Measure Of Damages for Breach of Construction Contract
October 18, 2021 —
David Adelstein - Florida Construction Legal UpdatesHow do you determine damages for a breach of a construction contract? If you are interested in pursing a breach of a construction contract action, this is something you NEED TO KNOW!
The recent Fourth District Court of Appeal’s decision in Cano, Inc. v. Judet, 46 Fla. L. Weekly D2083b (Fla. 4th DCA 201) explains:
Where a contractor breaches a construction contract, and the owner sues for breach of contract and the cost to complete, the measure of damages is the difference between the contract price and the reasonable cost to perform the contract. See Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037, 1039-40 (Fla. 1982). In Grossman, the supreme court adopted subsection 346(1)(a) of the Restatement (First) of Contracts (1932), which it concluded was “designed to restore the injured party to the condition he would have been in if the contract had been performed.” Id. at 1039. In other words, the owner will obtain the benefit of his bargain [and this is known as benefit of the bargain damages]. But where there is a total breach of the contract as opposed to a partial breach, an injured party may elect to treat the contract as void and seek damages that will restore him to the position that he was in prior to entering into the contract or the party may seek the benefit of his bargain. See McCray v. Murray, 423 So. 2d 559, 561 (Fla. 1st DCA 1982).
In Judet, an owner entered into a fixed price contract with a contractor to repair damage from a lightning strike. The contract amount was $300,000 payable in $30,000 installments. A few months after the contractor commenced performance, the owner terminated the contractor because the owner learned the contractor had not obtained required electrical and plumbing permits. At this time, the owner had paid the contractor $90,000. The contractor recorded a $40,000 lien for an amount it claimed it was owed and filed a lawsuit to foreclose its construction lien. The owner counter-sued the contractor to recover a claimed over-payment and a disgorgement of monies for unpermitted work. The owner was NOT claiming benefit of the bargain damages, but rather, damages for the contractor’s total breach “to restore him to the position that he was in prior to entering into the contract.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
General Release of Contractor Upheld Despite Knowledge of Construction Defects
February 27, 2019 —
Garret Murai - California Construction Law BlogAh, the elusive Lepus Cornutus, commonly known as the Jackalope. Rarely seen, we may have one in SI 59 LLC v. Variel Warner Ventures, LLC, Court of Appeals for the Second District, Case No. B285086 (November 15, 2018), an interesting case involving a developer, a contractor, a general release, and Civil Code section 1688.
SI 59 LLC v. Variel Warner Ventures, LLC
In 2005, Variel Warner Ventures, LLC (Variel Warner) entered into a construction contract with Verdugo Management & Investment, Inc. (Verdugo) to construct improvements at an 85 unit apartment complex. Under the terms of the contract, Verdugo agreed to construction the improvements in a good and workmanlike manner in strict compliance with all drawings and specifications and to comply with all laws. It didn’t. The work was defectively flashed, counterflashed, and waterproofed.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
City of Sacramento Approves Kings NBA Financing Plan
May 21, 2014 —
Beverley BevenFlorez-CDJ STAFFSacramento, California’s city council recently approved a financing plan that will enable the construction of the $477 million downtown arena project to move forward, reported KNOE News. Sacramento will now be responsible for a $223 million subsidy, and “the Kings would contribute $254 million to construct the arena and develop surrounding land with a hotel, office tower and shopping.”
“Kings President Chris Granger called it a historic day for the team and Sacramento region, saying the arena would serve as a hub for economic development,” according to KNOE News. “The project would bring 11,000 construction jobs and 4,000 permanent jobs, [Granger] said.”
Read the court decisionRead the full story...Reprinted courtesy of
Retired Judge Claims Asbestos in Courthouse gave him Cancer
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFAmos Saunders, retired Passaic County, New Jersey, Superior Court judge claimed "he got cancer as a result of coming into contact with asbestos at the courthouse during his time on the bench," the New Jersey Law Journal reported.
Saunders alleged "that he was exposed to asbestos throughout his tenure, up to and including an asbestos removal project at the Paterson, N.J., courthouse in the 1980s." The complaint filed, as quoted in the New Jersey Law Journal, stated that "he has been diagnosed with adenocarcinoma 'as a direct and proximate result' of 'inhalation and ingestion of dust particles and fibers' from asbestos products."
According to the complaint, A. H. Environment Inc. was the contractor and Alaimo Group was the consulting engineer.
Read the court decisionRead the full story...Reprinted courtesy of
Microsoft Urges the Construction Industry to Deliver Lifecycle Value
June 25, 2019 —
Aarni Heiskanen - AEC BusinessDigitalization is changing the way that we operate and use buildings. Salla Palos is directing Microsoft towards a future that inspires innovative changes in both the mindset and the business models of AECO industry stakeholders.
Salla Palos moved from Finland to the United States in July 2015 and settled down in Seattle, one of the fastest growing areas in the USA. She was versed in digitalization of construction industry in Finland as well as Europe and sought the opportunity to bring that knowledge into the US market.
As the Director of Emerging Technology and Innovation for Sellen Construction, one of the largest general contractor companies in the Pacific Northwest United States, Salla started developing digital building lifecycle as a strategy to solve number of industry problems.
“I zeroed in on developing digital construction strategy, re-engineering processes, and innovating how emerging technology supports digital construction. My approach was open innovation, pulling the industry along with our own digital transformation. I set up collaboration with both local and international partners to be successful in driving change and transforming AEC,” Salla recalls.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
A New Hope - You Now May Have Coverage for Punitive Damages in Connecticut
February 15, 2018 —
Stella Szantova Giordano – SDV BlogOn December 19, 2017, the Connecticut Supreme Court released its decision in Nationwide Mutual Ins. Co. v. Pasiak. The decision is significant for two reasons: 1) it clarifies the amount of proof an insurer needs to determine whether an exclusion to coverage applies; and 2) it found that where an insurance policy expressly provides coverage for an intentional act such as false imprisonment, common-law punitive damages are also covered.
Underlying action
The underlying action proves that real life is often stranger than fiction. Ms. S worked as an office help for a construction company owned by Mr. P, which operated out of his home. Ms. S was working alone in the home office, when an armed, masked intruder entered the office, tied her hands, gagged and blindfolded her and, pointing a gun to her head, threatened to kill her family if she did not give him the combination to a safe in the home. As this was happening, Mr. P entered the office, unmasked the intruder, and discovered it was his lifelong friend. After Ms. S was untied, she asked to leave, but Mr. P told her to stay. She was not allowed to leave for several hours as Mr. P made her accompany him to an errand. Ms. S sued Mr. P for false imprisonment, among other things. The trial court awarded her compensatory and punitive damages. Insurance coverage for the underlying judgment is at the heart of the Pasiak case.
Read the court decisionRead the full story...Reprinted courtesy of
Stella Szantova Giordano, Saxe Doernberger & Vita, P.C.Ms. Szantova Giordano may be contacted at
ssg@sdvlaw.com
Green Buildings Could Lead to Liabilities
March 28, 2012 —
CDJ STAFFAttempts to build “green,” reducing energy costs and increasing the use of sustainable building materials, may lead to more lawsuits, according to a report issued by the British Columbia Construction Association. The report warned those who were going to build green look into the implications. The report looked at the result of green building practices and requirements adopted in the United States.
The report warns that “the use of novel, less harmful building material or new construction techniques may give rise to liability due to: contractor inexperience with installation; lack of long-term evaluation of green materials; lack of understanding of how new building materials may impact existing traditional building systems; or warranties provided unintentionally about the durability or effectiveness of unproven materials or techniques.”
Manley McLachlan, president of the BCAA noted that they are aware of “legal action around the performance of the buildings,” noting that while fast-growing trees help toward LEED certification, their wood is more prone to mold. He also felt that low-VOC paints needed more testing to prove their durability as exterior finishes.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Reinforces COVID Guidelines for the Workplace
March 08, 2021 —
Joseph P. Paranac Jr. & Robert M. Pettigrew - White and Williams LLPOn January 29, 2021, the Occupational Safety and Health Administration (OSHA) updated its existing guidelines concerning coronavirus protection measures for the workplace. Focusing on the implementation of workplace protection programs, OSHA’s updated advisory guidance seeks to reinforce the benefits of implementing workplace policies along with the critical role employees have in combatting workplace spread. These guidelines are “intended to inform employers and workers in most workplace settings outside of healthcare to help them identify risks of being exposed to and/or contracting COVID-19 at work and to help them determine appropriate control measures to implement.”
OSHA maintains that the implementation of a strong coronavirus protection program is the most effective way to combat virus spread in the workplace. OSHA has identified 16 categories or elements that an effective coronavirus protection program should address, which include appointing a workplace coordinator and conducting a workplace specific hazard assessment. This assessment should begin by identifying risks in the workplace and developing control measures to mitigate them. The guidance stresses that workers are often the most valuable source of information relating to conditions that contribute to the risk of spread.
Reprinted courtesy of
Joseph P. Paranac Jr., White and Williams LLP and
Robert M. Pettigrew, White and Williams LLP
Mr. Paranac may be contacted at paranacj@whiteandwilliams.com
Mr. Pettigrew may be contacted at pettigrewr@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of