Stormy Seas Ahead: 5th Circuit to Review Whether Maritime Law Applies to Offshore Service Contract
July 26, 2017 —
Richard W. Brown & Afua S. Akoto - Saxe Doernberger & Vita, P.C.Earlier this year, the 5th Circuit applied the Davis factors to determine the validity of an indemnity clause in a Master Services Contract. In Larry Doiron Inc. et al., v. Specialty Rental Tool & Supply LLP et al., the court affirmed the notion that if a contract provides services on navigable waters aboard a vessel, a maritime contract exists, even if the contract calls for incidental or insubstantial work unrelated to the use of a vessel. With this decision, plaintiffs were granted indemnification for a crane injury and all was well on the open seas.
The 5th Circuit made waves, however, on July 7, 2017, when it agreed to rehear the case en banc. In its petition for rehearing, defendant STS argued that: (1) the original opinion conflicted with Supreme Court precedent by applying tort law principles to a contract case; (2) the court misapplied the Davis factors and the decision was contrary to Davis because the historical treatment of specialty well service work has been established as non-maritime; (3) the court needed to address whether a contract is subject to maritime or land-based law in the context of offshore mineral exploration.
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Afua S. Akoto, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Ms. Akoto may be contacted at asa@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Angels Among Us
June 21, 2024 —
Maggie Murphy - Construction ExecutiveIn the early morning hours of March 26, 2024, an outbound cargo ship in the Port of Baltimore unexpectedly lost power as it churned toward the Francis Scott Key Bridge. Authorities had just minutes to stop vehicular traffic before the massive vessel—985 feet long and 157 feet wide, nearly as tall as the Eiffel Tower if stood on end—crashed headlong into one of the bridge’s support piers. Quick-acting dispatchers were able to stop the flow of traffic in time, but overnight work crews filling potholes on the bridge didn’t have enough warning. Six workers lost their lives when the bridge collapsed.
On top of bringing immense grief, construction fatalities can be financially devastating to the surviving families. Enter Construction Angels, a nonprofit that provides financial assistance, grief counseling and scholarships to families of fallen construction workers. When founder Kristi Ronyak first heard news of the Key Bridge collapse, she immediately jumped into action. “We started getting calls just hours after the crash,” Ronyak says. “When I first heard the news, my heart sank, and I just started crying.
Reprinted courtesy of
Maggie Murphy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mitigating Mold Exposure in Manufacturing and Multifamily Buildings
July 31, 2024 —
Laura Champagne - Construction ExecutiveAs hurricanes season and summer storms approach, more apartment complexes, commercial and industrial properties, and public buildings are at risk of leaking and flooding. Water-saturated structures are prime breeding grounds for mold, but there are ways to prevent, detect and remove it before it becomes a serious and costly issue—for buildings and building residents alike. Being proactive limits an owner’s exposure to the liability of debilitating health effects and structural safety concerns.
Mold requires three things to grow: water, food and humidity. Water will stealthily penetrate small porous surfaces of any building material, such as drywall, plaster, wood, concrete or even fabrics. These materials serve as a food source to quickly produce more fungus. Common sources of undetected water flow include foundation problems, poorly installed windows, roof malfunctions, gutter clogs, storm damage, leaky pipes, improper drainage, HVAC issues, faulty appliances, bathroom vent issues and wet building materials. Mold loves humidity and thrives in dark, warm environments, such as attics, basements, lofts, building corners and bathrooms.
Reprinted courtesy of
Laura Champagne, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Best Lawyers® Recognizes 37 White And Williams Lawyers
September 26, 2022 —
White and Williams LLPThirty-two White and Williams lawyers were recognized in The Best Lawyers in America© 2023. Inclusion in Best Lawyers® is based entirely on peer-review. The methodology is designed to capture, as accurately as possible, the consensus opinion of leading lawyers about the professional abilities of their colleagues within the same geographical area and legal practice area. Best Lawyers® employs a sophisticated, conscientious, rational, and transparent survey process designed to elicit meaningful and substantive evaluations of quality legal services.
In addition, eight lawyers were recognized as "Ones to Watch” by Best Lawyers®. This recognition is given to attorneys who are earlier in their careers for outstanding professional excellence in private practice in the United States.
The firm is also pleased to announce Best Lawyers®
has recognized four White and Williams lawyers as "Lawyer of the Year." Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Encinitas Office Obtains Complete Defense Verdict Including Attorney Fees and Costs After Ten Day Construction Arbitration
May 23, 2022 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Vik Nagpal and Associate Attorney Tim McNulty of the Encinitas office recently obtained a substantial victory on behalf of BWB&O’s client after a 10-day binding construction arbitration before a three-arbitrator panel of the American Arbitration Association.
BWB&O’s client was sued by the Owner of a commercial office building related to a multimillion-dollar tenant improvement project in San Diego. The Owner asserted construction defect damages, delay damages, architectural negligence, fraudulent billing practices and consequential damages of $3.6 million dollars. BWB&O’s client claimed breach of contract damages against the owner for failure to pay invoices.
The Owner who had substantial financial resources and a personal spite against the general contractor, unreasonably pursued the case with an extensive team of lawyers and experts. At an earlier full-day mediation, the owner rejected a reasonable settlement offer which included a settlement payment to the Owner and the client’s agreement to dismiss their affirmative claim for damages.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
A Guide to Evaluating Snow & Ice Cases
December 13, 2021 —
Lewis BrisboisNew York, N.Y. (November 9, 2021) - As the winter season nears, defendant property owners are reminded that New York law imposes liability for sidewalk accidents resulting from slip and falls on snow and ice. Within the City of New York, Administrative Code § 7-210 imposes liability on the owners of real property (other than single-family dwellings) to maintain an abutting sidewalk in a reasonably safe condition, which includes the removal of snow and ice.
Some of the most important issues in this area of the law were recently reaffirmed by New York’s Appellate Division in Zamora v. David Caccavo, LLC, 190 A.D.3d 895 (2d Dept. 2021). In particular, that the Court of Appeals made clear in 2019 that the statutory non-delegable duty to remove snow and ice from sidewalks extends even to out-of-possession landowners, who, although they may shift the work of maintaining the sidewalk to another, "cannot shift the duty, nor exposure and liability for injuries caused by negligent maintenance, imposed under [Administrative Code §] 7-210." Xiang Fu He v. Troon Mgt., Inc., 34 N.Y.3d 167, 174 (2019). In other words, even if the defendant leases the property to a tenant who is obligated under the lease to maintain the property in every way, including snow and ice on sidewalks, the defendant cannot escape liability by claiming the tenant is solely responsible for the plaintiff’s loss. On the other hand, property owners are not strictly liable for all personal injuries that occur on the abutting sidewalks, because the statute "adopts a duty and standard of care that accords with traditional tort principles of negligence and causation." Xiang Fu He v. Troon Mgt., Inc., 34 N.Y.3d at 171.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Texas Court of Appeals Conditionally Grant Petition for Writ of Mandamus to Anderson
April 25, 2011 —
Beverley BevenFlorez CDJ STAFFThe Texas Court of Appeals conditionally grant mandamus relief to Anderson Construction Company and Ronnie Anderson (collectively “Anderson”)… from the trial court in a construction defect lawsuit filed by Brent L. Mainwaring and Tatayana Mainwaring. See Tex. Prop. Code Ann. 27.001-.007 (West 2000 & Supp. 2010). Relators contend the trial court abused its discretion by compelling discovery while the case was abated by operation of law.
The Court of Appeals opinion describes what led up to the proceedings: “The Mainwarings’ original petition identified certain defects in their Anderson-constructed home. Those defects concerned the roof trusses and framing, air conditioning, mortar and masonry, exterior doors and windows, and weep holes. With respect to the five areas of defects identified in their original petition, the Mainwarings gave Anderson the statutorily required notice on January 13, 2010. After implementing agreed extensions, Anderson made an offer of settlement for the defects the Mainwarings identified in their notice. Almost eight months later, the Mainwarings filed an amended petition adding defects they had not included in their original petition and notice. The additional defects the Mainwarings included in their amended petition had not been addressed by Anderson’s offer of settlement.”
Following these events, Anderson claimed the Mainwarings did not respond in writing to their settlement offer. “Anderson filed a verified plea in abatement on December 2, 2010. In the trial court, Anderson claimed that the Mainwarings failed to respond in writing to Anderson’s settlement offer, as required by Section 27.004(b) of the RCLA. See Tex. Prop. Code Ann. 27.004(b)(1). The Mainwarings moved to compel discovery responses from Anderson. The Mainwarings alleged that they rejected Anderson’s settlement offer, and that if their response was insufficient, they contend that Anderson’s offer was rejected by operation of law on the twenty-fifth day after the Mainwarings received it. See Tex. Prop. Code Ann. 27.004(i). The Mainwarings’ motion to compel was not supported by affidavit. See Tex. Prop. Code Ann. 27.004(d)(2). On January 13, 2011, Anderson filed a verified supplemental plea in abatement. Anderson alleged that the Mainwarings failed to provide written notice concerning the newly alleged defects and complained the Mainwarings were attempting to circumvent the inspection and resolution procedure of the RCLA. Over Anderson’s objection that the lawsuit had been abated, the trial court granted the Mainwarings’ motion to compel discovery.”
After listening to both sides, the Court of Appeals offered this reasoning for their opinion: “The parties do not dispute that Anderson inspected the property before the Mainwarings alleged the existence of additional defects in their amended pleading, nor do the Mainwarings claim that Anderson has been given an opportunity to inspect the additional defects the Mainwarings identified in their amended pleadings. We conclude the trial court did not have the discretion to deny or lift the abatement until the Mainwarings established their compliance with the statute. In other words, the Mainwarings are required to provide Anderson a reasonable opportunity to inspect the additional defects identified by their amended pleading, which will allow Anderson the opportunity to cure or settle with respect to the newly identified defects.”
The Court of Appeals spoke directly on the issue of mandamus relief: “The Mainwarings contend that mandamus relief is not available because the trial court’s ruling does not prevent Anderson from making settlement offers during the discovery process. ‘An appellate remedy is “adequate” when any benefits to mandamus review are outweighed by the detriments.’ In re Prudential Ins. Co. of Am., 148 S.W.3d 124, 136 (Tex. 2004). The failure to abate a case is typically not subject to mandamus. See In re Allstate Cnty. Mut. Ins. Co., 85 S.W.3d 193, 196 (Tex. 2002) (citing Abor v. Black, 695 S.W.2d 564, 567 (Tex. 1985)). In this case, however, the case was abated by operation of law. By ignoring the statutory abatement, the trial court interfered with the statutory procedure for developing and resolving construction defect claims. See In re Kimball Hill Homes Tex., Inc., 969 S.W.2d 522, 525 (Tex. App. Houston [14th Dist.] 1998, orig. proceeding) (An appeal provides an inadequate remedy for the trial court’s failure to observe automatic abatement pursuant to the RCLA.). The benefits of mandamus review are not outweighed by the detriments of mandamus review in this case.“
In conclusion, “The trial court had no discretion to compel discovery while the case was abated, and Anderson, who has been compelled to respond to discovery during a period the case was under an automatic abatement, has no adequate remedy on appeal. Accordingly, we conditionally grant the petition for writ of mandamus. The writ will issue only if the trial court fails to vacate its order of February 3, 2011, and fails to refrain from proceeding with the case until a motion to reinstate is filed that establishes compliance with the notice and inspection requirements of the Residential Construction Liability Act.”
Read the trial court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Report to Congress Calls for Framework to Cut Post-Quake Recovery Time
February 01, 2021 —
Bruce Buckley - Engineering News-RecordEngineers and government agencies along with model building code and standard developers should work together to create a national framework more focused on earthquake resilience and post-quake recovery time, according to a report delivered to Congress last week. While current seismic codes address life safety, the report says stakeholders should also consider re-occupancy and functional recovery time, taking into account the potential impacts to a community as a whole.
Reprinted courtesy of
Bruce Buckley, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of