South Carolina Clarifies the Accrual Date for Its Statute of Repose
March 18, 2019 —
William L. Doerler - The Subrogation StrategistIn Lawrence v. General Panel Corp., 2019 S.C. LEXIS 1, No. 27856 (S.C. Jan. 1, 2019), the Supreme Court of South Carolina answered a certified question related to South Carolina’s statute of repose, S.C. Code § 15-3-640,[1] to wit, whether the date of “substantial completion of the improvement” is always measured from the date on which the certificate of occupancy is issued. The court held that a 2005 amendment to § 15-3-640 did not change South Carolina law with respect to the date of substantial completion. Thus, under the revised version of § 15-3-640, “the statute of repose begins to run at the latest on the date of the certificate of occupancy, even if there is ongoing work on any particular part of the project.” A brief review of prior case law may assist with understanding the court’s ruling in Lawrence.
In Ocean Winds Corp. of Johns Island v. Lane, 556 S.E.2d 377 (S.C. 2001), the Supreme Court of South Carolina addressed the question of whether § 15-3-640 ran from substantial completion of the installation of the windows at issue or on substantial completion of the building as a whole. Citing § 15-3-630(b),[2] the court found that the windows “were ‘a specified area or portion’ of the larger condominium project” and, upon their incorporation into the larger project they could be used for the purpose for which they were intended. Thus, the court held that “the statute of repose began running when installation of the windows was complete.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and WilliamsMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Can an Architect, Hired by an Owner, Be Sued by the General Contractor?
September 10, 2014 —
Craig Martin – Construction Contractor AdvisorAs is often the answer in this blog, maybe. And, it will likely depend on which state’s law is applied. Over the last few weeks, courts around the country have reached differing conclusions on whether a general contractor may sue an architect that it did not hire.
Here’s the situation: The owner hires an architect to draft plans for a project. The project is then put out for bid and the owner hires a general contractor for the work. The general contractor and architect do not enter into a contract with each other.
If, during construction, the general contractor finds fault with the plans, it may seek Request for Information and Change Orders, to shore up the perceived problems with the plans. Ultimately, the general contractor may sue the architect to recover damages it suffered in completing the project.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Builder’s Be Wary of Insurance Policies that Provide No Coverage for Building: Mt. Hawley Ins. Co v. Creek Side at Parker HOA
July 31, 2013 —
Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLCOn the heels of a recent order regarding coverage under a Comprehensive General Insurance policy issued by Mt. Hawley Insurance Company (“Mt. Hawley”), builders should be very wary of CGL policies providing no coverage for property damage.
On January 8, 2013, District Court Judge R. Brooke Jackson granted a motion for declaratory judgment filed by Mt. Hawley. The order states that the subject insurance policies issued by Mt. Hawley to Mountain View Homes II, LLC (“MV Homes”), the builder developer of the Creek Side at Parker development (the “Project”), did not provide coverage for any of the work performed by MV Homes or its subcontractors on the Project.
MV Homes originally began construction on the Project in 2002 and completed construction in 2005. MV Homes was insured by National Fire and Marine Insurance Company (“National Fire”) and Mt. Hawley. In December 2008, Creek Side at Parker Homeowners Association, Inc. (“the HOA”) served notice on MV Homes. The HOA then instituted a construction defect lawsuit on June 1, 2009 against MV Homes and others. MV Homes initially demanded a defense and indemnity from National Fire, which provided a defense. Then, after two years, MV Homes demanded a defense and indemnity from Mt. Hawley in July 2011. Mt. Hawley denied coverage and did not provide a defense. The case was settled soon after, and National Fire reserved or assigned claims against Mt. Hawley.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at
Iandiorio@hhmrlaw.com
Condo Buyers Seek to Void Sale over Construction Defect Lawsuit
November 07, 2012 —
CDJ STAFFA Michigan couple seeks to void their purchase of a condo in Texas after discovering that the complex was undergoing a construction defect lawsuit. ABQ Journal reports that Charles M. Lea and Olga Y. Ziabrikova said that they would not have purchased the condo if they had known the association was already alleging construction defects. The condo association discovered the defects “by at least late 2010,” according to the suit. The couple bought their condo in August 2011 and heard of the defects only in March 2012.
The couple notes that no one involved with the sale informed them of the construction defect complaints. The community association’s lawsuit states that problems have lead to $2.5 million in damages. The developer, Vegas Verde Condo Partners, have filed a general denial of the construction problems.
Read the court decisionRead the full story...Reprinted courtesy of
California Precludes Surety from Asserting Pay-When-Paid Provision as Defense to Payment Bond Claim
December 21, 2020 —
Nicholas Korst - Ahlers Cressman & Sleight PLLCIn a recent case in California, the Court of Appeals held that a surety who had issued a public works payment bond cannot rely on the “Pay-When-Paid” provision in the subcontract as a defense against the subcontractor’s claim against the payment bond.[1] The case was a public works project in Kern County, CA where the North Edwards Water District (the “District”) hired Clark Bros., Inc. (“Clark”) as the general contractor to build an arsenic removal water treatment plant. Clark hired subcontractor Crosno Construction (“Crosno”) to build and coat two steel reservoir tanks. The subcontract included the following “pay-when-paid” provision, which provided a definition of “reasonable time”:
If the Owner or other responsible party delays in making any payment to the Contractor from which payment to Subcontractor is made, Contractor and its sureties shall have a reasonable time to make payment. “Reasonable time” shall be determined according to the relevant circumstances, but in no event shall be less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against the Owner or other responsible party to obtain payment, including (but not limited to) mechanics lien remedies. (emphasis added).
Read the court decisionRead the full story...Reprinted courtesy of
Nick Korst, Ahlers Cressman & Sleight PLLCMr. Korst may be contacted at
nicholas.korst@acslawyers.com
Defining Catastrophic Injury Claims
December 16, 2019 —
Bremer Whyte Brown & O'Meara LLPHow do we define circumstances and injuries that go beyond a typical claim and severely impact a person’s life? How do we characterize the types of claims where an individual’s enjoyment of life is affected in an extraordinary manner? Typically, attorneys refer to these types of cases as “catastrophic injury” claims. These are the type of personal injury claims where the health of an individual has been so seriously impacted that their life has been irreparably altered. Defining these claims legally is somewhat murky and case law has done little to provide attorneys with a specific definition of the term. However, a recent Workers Compensation Appeals Board ruling attempted to list factors in order to establish a catastrophic injury claim. These include:
- An intensity and seriousness of treatment received for an injury;
- The ultimate outcome when a person’s physical injury is permanent and stationary;
- Whether the severity of the physical injury impacts the person’s ability to perform daily activities;
- Whether the physical injury is closely analogous to one of the injuries specified in various statutes, including loss of a limb, paralysis, severe burns, or a severe head injury; and
- If the physical injury is incurable or progressive. Wilson v. State of California CAL Fire (5/10/19) 2019 Cal.Wrk.Comp. LEXIS 29.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP
Fifth Circuit Reverses Summary Judgment Award to Insurer on Hurricane Damage Claim
December 18, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Fifth Circuit reversed the district court's grant of summary judgment to the insurer on a property damage claim arising from Hurricane Harvey. Advanced Indicator and Manufacturing, Inc. v. Acadia Ins. Co., 50 F.4th 469 (2022).
After Hurricane Harvey struck southern Texas in 2017, Advanced submitted a claim to Acadia for damage to its building that it claimed was caused by the hurricane's winds. Acadia sent an adjuster, Nick Warren, as well as an engineer, Jason Watson. Watson determined that pre-existing conditions - including ongoing leaks from deterioration and poor workmanship - caused the damage, rather than winds from Hurricane Harvey. Warren adopted these conclusions in his recommendations to Acadia. Acadia denied Advanced's claim based on these reports.
Advanced sued Acadia, alleging breach of contract and bad faith. Advanced filed a motion to remand to state court which was denied. Acadia moved for summary judgment arguing that it did not breach the policy and that Advanced could not segregate any damages caused by hurricane from pre-existing damage. The district court granted Acadia's motion, finding that Acadia's denial of Advanced's claim was based on "extensive consideration of the evidence." Further, Advanced failed to carry its burden of showing that covered and non-covered damages could be segregated as required by Texas's concurrent causation doctrine. Finally, the bad faith claim was dismissed because there was no breach of contract.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Caltrans Hiring of Inexperienced Chinese Builder for Bay Bridge Expansion Questioned
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFThe construction of the new eastern span of San Francisco’s bay bridge has been criticized for the $6.5 billion cost, welding crack violations, and alleged cover ups by Caltrans. The Sacramento Bee reported that the company Shanghai Zhenhua Port Machinery Co. Ltd. (ZPMC) “had never built a bridge.” In fact, ZPMC “was a manufacturer of giant cranes for container ports.”
How then did ZPMC manage to obtain the contract? The Sacramento Bee stated that the company “had established a reputation as fast and cost-effective, offering savings of about $250 million compared to the competing bidder.” The project was already “years behind schedule and billions of dollars over budget by political squabbles and construction delays” and there were some fears that the “old bridge might not survive a major quake.”
Caltrans was told by an outside expert that ZPMC was a “high risk,” however, the company received a “contingent pass.” Sacramento Bee reported that an audit showed “ZPMC didn’t have enough qualified welders or inspectors…and routinely welded in the rain, a basic error that often causes defects.” Regardless, Caltrans signed off on the project.
“In August 2007, Caltrans auditors approved ZPMC outright, although the firm still lacked adequate quality control, even for ‘fracture critical’ materials,” the Sacramento Bee reported.
During the California Senate committee hearing in January, Doug Coe, a senior Caltrans engineer, said “’The race for time’ created overwhelming pressure to keep moving as planned….But there’s no excuse for building something defective like that because we are in a race for time.”
Read the court decisionRead the full story...Reprinted courtesy of