Miller Act Payment Bond Surety Bound to Arbitration Award
December 29, 2020 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting case binding a Miller Act payment bond surety to an arbitration award against its prime contractor (bond principal) that it received sufficient notice of. Notice is the operative word. The surety could have participated in the arbitration, elected not to, and when its prime contractor (bond principal) lost the arbitration, it was NOT given another bite out of the apple to litigate facts already been decided.
In BRC Uluslararasi Taahut VE Ticaret A.S. v. Lexon Ins. Co., 2020 WL 6801933 (D. Maryland 2020), a prime contractor was hired by the federal government to make security upgrades and interior renovations to a United States embassy in the Czech Republic. The prime contractor hired a subcontractor to perform all of the installed contract work. The prime contractor terminated the subcontractor for default during the course of construction.
The subcontractor demanded arbitration in accordance with the subcontract claiming it was wrongfully terminated. The subcontractor also filed a lawsuit asserting a Miller Act payment bond claim against the prime contractor’s surety (as well as a breach of contract action against the prime contractor). The subcontractor made clear it intended to pursue its claims in arbitration and hold the payment bond surety jointly and severally liable. The parties agreed to stay the lawsuit since the facts were identical to those being arbitrated. The arbitration went forward and an award was entered in favor of the subcontractor and against the prime contractor for approximately $2.3 Million.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Supreme Court Finds Vertical Exhaustion Applies to First-Level Excess Policies
August 26, 2024 —
Tred R. Eyerly - Insurance Law HawaiiAddressing issues left open in its seminal decision in Montrose, the California Supreme Court found that the language in the first-level excess policies meant that the insured could access the policies upon exhaustion of the directly underlying policies purchased for the same policy period. Truck Ins. Exchange v. Kaiser Cement & Gypsum Corp., 2024 Cal. LEXIS 3271 (Cal. June 17, 2024).
From 1944 through the 1970's, Kaiser manufactured asbestos-containing products at numerous different facilities. By 2004, more than 24,000 claimants had filed product liability claims against Kaiser alleging that they had suffered bodily injury as a result of exposure to Kaiser's asbestos products. Kaiser tendered these claims to Truck, one of several primary insurers that had issued CGL policies to Kaiser.
In 2001, Truck initiated this coverage action to determine its indemnity and defense obligations to Kaiser. Truck later amended its complaint to add a cause of action for contribution against several of Kaiser's excess insurers. The issue presently before the court was whether Truck was entitled to contribution from various coinsurers that issued first-level excess policies to Kaiser during the period in question.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Read Her Lips: “No New Buildings”
November 18, 2011 —
CDJ STAFFMartha Johnson, the head of the General Services Administration, has said that her agency will not be building any new buildings in the near future. Among other duties, the GSA is responsible for the building, renovating, and leasing of federal office space. The White House had proposed $840 million in new construction, the Senate only $56 million. The House did not appropriate any money for the agency to use for new construction.
In addition to cutbacks on new buildings, Congress is suggesting only $280 million in repairs of existing government buildings. In order to cut back, the GSA has dropped plans to renovate their own offices in favor of renovations at the Department of Homeland Security and the Food and Drug Administration.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Cameron Pledges to Double Starter Homes to Boost Supply
March 05, 2015 —
Svenja O’Donnell – Bloomberg(Bloomberg) -- Prime Minister David Cameron pledged to double the number of homes built for first-time buyers by the end of the next parliamentary term in a bid to tackle Britain’s housing shortage.
In a speech in Colchester, Essex, on Monday setting out the final part of his Tory party’s six-point campaign platform for the May 7 election, Cameron said 200,000 properties will be built by 2020 under his starter-homes plan. Prices of the homes, only available to first-time buyers under the age of 40, will be capped at 450,000 pounds ($692,000) in London and 250,000 pounds outside the capital. Reduced planning constraints will make it easier for developers to cut building costs, allowing the homes to be sold at a 20 percent discount.
Read the court decisionRead the full story...Reprinted courtesy of
Svenja O’Donnell, BloombergMs. O’Donnell may be contacted at
sodonnell@bloomberg.net
Tips for Contractors Who Want to Help Rebuild After the California Wildfires
November 02, 2017 —
Garret Murai - California Construction Law BlogI received a call from one of my contractor clients this past week to see what he could do to help those affected by California’s North Bay fires.
The North Bay fires are the deadliest and most destructive wildfires in California’s history. To date, the fires have claimed 42 lives, burned more than 200,000 acres of land, destroyed an estimated 8,400 structures and likely damaged tens of thousands more. By comparison, the state’s second most deadly wildfire, the Oakland Hills fire of 1991, claimed the lives of 25 people, burned 1,600 acres of land, and destroyed 2,900 structures. Rebuilding costs for the North Bay fires, according to the California Insurance Commissioner, are expected to top $1 billion.
For those with insurance, insurance experts say that the rebuilding process can take two years or more for those whose homes and businesses were destroyed. For those whose homes and businesses were fortunate enough only to be damaged, rebuilding efforts are already underway.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
The Choice Is Yours – Or Is It? Anti-Choice-of-Laws Statutes Applicable to Construction Contracts
October 03, 2022 —
Tiffany Raush & Tanya McGill - ConsensusDocsDuring contract negotiations and review, the parties make choices about what risks they are willing to accept and at what cost. But one often overlooked choice—the choice of law applicable to the contract—can undermine carefully negotiated construction contracts and expose contractors to risks they never intended to accept.
Choice-of-law provisions are standard provisions in most contracts. These provisions allow the parties to the contract to decide which state’s laws will apply to their contract. Often, choice-of-law in the construction contract is the law of the state where the project is located and there will be no issue. But, if the project is located in an unfamiliar, the owner or prime contractor may prefer the laws of the state where the owner or prime contractor is primarily located over the laws of the state where the project is located.
Generally, most states will enforce the parties’ choice of law in a contract. But that may not be the case for construction contracts. States like Texas, California, New York, Florida, Louisiana, and others may prohibit parties from agreeing to the application of another state’s law for construction projects in their states.
Reprinted courtesy of
Tiffany Raush, Jones Walker LLP (ConsensusDocs) and Tanya McGill, University of Mississippi School of Law Student, 2023 Graduate (ConsensusDocs)
Ms. Raush may be contacted at traush@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
China Construction Bank Sued in US Over Reinsurance Fraud Losses
June 21, 2024 —
Robert Burnson - BloombergChina Construction Bank Corp., the nation’s third-largest commercial lender, was accused in a US lawsuit of enabling a massive fraud in the reinsurance industry that left companies with “monumental losses” and sinking stock prices.
The bank allowed employees to conspire with Israeli insurance startup Vesttoo Ltd. to sell reinsurance policies that weren’t real, according to a complaint filed late Thursday by the Porch Group in Manhattan federal court.
Vesttoo filed for Chapter 11 bankruptcy in August after it was accused of using some $2 billion of fraudulent letters of credit.
The Porch Group said that its unit Homeowners of America Insurance Co. lost tens of millions of dollars when its purported $300 million letter of credit proved worthless.
“Not only did HOA incur colossal losses, but news of its exposure to the fraud perpetrated by Vesttoo and CCB shocked the market and imposed severe losses on Porch Group’s shareholders as its stock price plummeted,” according to the suit.
Read the court decisionRead the full story...Reprinted courtesy of
Robert Burnson, Bloomberg
Illinois Supreme Court Finds Construction Defect Claim Triggers Initial Grant of Coverage
February 26, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Illinois Supreme Court found that the underlying allegations addressing construction defects were sufficient to establish "property damage" caused by an "occurrence."Acuity v. M/I Homes of Chicago, LLC, 2023 Ill. LEXIS 1019 (Ill. Nov. 30, 2023).
M/I Homes was the general contractor for a residential townhome development. The Owners' Association sued for breach of conract and breach of the implied warranty of habitability against M/I Homes. The complaint alleged that M/I Homes' subcontractors caused construction defects by using defective materials, conducting faulty workmanship and failing to comply with applicable building codes. The defects included leakage and uncontrolled water with moisture in locations in the buildings where it was not intended or expected. The Association further alleged that M/I Homes did not intend to cause the construction defects nor did it expect or intend the resulting property damage, such as damage to other building materials. The complaint further alleged that M/I Homes did not perform any of the construction work and that the subconractors performed all the work on its behalf.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at