Tred R. Eyerly – Insurance Law HawaiiThe Hawaii Intermediate Court of Appeals (ICA) vacated the trial court's issuance of summary judgment to the title insurer on a bad faith claim and remanded the case. Anastasi v. Fidelity Nat. Title Ins. Co., 2014 Haw. App. LEXIS 585 (Haw. Ct. App. Dec. 30, 2014).
Fidelity issued a title insurance policy to Anastasi insuring that Alajos Nagy had good title to the property. The policy insured Anastasi against loss in the event a mortgage on the property executed by Nagy was not enforceable. Anastasi had loaned $2.4 million to Nagy and Nagy had executed the mortgage in favor of Anastasi as security for the loan.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
U.K. Broadens Crackdown on Archaic Property Leasehold System
October 23, 2018 —
Sree Vidya Bhaktavatsalam - BloombergThe U.K. government is cracking down on what it called “unfair” leasehold practices as part of sweeping reforms to its housing system, in a move that would modernize the property market to bring it more in line with nations such as the U.S.
Initially prompted by a malpractice scandal, the proposed scope of the focus by the Ministry of Housing, Communities & Local Government has become far broader. A consultation will seek views not only on the practice of charging buyers an annual fee for owning leasehold properties -- known as ground rents -- it will review the whole process of buying, selling and property management of leasehold homes.
Read the court decisionRead the full story...Reprinted courtesy of
Sree Vidya Bhaktavatsalam, Bloomberg
Temecula Office Secures Approval for Development of 972-Acre Community on Behalf of Pulte Homes
December 27, 2021 —
Lewis BrisboisTemecula, Calif. (December 7, 2021) – Temecula Partners Kelly Black and Samuel Alhadeff, along with Associate Mark Mercer, recently represented Pulte Homes in securing unanimous approval from the Murrieta City Council and the Murrieta Planning Commission for a large-scale 972-acre development known as the Murrieta Hills development.
As described by local media including
The Press-Enterprise,
Menifee 24/7, and the
Murrieta Patch, the Murrieta Hills development will be located just south of Menifee and east of Wildomar. It will include 750 homes – 522 single-family units and 228 multi-family dwellings. The project will also include an 18-acre commercial center with plans for shopping, dining, lodging, and office space.
In addition, 619 of the 972 acres will be dedicated as natural open space and will be overseen by the Western Riverside County Regional Conservation Authority. The project will be built in three phases, with the first phase scheduled to be completed by 2023 and the final phase to be completed in 2031.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Were Quake Standards Illegally Altered for PG&E Nuclear Power Plant?
October 29, 2014 —
Beverley BevenFlorez-CDJ STAFFAn environmental group has brought a lawsuit alleging that “[f]ederal regulators secretly and illegally revised the license for California’s last nuclear power facility — PG&E’s Diablo Canyon — to mask the aging plant’s vulnerability to earthquakes,” according to SF Gate.
Friends of the Earth’s “suit claims that the Nuclear Regulatory Commission and Pacific Gas and Electric Co. last year changed a key element of the plant’s license related to seismic safety without allowing public input as required by law — or even notifying the public at all.”
However, spokesman Blair Jones claimed that “Friends of the Earth continues to mischaracterize the facts regarding seismic safety at Diablo Canyon. The facts are Diablo Canyon was built with earthquake safety at the forefront, is a seismically safe facility, and is in compliance with NRC licensing requirements.”
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Pay for Matching Siding of Insured's Buildings
December 02, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit found that the insurer was obligated to pay for siding of a building that was not damaged by hail so that it matched the replaced damaged portions of the siding. Windridge of Naperville Condominium Association v. Philadelphia Indem. Ins. Co., 2019 U.S. App. 23607 (7th Cir. Aug. 7, 2019).
A hail and wind storm damaged buildings owned by Windridge. The storm physically damaged the aluminum siding on the buildings' sought and west sides. Philadelphia Indemnity, Windridge's insurer, contended that it was only required to replace the siding on those sides. Windridge argued that replacement siding that matched the undamaged north and east elevations was no longer available, so Philadelphia had to replace the siding on all four sides of the buildings to that all of the siding matched.
Windridge sued and moved for summary judgment. The district court ruled that matching was required. The only sensible result was to treat the damage as having occurred to the building's siding as a whole.
The policy was a replacement-cost policy. Philadelphia promised to "pay for direct physical 'loss' to 'Covered Property' caused by or resulting from" the storm, with the amount of loss being "the cost to replace the lost or damaged property with other property . . . of comparable material and quality . . . and . . . used for the same purpose." The loss payment provision offered four different measures for loss, leaving Philadelphia free to choose the least expensive: (1) pay the value of the lost or damaged property; (2) pay the cost of repairing or replacing the lost or damaged property; (3) take all or any part of the property at an agreed or appraised value; or (4) repair, rebuild or replace the property with other property of like kind and quality.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Future Army Corps Rulings on Streams and Wetlands: Changes and Delays Ahead
November 06, 2023 —
Mark Sudol - Engineering News-RecordNew regulations published by the U.S. Environmental Protection Agency and U.S. Army Corps of Engineers dramatically reduce federal protections of previously regulated streams and wetlands. This change will lead to further controversy and litigation as the legal terms are applied to physical features on the ground leading to conflicting interpretations by the regulated public, environmentalists and federal agencies.
Reprinted courtesy of
Mark Sudol, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Hail Damage Requires Replacement of Even Undamaged Siding
February 05, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a dispute over the property policy's requirement that lost or damaged property be repaired or replaced, the Minnesota Supreme Court held that the policy language called for replacement of undamaged siding panels to obtain a color match. Cedar Bluff Townhome Condominium Ass'n, Inc. v. Am. Family Mut. Ins. Co., 2014 Minn. LEXIS 661 (Minn. Dec. 17, 2014).
During a hail storm, all 20 of Cedar Bluff's buildings sustained some damage. The roofs on all of the buildings needed to be replaced, and at least one siding panel on each building sustained damage. Eleven of the 20 buildings had three or fewer damaged panels. At the time of the hail storm, the siding was approximately 11 years old, and the color of the panels had faded. Replacement panels were available, but not in the same color.
Cedar Bluff submitted a claim under its business owners' policy to American Family. The policy obligated the insurer to pay for "direct physical loss of or damage to Covered Property at the premises . . . caused by or resulting from any Covered Cause of Loss." "Covered Property" was broadly defined in the policy to include buildings at the premises.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Goldberg Segalla Welcomes William L. Nimick
February 07, 2022 —
Goldberg Segalla LLP(RALEIGH, N.C.)—Goldberg Segalla added William L. Nimick to the firm's Construction Litigation and Counsel group in Raleigh. Nimick was previously with The Law Offices of Stephen R. Paul in Raleigh.
Nimick is an experienced litigator who focuses his practice on counseling and defending corporate entities, insurers, contractors, and subcontractors in a range of liability claims, including those alleging construction defect, personal injury, property damage, premises liability, and more. Nimick draws on a background in civil litigation, personal injury and wrongful death, workers' compensation, and subrogation. He has handled subrogation claims across North Carolina, including construction defects, motor vehicle accidents, product liability lawsuits, and large fire losses.
Nimick earned his bachelor's degree at the University of North Carolina at Wilmington and his juris doctor at the Campbell University Norman Adrian Wiggins School of Law.
About Goldberg Segalla
Goldberg Segalla is a national civil litigation firm with more than 20 offices in 10 states spanning major metro markets across the U.S., providing strategic coverage wherever our clients do business. As a firm of experienced litigators and trial attorneys, Goldberg Segalla's capabilities span business and commercial disputes, employment and labor, insurance coverage, product liability, and more. Today, our more than 400 attorneys are trusted counselors to public and private clients in key sectors and industries including construction and energy, transportation, manufacturing, retail and hospitality, and insurance. To learn more, visit goldbergsegalla.com or follow us on
LinkedIn,
Facebook, and
Twitter.
Read the court decisionRead the full story...Reprinted courtesy of