Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Newmeyer Dillion Attorneys Named to 2020 Southern California Rising Stars List
June 22, 2020 —
Newmeyer DillionProminent business and real estate law firm Newmeyer Dillion is pleased to announce that partner Eric Rollins and associates Jason Moberly Caruso and Richard Protzmann have been selected to the 2020 Southern California Rising Stars list by Super Lawyers. Each year, no more than 2.5 percent of the lawyers in the state are selected to receive this honor. The attorneys will be recognized in the June 2020 issues of Super Lawyers Magazine, Los Angeles Magazine and Orange Coast Magazine.
Eric Rollins, a partner in the Newport Beach office, provides legal counsel in a diverse array of practice areas with a focus on business, real estate, construction, insurance, and entertainment law. In his more than ten years at the firm, Eric has litigated and resolved hundreds of matters in both state and federal court through negotiation, mediation, arbitration, and trial. This is his third year as a Rising Star honoree.
Jason Moberly Caruso is an associate in the Newport Beach office. Jason's practice focuses on various aspects of "contaminated sites" environmental legal work, complex litigation, and appellate matters. This is the fifth consecutive year Jason has been honored.
Richard Protzmann is an associate in the Newport Beach office. Richard's practice focuses on focuses his practice on areas of business litigation, eminent domain, environmental law, zoning and land use, and general real estate litigation. This is the first year Richard has been selected.
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The patented selection process evaluates candidates on 12 indicators of peer recognition and professional achievement, resulting in a comprehensive, credible and diverse listing of exceptional attorneys. The Rising Stars list is developed using the same selection process except candidates must be either 40 years old or younger, or have been in practice for 10 years or less.
About Newmeyer Dillion
For 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 70 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, environmental/land use, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's operations, growth, and profits. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
Harsh New Time Limits on Construction Defect Claims
April 26, 2011 —
Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq.A recent Colorado Supreme Court decision, Smith v. Executive Custom Homes, Inc., 230 P.3d 1186 (Colo. 2010), considerably shortens the time limit for bringing many construction defect lawsuits. Homeowners and homeowner associations risk losing the right to seek reimbursement from builders, developers and other construction professionals unless they carefully and quickly act upon discovery of evidence of any potential construction defect.
The Statute of Limitations for Construction Defect Claims
Colorado’s construction defect statute of limitations limits the time for homeowners and homeowners associations to bring lawsuits for construction defects against “construction professionals,” including developers, general contractors, builders, engineers, architects, other design professionals, inspectors and subcontractors. The statute requires homeowners and associations to file suit within two years “after the claim for relief arises.” A claim for relief “arises” when a homeowner or association discovers or reasonably should have discovered the physical manifestation of a construction defect.
The two-year time limitation applies to each construction defect separately, and will begin to run upon the appearance of a “manifestation” of a construction defect (which may include, for example, a condition as simple as a roof leak or drywall cracks), even if the homeowner or association does not know the cause of the apparent problem.
The Smith Opinion and its Effect on the Statute of Limitations
In Smith v. Executive Custom Homes, Inc., the plaintiff homeowner, Mrs. Smith, slipped on ice that had accumulated on her sidewalk because of a leaking gutter and suffered injury. When she first noticed the leak, she reported it to her property manager, who reported it to the builder. The builder attempted to repair the gutter, unbeknownst to Mrs. Smith, and she did not notice further problems until approximately one year after she first observed the leak, when she fell and suffered serious injury. She sued the builder within two years of her injury, but nearly three years after she first learned of the leak.
The Colorado Supreme Court dismissed Mrs. Smith’s claims as untimely and held that under the construction defect statute of limitations, the two-year period for suing for injuries due to construction defects begins when the homeowner first observes the physical manifestation of the defect, even if the resulting injury has not yet occurred. The court acknowledged that this ruling could result in “unfair results,” especially if a serious and unforeseeable injury occurs more than two years after the first time the homeowner noticed the problem, and as a result the victim is unable to seek redress from those responsible for the defect.
Read the full story…
Reprinted courtesy of Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq. of Sullan2, Sandgrund, Smith & Perczak, P.C., and they can be contacted through their web site.
Read the court decisionRead the full story...Reprinted courtesy of
Public-Private Partnerships: When Will Reality Meet the Promise?
October 09, 2018 —
Richard Fechner, GHD - Engineering News-RecordThe promise of public-private partnerships (P3s) seems irresistible. The $4.5-trillion that the American Society of Civil Engineers says the U.S. must spend on at-risk infrastructure by 2025 is a backlog beyond the collective means of local, state and federal governments to fund and deliver.
Read the court decisionRead the full story...Reprinted courtesy of
Richard Fechner, GHD, ENRENR may be contacted at
ENR.com@bnpmedia.com
Cultivating a Company Culture Committed to Safety, Mentorship and Education
March 19, 2024 —
David Frazier - Construction ExecutiveThe construction industry is aging. Valuing the significance of promoting a culture that enhances safety, mentorship and educational opportunities is essential to recruiting and retaining top talent to keep the industry thriving.
According to the U.S. Department of Labor, one in five worker deaths in the U.S. occurs in the construction industry. Additionally, construction workers are statistically at a higher risk for mental-health issues than virtually every other profession. According to a study conducted by CIRP, 83% of construction workers have struggled with mental-health disorders.
Today’s leaders must be dedicated to listening to employees' voices to shape the construction industry, as future leaders will be formed by a culture committed to employees' mental and physical health, safety, professional growth and overall workplace culture.
Reprinted courtesy of
David Frazier, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Governor Signs AB5 Into Law — Reshaping California's Independent Contractor Classification Landscape
December 02, 2019 —
Eric C. Sohlgren & Matthew C. Lewis - Payne & Fears Legal AlertToday, Governor Gavin Newsom signed California Assembly Bill 5 (“AB5”), controversial legislation which will have a substantial impact on California employers when it goes into effect on January 1, 2020.
AB5 enacts into a statute last year’s California Supreme Court decision in Dynamex Operations West, Inc. v. Superior Court, 4 Cal. 5th 903 (2018), and the Court’s three-part standard (the “ABC test”) for determining whether a worker may be classified as an employee or an independent contractor.
Under the ABC test established in Dynamex and now under AB5, a worker may be properly considered an independent contractor only if the hiring entity establishes all three of the following: (A) that the worker is free from the control and direction of the hirer in connection with the performance of the work, both under the contract for the performance of such work and in fact; (B) that the worker performs work that is outside the usual course of the hiring entity’s business; and (C) that the worker is customarily engaged in an independently established trade, occupation, or business of the same nature as the work performed for the hiring entity.
Reprinted courtesy of
Eric C. Sohlgren, Payne & Fears and
Matthew C. Lewis, Payne & Fears
Mr. Sohlgren may be contacted at ecs@paynefears.com
Mr. Lewis may be contacted at mcl@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Coronavirus and Contract Obligations
March 30, 2020 —
David R. Cook - AHC Construction and Procurement BlogThe Coronavirus (COVID-19) pandemic has caused a global disruption to businesses, causing many to temporarily close and lay off employees. As businesses assess the short– and long–term economic impact of COVID-19, they should also evaluate what contractual obligations and remedies are available under various agreements (e.g., leases, vendor agreements, and supply agreements). When performance may be delayed or may not occur altogether, businesses should consider their force majeure clauses, if any, and the doctrines of impossibility, impracticability, and frustration of purpose.
Force Majeure
Generally, unless a contract provides that performance will be suspended or relieved when certain events occur (e.g., “acts of God,” government regulation, acts of war or terror, strikes), each party is obligated to perform. However, when there is an express force majeure provision, certain events or acts may excuse non-performance or delayed performance. But depending on the jurisdiction, courts may construe force majeure provisions narrowly and excuse performance only for those events expressly listed in the clause. Nonetheless, if the force majeure provision includes pandemic, epidemic, quarantine, government act, disease, or similar terms, then the COVID-19 pandemic may excuse performance or allow delayed performance.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Congratulations Devin Brunson on His Promotion to Partner!
April 26, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is very proud to announce Devin Brunson has been promoted to the position of partner with the firm!
Mr. Brunson came to BWB&O from another civil litigation firm and helped start the Denver, Colorado office along with partners Lucian Greco, John Toohey and Peter Brown. He has taken on a significant leadership role within the firm over the past several years and has been integral in growing the office to its current footprint.
He is licensed to practice law in Colorado, District of Colorado, and in the U.S. District Court. His practice is focused in the areas of civil and business litigation, construction litigation, and employment law. Mr. Brunson has a diverse practice background that includes complex civil litigation and intellectual property disputes and has had the privilege of representing business owners, contractors, corporate executives, and professional athletes during the course of his career.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP