Major Changes in Commercial Construction Since 2009
December 11, 2013 —
CDJ STAFFA new report from Jones Lang LaSalle tracks some of the changes that the commercial building industry has seen since 2009. One important change is that financing has returned. In reviewing the report, Buildings.com notes that “commercial lending conditions are improving.” A less positive change is that construction costs have gone up, with the increase in residential construction pushing prices up in commercial construction. Green construction has gone from a luxury to something owners and developers want.
Read the court decisionRead the full story...Reprinted courtesy of
Know and Meet Your Notice Requirements or Lose Your Payment Bond Claims
May 17, 2021 —
Chris Broughton, Jones Walker LLP - ConsensusDocsTime is of the essence in the construction industry, and failing to provide timely notice of your payment bond claim can end your chance of recovery. Payment bonds guarantee payment for the subcontractors and suppliers who provide labor or materials on covered construction projects. Federal and state statutes governing payment bonds on public projects and the specific terms of non-statutory, private payment bonds have strict notice and timing requirements. Claimants who fail to provide timely notice can forfeit their chance of recovery. This article provides a brief overview of the notice requirements for payment bond claims – who has to give notice, what notice is required, and when you have to give notice.
Payment bond protection is a frequent feature in construction. Payment bonds are required on most federal construction projects of over $100,000 under the federal Miller Act. Similar state statutes, typically referred to as “Little Miller Acts,” also require payment bonds on most state and local construction projects. Owners on private projects may require their general contractor to provide a payment bond to protect the property from liens. Finally, general contractors may also require subcontractors to provide payment bonds on public or private projects.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Broughton, Jones Walker LLPMr. Broughton may be contacted at
cbroughton@joneswalker.com
Comparative Breach of Contract – The New Benefit of the Bargain in Construction?
October 26, 2020 —
Steven Hoffman - Florida Construction Law NewsAsk most Florida Construction Law practitioners, and you will likely hear that liability may not be apportioned in “pure” breach of contract cases via the Comparative Fault Act, section 768.81, Florida Statutes (the “Act”). If a material breach is a “substantial factor” in causing damages, the breaching party must answer for all damages that were reasonably contemplated by the parties when they formed the contract. Claimants argue that matters of contract should be governed strictly by the agreement, and risk can be controlled by negotiated terms, including waivers and limitations. Defendants complain that construction projects are collaborative, multi-party affairs, and strict application of contract principles leads to harsh results for relatively minor comparative fault for the same or overlapping damages.
The notion of apportioning purely economic loss contract damages based on comparative fault is not new. Since April 2006, Florida has been a “pure” comparative fault jurisdiction with limited exceptions. Prior to the amendment, tort liability for non-economic damages was purely comparative, but liability for economic damages was typically a combination of joint and several liability with an additional exposure based on comparative fault.
Read the court decisionRead the full story...Reprinted courtesy of
Steven Hoffman, Cole, Scott & KissaneMr. Hoffman may be contacted at
Steven.Hoffman@csklegal.com
Florida Representative Wants to Change Statute of Repose
December 10, 2015 —
Beverley BevenFlorez-CDJ STAFFCurrently in Florida, the ten year clock for construction defect claims typically starts ticking after the final payment is made by the owner. However, WFSU reported, Representative Keith Perry wants to change it so that the completion of the construction triggers the statute of repose.
This change “could favor the construction industry, by shifting the power to start the clock from home owners to builders,” WFSU claimed. Representative Dwight Dudley worries about “what would happen if a contractor felt she was finished but the property owner didn’t agree.”
Read the court decisionRead the full story...Reprinted courtesy of
Home Sales and Stock Price Up for D. R. Horton
February 04, 2013 —
CDJ STAFFThey call themselves "America's Builder," and in the last three months of 2013, D. R. Horton exceeded the market's predictions of how many of the homes they built would translate into sales. At the end of 2011, they had $27.7 million in earnings. At the end of last year, they saw $66.3 million in earnings. The 2011 earnings work out to 9 cents per share. Analysts were expecting 14 cents per share, but D. R. Horton delivered 20 cents per share.
The stock market responded with a 3.7% increase in the home builder's stock price, upping it by 79 cents to $22.10.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: A Specialty License May Not Be Required If Work Covered By Another License
March 07, 2011 —
Steven M. CvitanovicContractors should always be sure that they understand the licensing in any Subcontract or Prime Contract before entering into any agreement. However, on March 3, 2011, in the case of Pacific Casson & Shoring, Inc. v. Bernards Bros., Inc. 2011 Cal.App.Lexis 236, the Court of Appeal determined that if a specialty license is subsumed within another license, the specialty license may not be required.
Bernards entered into a subcontract with Pacific to excavate, backfill, grade and provide geotechnical design parameters for a hospital. The Prime Contract required the bidder to maintain a Class C-12 specialty earthwork license. However, Pacific only held a Class A general engineering license which it turns out was suspended during the performance of the work. Pacific sued Bernards for nonpayment of $544,567, but the lawsuit was dismissed because the trial court found that Pacific (1) lacked a C-12 license, and (2) Pacific’s Class A license was suspended for failure to pay an unrelated judgment. Pacific was also ordered to disgorge $206,437 in prior payments.
The Court of Appeal reversed and remanded. The Court of Appeal agreed with Pacific and held that a C-12 specialty license was not required despite the Prime Contract. The Court of Appeal found that the C-12 specialty license would have been “superfluous” since it was fully encompassed within the Class A requirements. However, the Court of Appeal also remanded the case for further
Read the full story...
Reprinted courtesy of Steve Cvitanovic of Haight Brown & Bonesteel, LLP.
Read the court decisionRead the full story...Reprinted courtesy of
Congress Addresses Homebuilding Credit Crunch
May 20, 2011 —
CDJ STAFFThe National Association of Home Builders (NAHB) reports that Representatives Gary Miller (CA), Brad Miller (NC) and twenty-nine cosponsors have put forth a bill with bipartisan support to “address the severe credit crunch for acquisition, development, and construction (AD&C) financing.” They report in addition to more than 1.4 million construction workers who have been “idled since 2006,” the housing slump has cost 3 million jobs and $145 million in wages.
NAHB reports that they worked closely with lawmakers on the bill. The association had members meet with legislators both in D.C. and in their home districts. They state that HR 1755 would help homebuilders “find the credit they need to move forward with new or existing projects.”
The bill would allow lenders to use the value upon completion when assessing loan collateral and ban the use of foreclosed or distressed sale properties in assessing values of projects. The would bill would also lessen restrictions by banking regulators, which the lead sponsors said “have hindered federal and state chartered banks and thrifts’ ability to make and maintain loans to qualified small home builders that have viable projects.”
The NAHB is urging members of Congress to cosponsor the bill and is urging the Senate to introduce a companion bill.
Read the full story…
Read HR 1755
Read the court decisionRead the full story...Reprinted courtesy of
Takeaways From Schedule-Based Dispute Between General Contractor and Subcontractor
September 09, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion out of the Southern District of Florida, Berkley Insurance Co. v. Suffolk Construction Co., Case 1:19-cv-23059-KMW (S.D.Fla. July 22, 2024), provides valuable takeaways on schedule-based disputes between a general contractor and subcontractor on a high-rise project.
In a nutshell, the general contractor’s original project schedule was abandoned due to project delays and the project wasn’t being built by any updated project schedule. The subcontractor claimed the general contractor was mismanaging the schedule putting unreasonable manpower and supervision constraints on it, i.e., it was working inefficiently. A bench trial was conducted and the Court found in favor of the subcontractor’s arguments. The Court found the general contractor had unrelated delays and that work activities were no longer methodical but, simply, piecemeal demands. The Court also rejected any inadequate manpower arguments finding the subcontract did not place any manpower requirements on the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com