Scott Van Voorhis - Engineering News-RecordA Toronto area contractor at the center of a series of delays to major projects in Ontario, including a $139-million hospital expansion, has won court protection from its creditors. The Ontario Superior Court earlier this month granted Bondfield Construction Co.’s application for protection, court records show.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENR
Eastern District of Pennsylvania Confirms Carrier Owes No Duty to Defend Against Claims for Faulty Workmanship
April 05, 2021 —
Anthony L. Miscioscia & Marianne Bradley - White and Williams LLPOn March 17, 2021, the Eastern District of Pennsylvania issued its decision in Estate Chimney & Fireplace v. IFG Companies & Burlington Insurance Company, 2021 U.S. Dist. LEXIS 50360 (E.D. Pa. March 17, 2021), finding that an insurance carrier had no duty to defend its insured where the allegations in the underlying litigation involved claims of faulty workmanship.
Estates Chimney & Fireplace, LLC (Estates Chimney) had performed inspections and replaced chase covers for a number of chimneys in a condominium complex. Chase covers are pieces of metal, which are placed over chimneys in order to keep out environmental elements. Several condominium owners sued Estates Chimney, alleging that Estates Chimney had improperly installed, then improperly replaced, their chimney caps, which caused their chimneys to cease working properly. As a result, the underlying plaintiffs allegedly incurred costs to repair or replace the chimney caps and chimneys.
Estates Chimney sought coverage from its carrier, who denied coverage based upon its determination that the claims in the underlying lawsuits arose out of faulty workmanship, which did not result in damage to the property of a third party. Estates Chimney filed a declaratory judgment action, seeking a declaration that it was entitled to coverage under the policy. Both parties moved for summary judgment, and the Eastern District ruled in favor of the carrier.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams LLP and
Marianne Bradley, White and Williams LLP
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Bradley may be contacted at bradleym@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeals Finds Arbitration Provision Incorporated by Reference Unenforceable
September 20, 2021 —
Garret Murai - California Construction Law BlogSubcontractors have gotten accustomed to incorporation clauses in their contracts. While an incorporation clause can incorporate any document, most typically, it’s the prime contract between the general contractor and the project owner. Subcontractors will sometimes even accept these documents sight unseen which can be a recipe for disaster. But not in the next case.
In Remedial Construction Services, LP v. AECOM, Inc., Case No. B303797 (June 15, 2021), the 2nd District Court of Appeal examined whether a subcontractor was bound to an arbitration provision contained in a prime contract that was incorporated by reference into the subcontractor’s contract. In this case, it was the prime contractor who was in for a surprise.
The Remedial Construction Case
In 2015, Shell Oil Products US, LLC entered into a prime contract with AECOM Technical Services, Inc. for the demolition, remediation and restoration of the Gaviota oil terminal in Goleta, California. AECOM in turn entered into a subcontract with Remedial Construction Services, LP to perform portions of the work. When AECOM refused to pay Remedial for delay costs asserted by Remedial, Remedial filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Boilerplate Contract Language on Permits could cause Problems for Contractors
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFCraig Martin on his blog Construction Contractor Advisor discusses the potential problems for a contractor that a “boilerplate contract” could cause: “A recent case revealed the problems a contractor had with permits when the contractor’s estimate contemplated an easy permitting process and compliance, but in actuality it was much, much more difficult.”
Martin cites the case Bell/Heery v. United States, where a contractor discovered that the permit process would be much more time-consuming and expensive than originally planned. When Bell/Heery asked for additional funds to cover the additional costs, the “contracting officer rejected the request, finding that Bell/Heery had assumed the risk of the permitting process and it was liable for any costs associated with the permitting process and construction methods required by the permitting process.”
“Bell/Heery appealed to the Court of Claims,” but lost the battle. The contractor had to absorb $7 million in costs to comply with the required permits.
Read the court decisionRead the full story...Reprinted courtesy of
Appeals Court Reverses Summary Judgment over Defective Archway Construction
February 10, 2012 —
CDJ STAFFA judge has ruled that a plaintiff can go forward with her suit that she was injured by a defective archway during a birthday party. A three-judge panel of the California Court of Appeals issued this ruling on January 23, 2012, in the case of Trujillo v. Cosio.
Ms. Trujillo attended a birthday party at the home of Maria Cosio and Joel Verduzco. A piñata was hung between a tree and a brick archway. Ms. Trujillo went to get candy that had fallen from the piñata, during which the archway fell on her hand. Subsequent examination of the archway showed that it had not been “properly anchored to the supporting pillars to protect the arch from falling.”
Ms. Cosio and Mr. Verduzco argued that they could not have been aware of the defective nature of the archway’s construction, as it had been built at the request of the prior property owner. The structure was constructed without building permits. Mark Burns, a civil engineer testifying for the plaintiff, said that “a reasonable property owner would have thoroughly tested the archway to ensure it was capable of withstanding such horizontal forces before allowing children to enter into the area.” Mr. Burns noted that twenty rope pulls would have been sufficient to demonstrate the structure’s instability.
The trial court rejected Mr. Burn’s statements, finding that the respondents did not have any knowledge of the defect and that a visual inspection should have sufficed. The court noted that this a triable issue, whether visual inspection suffices, or whether the property owners should have done as Mr. Burns suggested and yank a rope twenty times. The court noted that “although a jury may ultimately disagree with Burn’s opinion, it was supported by sufficient foundation and was not speculative.”
The opinion was written by Judge Flier, with Judges Rubin and Grimes concurring.
Read the court’s decison…
Read the court decisionRead the full story...Reprinted courtesy of
Arctic Fires Are Melting Permafrost That Keeps Carbon Underground
December 27, 2021 —
Eric Roston - BloombergFew things signal something's gone haywire on the planet quite like frozen land on fire. Now scientists have determined that Arctic fires, even milder ones, can reshape a landscape for decades, in ways that may make it even harder to keep global heating from eclipsing international goals.
It's mostly rising temperatures that are thawing out frozen Arctic ground but northern blazes — already increasing — are now understood to play a disproportionate role, according to a study
published last week in the journal
One Earth.
Previous research has shown that higher temperatures, drier soil and more lightning storms will lead to
more fires. That work, with the new paper, mean that “in the future we might expect to see an outsized influence on thaw from the fires that will likely increase," said Róisín Commane, a Columbia University assistant professor who studies atmospheric composition and wasn’t involved in the new study.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Roston, Bloomberg
There is No Claims File Privilege in Florida, Despite What Insurers Want You to Think
June 17, 2024 —
Susana Arce & Stephanie A. Giagnorio - Saxe Doernberger & Vita, P.C.As Florida insurers continue their attempts to narrow protections for policyholders, it is imperative - now more than ever - that insureds be well-informed and know their rights. Most recently, in Florida, insurers are attempting to weaponize the death of Senate Bill 1726 and House Bill 1287 to limit the documents disclosed to policyholders. Specifically, the proposed bill, which required insurers to disclose their claims file to policyholders, hoped to thwart insurers from utilizing “claims file privilege” to obstruct justice for policyholders and help level the playing field. The goal of the proposed bill was to promote transparency of the claim adjustment process and undercut insurers’ attempts to dodge discovery of relevant and necessary information during litigation, forcing the insurers to fully and honestly justify their basis for withholding coverage . Unfortunately for policyholders, on March 8, 2024, the proposed legislation was not passed by the Insurance and Banking Subcommittee.
While insurers want you to believe this is a significant victory and a free pass to continue withholding documents under a “claims file privilege,” this is not the case. The proposed bill merely codified current Florida law – simply put, the “claims file privilege” never existed, and still does not.
Reprinted courtesy of
Susana Arce, Saxe Doernberger & Vita, P.C. and
Stephanie A. Giagnorio, Saxe Doernberger & Vita, P.C.
Ms. Arce may be contacted at SArce@sdvlaw.com
Ms. Giagnorio may be contacted at SGiagnorio@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Hurricane Ian: Florida Expedites Road Work as Damage Comes Into Focus
October 10, 2022 —
Derek Lacey - Engineering News-RecordHurricane Ian’s devastation is coming into view days after the storm decimated southwest Florida. Work is underway to rebuild much of the state’s electrical, transportation and other infrastructure, with certain emergency road repairs expedited and restoration of power prioritized after the storm's devastation left millions in the dark and washed out roadways serving as the only access to barrier islands such as Sanibel Island and Pine Island.
Reprinted courtesy of
Derek Lacey, Engineering News-Record
Mr. Lacey may be contacted at laceyd@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of