White and Williams Obtains Reversal on Appeal of $2.5 Million Verdict Against Electric Utility Company
September 03, 2014 —
Edward Koch, Mark Paladino, Luke Repici, & Andrew Susko – White and Williams LLPPPL Electric Utilities successfully argued on appeal that the $2.5 million plaintiff’s molded verdict awarded to an injured painting subcontractor should be vacated because the alleged evidence was legally insufficient and therefore the utility was not liable.
In Nertavich v. PPL Electric Utilities, the plaintiff argued that although the utility was a landowner out of possession of the worksite, the utility was liable because it controlled the work of the subcontractor both by contract and by conduct. PPL argued on appeal before the Superior Court of Pennsylvania that the alleged evidence of the utility company’s control was insufficient as a matter of law to constitute control over the means and methods of the subcontractor’s work, and thus, PPL was not liable as a landowner out of possession.
Reprinted courtesy of White and Williams LLP attorneys
Edward Koch,
Mark Paladino,
Luke Repici and
Andrew Susko
Mr. Koch may be contacted at koche@whiteandwilliams.com;
Mr. Paladino may be contacted at paladinom@whiteandwilliams.com;
Mr. Repici may be contacted at repicil@whiteandwilliams.com;
and Mr. Susko may be contacted at suskoa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Insured's Expert Qualified, Judgment for Coverage Affirmed
December 15, 2016 —
Tred R. Eyerly – Insurance Law HawaiiAddressing a host of issues on appeal, the Texas Court of Appeals affirmed the trial court's judgment against the insurer for property damage caused by Hurricane Ike. Nat'l Sec. Fire & Cas. Co. v. Henriquez, 2016 Tex. App. LEXIS 11391 (Tex. Ct. App. Oct. 20, 2016), withdrawn and substituted by 2016 Tex. App. LEXIS 12766 (Tex. Ct. app. Dec. 1, 2016).
The insureds alleged property damage to their home caused by the hurricane. The roof was damaged, resulting in interior water damage. Sheetrock, exterior bricks, windows, walls cabinets and insulation throughout the entire home were damaged. The insureds also alleged that the home shifted during the storm, causing the foundation to not be level and the ceilings and walls to crack. Personal property within the dwelling was also damaged.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Property Insurance Exclusion for Constant or Repeated Leakage of Water
March 14, 2018 —
David Adelstein – Florida Construction Legal UpdatesA
property insurance policy, no different than any insurance policy, contains
exclusions for events that are NOT covered under the terms of the policy. One such common exclusion in a property insurance policy is an exclusion for damages caused by "
constant or repeated seepage or leakage of water…over a period of 14 or more days."
The application of this exclusion was discussed in the recent opinion of
Hicks v. American Integrity Ins. Co. of Florida, 43 Fla. L. Weekly D446a (Fla. 5th DCA 2018). In this case, while the insured was out of town, the water line to his refrigerator started to leak. When the insured return home over a month later, the supply line was discharging almost a thousand gallons of water per day. The insured submitted a property insurance claim. The property insurer engaged a consultant that opined (likely, correctly) that the water line had been leaking for at least five weeks. Based on the above-mentioned exclusion,
i.e., that water had been constantly leaking for over a period of 14 days, the insurer
denied coverage. This denial led to the inevitable coverage dispute.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Construction Litigation Roundup: “The New Empty Chair.”
June 04, 2024 —
Daniel Lund III - LexologyIn a unanimous opinion, the United States Supreme Court ruled that cases in litigation in federal court but which are determined to be governed by the Federal Arbitration Act should be stayed pending arbitration, not dismissed.
Traditionally, some federal circuits treated the text of 9 U.S.C. §3 – which speaks in terms of a stay of a matter filed in court but referred to arbitration (“…shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement…”) – as discretionary, dismissing suits when all of the claims brought in the court were referred to arbitration.
In the case, the plaintiffs sued in Arizona state court on labor law violations, and the case was removed to federal court. When the defendant moved to compel arbitration and to dismiss, the plaintiffs “conceded that all of their claims were arbitrable.” Nonetheless, the plaintiffs requested a stay of the case, which the district court refused, dismissing the case without prejudice.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Harvey's Aftermath Will Rattle Construction Supply Chain, Economists Say
September 07, 2017 —
Tim Grogan - Engineering News-RecordHurricane Harvey’s immediate impact on the construction sector will be a disruption in the supply chain for key materials, along with scheduling problems for projects that were under construction. As the cleanup and eventual rebuilding proceed, increased demand for materials and labor will push costs upward and contractors will be scrambling to secure supplies and workers.
Read the court decisionRead the full story...Reprinted courtesy of
Tim Grogan, ENRENR may be contacted at
ENR.com@bnpmedia.com
LEEDigation: A Different Take
June 22, 2020 —
Christopher G. Hill - Construction Law MusingsThis weeks Guest Post Friday at Musings is a real treat. Sara Sweeney is a registered architect, LEED AP and GreenFaith Fellow in religious environmental leadership. Her 18-year architectural career reflects her passion and commitment to sustainable building design and stewardship of our natural environment. She is the founder of EcoVision LLC, a solutions-based research and consulting firm, grounded in sustainable design practices, environmental stewardship, and building science.
Dude
Every so often I come across a word that drives me nuts. A few years ago it was ‘Dude.’ Lately, it is ‘LEEDigation.’ It’s a new term to “describe green building litigation” coined by Chris Cheatham, a fine person and very knowledgeable attorney in construction law and a LEED AP as well. Per his definition, LEEDigation “could involve disputes arising from green building certification, could arise if a project fails to obtain government incentives or satisfy mandates for green building construction, or could simply result from improperly designed or constructed green building strategies. It all makes sense. So why does it drive me nuts?
Round Peg. Square Hole.
Although I fully understand why the term was coined, such a term keeps us in flat world, that is, the world of conventional design and construction. Designing and building to LEED standards, or rather, just designing and building sustainably in general, whether to meet a third party standard or not, is a different way than what we have been used to. Period. Whereas our conventional way is focused on first costs, and sees the building more as a commodity than the human imprint and legacy on Earth, sustainable design and building is a process which, at its best, considers the economic impacts of NOT building responsibly. It is a more holistic way of building and balances long-term costs and implications with short term costs.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Multigenerational Housing Trend
May 02, 2014 —
Beverley BevenFlorez-CDJ STAFFReuters reported that “[m]ore than 50 million Americans already live in multigenerational situations, according to Pew Research, and the number is expected to grow as baby boomers age.” Lennar Corp has “Next Gen” home models, which provides multigenerational housing for prices similar to traditional homes. For instance, according to Reuters, one of the Next Gen models contains “an 800-square-foot house-within-a-house” with “a separate entrance and its own patio, plus a bedroom, sitting area, and bathroom.”
Other home builders are also providing multigenerational housing: “Gertz Fine Homes, which builds between 12-30 houses a year near Portland, Oregon, says about 30 percent of sales are now multigenerational models, which can cost around $600,000.”
Read the court decisionRead the full story...Reprinted courtesy of
The Burden of Betterment
February 23, 2017 —
Ryan M. Charlson, Esq. - Florida Construction Law NewsThe concept of betterment has long been used by defendants in cases involving defective design or construction to limit the damages awarded to a plaintiff.[1] The theory behind betterment is that: “if in [the] course of making repairs [an] owner adopts a more expensive design, recovery should be limited to what would have been the reasonable cost of repair according to original design.”[2] Betterment is often raised as an affirmative defense, requiring a defendant to prove that the plaintiff has received a good or service that is superior to that for which the plaintiff originally contracted. A recent South Florida case seems, at first blush, to suggest the burden of establishing the value of betterments may fall to the plaintiff, although a closer reading indicates the decision is likely to have limited applicability.
In Magnum Construction Management Corp. v. The City of Miami Beach, the Third District Court of Appeal was asked to review the damages award to the City for construction defects associated with the redesign and improvement of a park.[3] The completed project contained landscaping deficiencies, along with other “minor defects” in the playground’s construction.[4] After a unilateral audit, and without providing the contractor its contractually required opportunity to cure the defects, the City “removed, redesigned, and replaced the playground in its entirety.”[5] It did so despite no recommendation by the City’s own expert to perform such work.[6] During the bench trial, the “only measure of damages provided by the City was the costs associated with the planning, permitting, and construction of a park that is fundamentally different from the one it contracted with [the contractor] to build.”[7]
Read the court decisionRead the full story...Reprinted courtesy of
Ryan M. Charlson, Cole, Scott & Kissane, P.A.Mr. Charlson may be contacted at
ryan.charlson@csklegal.com