Courthouse Reporter Series: Louisiana Supreme Court Holds Architect Has No Duty to Safeguard Third Parties Against Injury, Regardless of Knowledge of Dangerous Conditions on the Project
July 31, 2024 —
Stu Richeson - The Dispute ResolverIn Bonilla v. Verges Rome Architects, 2023-00928 (La. 3/22/24); 382 So.3d 62, the Louisiana Supreme Court held because the terms of the agreement between the architect and the public owner did not give the architect responsibility for the means and methods of construction or for safety on the project, the architect did not have a duty to safeguard third parties against injury, regardless of whether the architect may have had knowledge of dangerous conditions on the project.
In Bonilla, the City of New Orleans entered into a contract for the renovation of a building owned by the city. The city also entered into an agreement with Verges Rome Architects (“VRA”) to serve as the project architect. The general contractor on the project subcontracted the demolition work to Meza Services, Inc. (“Meza”).
An employee of Meza was injured while attempting to demolish a “vault” on the project. The vault was a ten-foot by ten-foot cinderblock room with a nine-foot-high concrete slab ceiling located on the second floor of the building. The walls of the vault had been partially demolished when one of the employees of Meza was directed by his supervisor to stand on the ceiling of the vault with a jackhammer to continue the demolition. Shortly after beginning the task, the vault structure collapsed and caused the employee to suffer significant injury.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Enforceability Of Subcontract “Pay-When-Paid” Provisions – An Important Update
June 15, 2020 —
Patrick McNamara - Porter Law GroupA California Court of Appeals opinion published earlier this month brings a change to payment bond claims brought by unpaid subcontractors and suppliers. The decision (Crosno Construction, Inc. v. Travelers Casualty and Surety Company of America) places limitations on a payment bond surety’s ability to rely on subcontract “pay-when-paid” language, stating that a payment provision typically found in subcontracts is contrary to the “reasonable time” statutory requirement and will not be enforced. This represents a major shift in California construction payment bond claim rights.
Plaintiff Crosno Construction, Inc. (“Crosno) was a subcontractor to general contractor Clark Brothers (“Clark”), who was principal on a public works payment bond issued by Travelers. The owner was a public agency district (“District.”) Crosno had completed most of its subcontract work when a dispute between District and Clark arose, causing the project to stop. Crosno then sought payment through a payment bond claim against Travelers. Travelers denied the claim, relying on the subcontract’s payment provisions and asserting the defense that it had no obligation to pay on the bond claim because the litigation between Clark and the District had not yet reached its conclusion.
Subcontract. The subcontract between Clark and Crosno contained a “pay-when-paid” provision stating that Clark would pay Crosno within a reasonable time after receiving payment from the District. In defining “a reasonable time,” the subcontract language provided that the time for payment “in no event shall be less than the time [Clark] and [Crosno] require to pursue to conclusion their legal remedies against [District] or other responsible party to obtain payment.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Mitsui Fudosan Said to Consider Rebuilding Tilted Apartments
October 28, 2015 —
Katsuyo Kuwako – BloombergMitsui Fudosan Co., Japan’s biggest developer, is considering rebuilding an apartment complex in Yokohama after one of the four buildings started to tilt, according to a person familiar with the situation.
Kiyotaka Fujibayashi, president and chief executive officer of Mitsui Fudosan Residential Co., on Thursday explained the plans to residents, according to the person, who asked not to be named because the information is private. Another option the company is studying is buying back the apartments from the residents at a price higher than what they had paid, the person said. The project was sold in 2006.
Mitsui Fudosan is the latest developer to come under scrutiny for defects at residential projects in the Tokyo area. Mitsubishi Estate Co., Japan’s biggest developer by market value, said last year it would rebuild a residential complex in the upscale Aoyama neighborhood after finding faults. Also last year, Sekisui House Ltd. said it would reconstruct a residential complex that was being built by Taisei Corp. after finding some columns were missing reinforcing metals.
Read the court decisionRead the full story...Reprinted courtesy of
Katsuyo Kuwako, Bloomberg
Environmental Roundup – May 2019
July 09, 2019 —
Anthony B. Cavender - Gravel2GavelFederal Courts of Appeal
Dam Claims Collapse
On May 7, 2019, the U.S. Court of Appeals for the Eleventh Circuit decided the case of Navelski, et al. v. International Paper Company. After a major storm, a dam constructed by International Paper to serve the operations of its local paper mill, was breached, releasing millions of gallons of water into a nearby creek resulting in the flooding of many homes located downstream from the creek. IP was sued by the homeowners in a class action, alleging negligence and strict liability for conducting an abnormally dangerous activity. The trial court dismissed the strict liability claim, and the jury found IP was not negligent in the operation of the dam. On appeal, the court upheld the jury verdict, agreeing that the verdict was supported by the evidence heard by the jury. The appeals court also agreed that the strict liability claim was properly dismissed as a matter of law because the operation of this dam was not an abnormally dangerous activity under Florida law. The plaintiffs had also argued that the jury should not have been advised that the home county, Escambia County, has applied for a FEMA grant which apparently made the case that some of the downstream homes were naturally prone to flooding. A redacted version of the application was allowed to be shown to the jury, but the appeals court held that the plaintiffs had not demonstrated that the court ruling was prejudicial.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Looming Housing Crisis and Limited Government Relief—An Examination of the CDC Eviction Moratorium Two Months In
December 14, 2020 —
Zachary Kessler - Gravel2GavelMonths after the Centers for Disease Control and Prevention (CDC) issued a nationwide eviction moratorium using its emergency pandemic powers under the Public Health Service Act, the efficacy of this unprecedented measure remains unclear. While the Order ostensibly protects tenants facing homelessness or housing insecurity due to the financial impacts of the COVID-19 pandemic through the end of 2020, legal challenges have been initiated in Ohio and Georgia, with additional lawsuits appearing likely. Further, even barring legal challenges, courts have not handled these cases in a uniform manner. With lawmakers unable to reach any stimulus or COVID-19 relief agreement before the election, the CDC Order appears likely to remain the only federal eviction moratorium through its expiration on December 31, 2020.
Since the Order’s enactment, the CDC has since released new guidance, answering some of the open questions not covered by the initial Order. This guidance, while non-binding, is largely more favorable to landlords and property management companies than the initial text of the Order, as it provides that landlords are not required to make tenants aware of the Order’s protections and may challenge the truthfulness of the tenants’ declarations in any state or municipal court. The guidance also clarified the potential criminal penalties for violating the Order and the criminal penalties for perjury for bad faith submissions of the requisite declaration by tenants.
Read the court decisionRead the full story...Reprinted courtesy of
Zachary Kessler, PillsburyMr. Kessler may be contacted at
zachary.kessler@pillsburylaw.com
Can Your Small Business Afford to Risk the Imminent Threat of a Cyber Incident?
November 28, 2018 —
Jeffrey M. Dennis & Heather H. Whitehead – Newmeyer & Dillion LLPCybersecurity incidents are occurring on a daily basis and at an increasingly growing rate. Yet, many small businesses still have not obtained adequate (or any) cyber insurance to address these risks and the costly impacts to the business that will result. In a recent study completed by the Insurance Information Institute1, only about a third of all small businesses polled responded that they have cyber insurance in place, with 70% of respondents replying that they have no plans to purchase a cyber insurance policy in the next 12 months. Most of the businesses indicated that they do not believe they have any need for cyber insurance, yet almost half of those same companies stated they are unprepared to handle cyber threats. A main reason for not purchasing cyber insurance was a lack of understanding about this type of insurance and coverages available.
The Risks for Small Businesses
These statistics are alarming considering that the average cost of a cyber-related loss for a small business has increased 250% in the past two years, and now totals $188,400. In determining whether insurance coverage should be purchased, companies typically assess the perceived risks to the company, the likelihood of such risks occurring, as well as any costs or expenses that may result. For example, most companies regularly obtain a property policy to cover a fire or other casualty that may damage its business location even though such an event is unlikely or unexpected. Yet, cyber incidents are just as likely, if not more likely to occur, and the impacts to a company in the event of an incident are far worse. Many incidents result in a complete suspension of the daily operations of the company for several days or longer.
In addition to financial loss, companies may face the following as a result of a cyber incident:
- Theft, breach or loss of information and data;
- Damage to the company's reputation, brand or image; and
- Regulatory, governance and legal issues.
- How Cyber Insurance can Help
Cyber insurance policies can be obtained to address the losses related to a data breach and may include costs for investigating a breach, notifying people affected by a breach of personally identifiable information, managing the potential damage to reputation and other crisis-management expenses, recovering lost or corrupted data, and related legal expenses. More importantly, well-drafted policies can afford coverage for business interruption losses; i.e. those expenses and lost revenue resulting from a breached system and a company's inability to continue its usual operations. Coverage may also be obtained for "cyber extortion", which covers costs resulting from an extortion event such as ransomware or fraudulent wire transfers.
It is important to keep in mind that cyber insurance is only one component to consider when developing and implementing an overall risk management strategy to prevent cyber incidents. However, taking into account the exposure to a company if and when a cyber incident occurs, it is highly advisable to have this coverage in place.
1Insurance Information Institute, "Small business, big risk: Lack of cyber insurance is a serious threat," October 2018.
Jeff Dennis is the head of the firm's Privacy & Data Security practice. Jeff works with the firm's clients on cyber-related issues, including contractual and insurance opportunities to lessen their risk. For more information on how Jeff can help, contact him at jeff.dennis@ndlf.com.
Heather Whitehead is a Partner in the firm's Privacy & Data Security practice. Heather also practices insurance coverage matters for commercial, retail, industrial, mixed-use, multi-family and residential projects. For more information on how Heather can help, contact her at heather.whitehead@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Motion for Summary Judgment to Dispose of Hail Damage Claim Fails
November 25, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer's motion for summary judgment seeking to dismiss the insured's complaint requesting coverage for hail damage and a claim for bad faith. Rodriquez v. State Farm Lloyds, 2024 U.S. Dist. LEXIS 160007 (W.D. Tex. Sept. 5, 2024).
Mr. Rodriquez sought coverage under his homeowners policy after a hail and wind storm damaged his roof. After inspection, State Farm agreed that some minimal loss caused by hail was covered, but determined that the covered loss was less than the amount of the deductible. State Farm further determined that any hail damage to the roof was excluded by an endorsement, Exclusion of Cosmetic Loss to Metal Roof Coverings Caused by Hail. State Farm also determined that some damage was caused by previous faulty workmanship or wear and tear, both of which were excluded from coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
GSA Releases Updated Standards to Accelerate Federal Buildings Toward Zero Emissions
August 12, 2024 —
The U.S. General Services AdministrationWASHINGTON — The U.S. General Services Administration (GSA) is advancing progress toward the Biden-Harris Administration's federal sustainability goals by releasing updated standards for federal buildings. P100 Facilities Standards for the Public Buildings Service establish mandatory design and construction standards and performance criteria for 300,000 federal buildings nationwide. The updated standards will help advance the adoption of cleaner, more efficient technologies for buildings; lead the way towards realizing the goals of the Federal Sustainability Plan to achieve net-zero emissions from all federal buildings by 2045; and promote the use of American-made, low carbon construction materials.
P100 requires that facilities adopt advanced energy conservation strategies and eliminate on-site fossil fuel use, directives that align with federal sustainability goals and will accelerate the transition to a clean energy economy. The industry-leading standard calls for grid-interactive efficient buildings, leverages innovative technologies through GSA's Green Proving Ground, requires the use of low-embodied carbon materials, and directs potable water reuse. These comprehensive measures ensure that new and renovated federal facilities achieve peak performance while minimizing environmental impact.
The 2024 P100 establishes exceptional benchmarks for:
- Electrification: New standards for building equipment and systems to be powered by clean energy sources.
- Embodied Carbon: Requirement to utilize low-embodied carbon materials, including salvaged, reused, regenerative, and biomimetic options.
- Energy Efficiency: Enhanced building envelope performance to minimize energy loss and improve overall efficiency.
- Grid-Interactive Efficient Buildings: New measures to support a more resilient, responsive grid.
- Water Reuse: Mandating that buildings have a 15% potable water reuse rate.
- Construction Decarbonization: Ground breaking new low-carbon methods for constructing federal buildings including clean energy operations, material salvage, and offsite assemblage.
- Labor Practices: New standards protecting workers from unfair or unsafe labor practices, ensuring supply chains are free from child and forced labor and that workers are protected from the impacts of extreme heat.
P100 is updated and published every three years. For more detailed information on the 2024 P100 and other GSA initiatives, visit www.gsa.gov/p100.
Read the court decisionRead the full story...Reprinted courtesy of