary Committee in anticipation of a study which he feels would be pertinent to the discussion. The bill would stop communities from suing developers over noise and vibration issues associated with transit facilities, and would also provide for developers fixing construction defects before being sued. Senator Scheffel said that the intent of his bill was to spur development near transit facilities.
The study, commissioned by the Denver Regional Council of Governments, would focus on the effects of the state’s construction defects law on housing. It might not come soon enough for the senator’s bill. The Denver Business Journal reports that the study, which will take four months to complete, doesn’t yet have a contract. The Legislature must adjourn by May 8, so it is not possible for the study to be concluded before the end of this legislative session.
Read the court decisionRead the full story...Reprinted courtesy of
Revamp to Nationwide Permits Impacting Oil and Gas Pipeline, Utility and Telecom Line Work
March 29, 2021 —
Alex P. Prochaska, Jones Walker LLP - ConsensusDocsTo avoid delay costs and penalties, contractors involved in pipeline and utilities construction maintenance, repair and removal need to understand how the 43 year old Nationwide Permit (NWP) regime has changed specific to the NWP 12 and what is now required for compliance. This change is important for contractors who construct, maintain, or repair pipelines that cross or impact waters of the United States, including wetlands. NWPs are a useful tool to streamline construction of a pipeline project, but it is important for contractors to know when certain terms and conditions still apply to the particular NWP and those that have been eliminated.
On January 13, 2021, the United States Army Corps of Engineers (the Corps) published a final rule that reissued and modified twelve existing NWPs and issued four new NWPs that will take effect on March 15, 2021.1 The remaining 40 NWPs that were not reissued or modified under this rule will continue under the general conditions and definitions of the January 6, 2017 final rule.
Read the court decisionRead the full story...Reprinted courtesy of
Alex P. Prochaska, Jones Walker LLPMr. Prochaska may be contacted at
aprochaska@joneswalker.com
U.S. Steel Invoking Carnegie’s Legacy in Revival Strategy
July 23, 2014 —
Sonja Elmquist – BloombergIn March 2013, Mario Longhi lobbed an unexpected question into a roomful of 150 U.S. Steel Corp. managers: Who here would buy the company’s stock, tomorrow?
He gave them three seconds, and “only a few reacted in that time frame positively,” Longhi said.
Since that meeting, Longhi has been promoted to chief executive officer, and nine months into his tenure he’s closed one plant permanently, two more are temporarily idled and he’s planning to overhaul another. It’s all part of his plan to transform the 144-year-old company into a lean, modern steel producer. Investors are taking note, with the shares up 53 percent since he took over.
Read the court decisionRead the full story...Reprinted courtesy of
Sonja Elmquist, BloombergMs. Elmquist may be contacted at
selmquist1@bloomberg.net
Court Says KBR Construction Costs in Iraq were Unreasonable
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFMike Bosse of Bernstein Shur, analyzed a case involving Kellogg Brown and Root Services Inc. (KBR) and the U.S. Army for services that KBR provided during Operation Iraqi Freedom, according to JDSupra Business Advisor: “The court case involved KBR’s construction of dining facility services near Mosul, Iraq under a cost-plus fee arrangement. Under this contractual arrangement, all allowable costs were reimbursed by the government plus the contractor was paid an additional fee.”
KBR first started on a prefabricated metal dining hall that would serve 2,500 people, but part way into building they were told to stop construction and to instead start on a new reinforced concrete building that would serve almost three times as many people.
“After construction was finished, a defense contract auditing agency suspended some of the payments to KBR and instead of the $12.5 million it expected to receive, KBR was paid only $6.7 million,” reported JDSupra Business Advisor. “After trial, the court concluded KBR did not meet its burden to show the costs it incurred were reasonable under the circumstances.”
Read the court decisionRead the full story...Reprinted courtesy of
Ceiling Collapse Attributed to Construction Defect
May 19, 2011 —
CDJ STAFFWSMV, Nashville reports that the ceiling collapse in a Franklin, Tennessee Kohl’s was attributed to a construction defect by fire officials. The officials noted that the ceiling was renovated at the time. No injuries were reported.
The report notes that “inspectors were supposed to look at the renovations next week, but fire officials said that will have to be delayed until another time.”
Read the full story…